Re: Construction Of 6self-contain Hostel Frm Start To Finish With Cost Saving Advice by simplynace(m): 10:09am On Nov 14, 2017 |
saydfact: Thanks... Would contact you in due time |
Re: Construction Of 6self-contain Hostel Frm Start To Finish With Cost Saving Advice by Nobody: 4:18pm On Nov 14, 2017 |
Are you in need of bamboo poles in large quantities for your building construction at an affordable price? Look no further,contact Ayo 08062166345 Or send a mail to ayodeleolaniyi@gmail.com |
Re: Construction Of 6self-contain Hostel Frm Start To Finish With Cost Saving Advice by ayinba1(f): 2:45am On Nov 18, 2017 |
saydfact: Hello OP, I am currently working on a project in Lagos around Badagry. I would like an estimate for your bore hole and septic tank and soakaway. I just want to use it to estimate how much I'll need for these |
Re: Construction Of 6self-contain Hostel Frm Start To Finish With Cost Saving Advice by saydfact(m): 9:52am On Nov 18, 2017 |
ayinba1: Hi.... I pray the project gets completed successfully... Now back to your requests. Bore Hole.... The bore hole coat depends on location, most time it's better to contract borehole jobs to pple in that locality offering that service.. . If you bring a professional borehole man from another locality.. He wld also meet his colleague in that region to ask questions.... So locate Sm1 there so you can have better assurance. Septic tank and soak away - There is a link on my signature where I've explained how to calculate this... Please check it out... (the size of your septic and nature of soil cld be a varying factor) Goodluck..... |
Re: Construction Of 6self-contain Hostel Frm Start To Finish With Cost Saving Advice by ayinba1(f): 5:31pm On Nov 18, 2017 |
saydfact: Thank you for your response I clicked on your signature to check the calculations. The area is around Okoafo off Lag -Badagry exp way. My initial post switched some words. I only wanted to estimate based on what figures you provide for me. |
Re: Construction Of 6self-contain Hostel Frm Start To Finish With Cost Saving Advice by saydfact(m): 5:41pm On Nov 18, 2017 |
ayinba1: Sent you a mail... |
Re: Construction Of 6self-contain Hostel Frm Start To Finish With Cost Saving Advice by azimulthal: 8:53pm On Nov 22, 2017 |
Thank you very much OP, Saydfact. I need to really appreciate you for this educating post. I learnt a lot from this. I joined Nairaland solely because of this beneficial post of yours tonight even thought I have been a guest visitors of NL since 2008. I never see the need considering the extent of name callings and abuse that I have been witnessing on this platform. Mature minds like you are not in abundance on NL. Please I'll need your Email address. About to start a construction project and I will like that we talk. My Email is sulaimonabdulaziz1@gmail.com. Thanks bro. |
Re: Construction Of 6self-contain Hostel Frm Start To Finish With Cost Saving Advice by azimulthal: 8:58pm On Nov 22, 2017 |
Thank you very much OP, Saydfact. I need to really appreciate you for this educating post. I learnt a lot from this. I joined Nairaland solely because of this beneficial post of yours tonight even though I have been a guest visitor of NL since 2008. I never see the need to register considering the extent of name callings and abuse that I have been witnessing on this platform. Mature minds like you are not in abundance on NL. Please I'll need your Email address. About to start a construction project and I will like that we talk. My Email is sulaimonabdulaziz1@gmail.com. Thanks bro. |
Re: Construction Of 6self-contain Hostel Frm Start To Finish With Cost Saving Advice by saydfact(m): 9:04pm On Nov 22, 2017 |
azimulthal: Woah... I'm humbled to say the least..... I'll send you a mail, I guess u wld receive it b4 reading this reply... |
Re: Construction Of 6self-contain Hostel Frm Start To Finish With Cost Saving Advice by tomsy2: 10:27am On Dec 23, 2017 |
Good morning Sir, Oga saydfact. I need some advice. My mum is looking at selling off a property because of some embarrassing financial issues. The property is located in a good government estate in Ibadan. It was allocated as a double plot 120/100 but roughly subdivided by us into two. Note that the subdivision has not been approved but we erected a dividing wall and the both sides have completed buildings on them. My family lives in one of the buildings. Now that the property is up for sale all the prospective buyers are wary of the issue of subdivision despite our assurances that it would be approved for them to get their own title. They would rather buy the whole. We are contemplating selling the whole but afraid that after selling and settling the issues on ground the balance won't be enough to build another 3 bedroom bungalow for us to move into. We have offers for N22 million which is very low. A fair forced sale should be between N25m to N28m. Similar properties in the area have rejected N 30m offers. If we could get N25m for it and she settles issues with N15m would the remaining N10m less agents commission build something small plus cost of land? Please advice urgently. She's killing herself with HBP and my siblings and I are of the opinion that she should sell. |
Re: Construction Of 6self-contain Hostel Frm Start To Finish With Cost Saving Advice by saydfact(m): 4:02pm On Dec 23, 2017 |
tomsy2: Hi, 10m would not be enough to get you a new land, and build back - ideally, yes 10 min might build you a decent 3 bedroom flat but realistically, it wont considering how developed that area has becomee.... I'll advice you wait a bit more for your buyer and ignore those trying to eject you out of your property stylishly. WHY NOT GET ALL THE RELEVANT PAPERS FOR THE SUBDIVISION AND THEN SELL AFTERWARD (Cost of acquiring those papers can be added to the initial cost) goodluck |
Re: Construction Of 6self-contain Hostel Frm Start To Finish With Cost Saving Advice by tomsy2: 12:03am On Dec 24, 2017 |
saydfact:I've modified your post with responses. Thanks for taking the time to respond Sir. I'm indebted. |
Re: Construction Of 6self-contain Hostel Frm Start To Finish With Cost Saving Advice by saydfact(m): 7:01am On Dec 24, 2017 |
tomsy2: YES, i expected you would get land in a cheaper region - if the money is managed well with a lot of discipline; good (you know how money is, once its in hand; diff things pop up) why not as suggested let the buyer have the original documents - then invite a lawyer to draft an agreement that he holds the paper for xyz reasons and wld be required to to return them once his papers are ready. Lastly - If all options fail - Follow your mind; when there is health, there is wealth..... HEALTH FIRST. Thanks |
Re: Construction Of 6self-contain Hostel Frm Start To Finish With Cost Saving Advice by folmus: 7:43am On Dec 25, 2017 |
Daboomb: Sometimes, I just want go do engineering when I see your comments 1 Like |
Re: Construction Of 6self-contain Hostel Frm Start To Finish With Cost Saving Advice by bvc(m): 4:34pm On Jan 01, 2018 |
Ready to paint your building? - Get a free quotation that is proven to reduce cost - Select from a variety of local and foreign paint products - Locate certified painters around you for that impeccable finishing - Get discounts for all paint purchases, just request for a coupon code. https://www.youtube.com/watch?v=lLNIgdTMRMM www.expertpaintadvice.com.ng |
Re: Construction Of 6self-contain Hostel Frm Start To Finish With Cost Saving Advice by saydfact(m): 5:56pm On Feb 16, 2018 |
Hi All, Please follow my latest article here >> https://www.nairaland.com/4351676/choosing-right-foundation-project-type#65115752 also contact me for your design & 3ds job... 1 Like |
Re: Construction Of 6self-contain Hostel Frm Start To Finish With Cost Saving Advice by saydfact(m): 8:39am On Apr 14, 2018 |
japhethGold: Morning - Remember your plan, hope its in progress? |
Re: Construction Of 6self-contain Hostel Frm Start To Finish With Cost Saving Advice by booz(m): 9:51am On Apr 28, 2018 |
saydfact: Bros, considering the weights of the precast lintels and possibility of breaking, how did you get the up. Also, to be sure, it looks like you line the German floor with polythene, that should suffice for non-sticking, right? |
Re: Construction Of 6self-contain Hostel Frm Start To Finish With Cost Saving Advice by saydfact(m): 9:19am On May 02, 2018 |
booz: 100mm thick precast isn't small - just allow it set well for about a week before lifting them and Yes, the polythene / cement bag is to prevent them sticking to the surface...... Goodluck |
Re: Construction Of 6self-contain Hostel Frm Start To Finish With Cost Saving Advice by enyiulo: 12:45am On Oct 15, 2018 |
16rooms hotel how much will it cost to build it |
Re: Construction Of 6self-contain Hostel Frm Start To Finish With Cost Saving Advice by saydfact(m): 12:10pm On Oct 18, 2018 |
enyiulo: you can only get an accurate response when their is a plan and location |
Re: Construction Of 6self-contain Hostel Frm Start To Finish With Cost Saving Advice by Babs612000(m): 1:19am On Oct 28, 2018 |
saydfact:please like how much did you spend on the wiring only, if possible list of the wires. |
Re: Construction Of 6self-contain Hostel Frm Start To Finish With Cost Saving Advice by saydfact(m): 7:04am On Oct 28, 2018 |
Babs612000: We did surface wiring so it wasn't expensive at all..... Conduit wiring are usually more expensive but I think we still spent close to 400k on tbaf... Including payment to PHCH, pole and related expenses..... Thanks |
Re: Construction Of 6self-contain Hostel Frm Start To Finish With Cost Saving Advice by Babs612000(m): 9:40am On Oct 29, 2018 |
saydfact:okay many thanks. |
Re: Construction Of 6self-contain Hostel Frm Start To Finish With Cost Saving Advice by saydfact(m): 2:54pm On Dec 01, 2018 |
Happy new month to all our esteemed clients, more finances to your bank account this month and COMPLIMENTS OF THE SEASON. |
Re: Construction Of 6self-contain Hostel Frm Start To Finish With Cost Saving Advice by buddie(m): 11:15am On Dec 18, 2018 |
Hello chief, The precast lintel was done for all openings (windows and doors) alone? No chain lintel done around the building either? This your cast lintel design can't incorporate paraphet Right? How popular is this proposed lintel design, cos it would largely save a lot of cost really sha saydfact: |
Re: Construction Of 6self-contain Hostel Frm Start To Finish With Cost Saving Advice by saydfact(m): 6:13am On Dec 19, 2018 |
buddie: LINTEL is a LINTEL sir - A bridge to allow you continue your blockwork - it can be done in wood, iron, concrete (our fathers used wood more).. For Roof Parapet, you would be required to do a beam to tie all elements together..... ON WHAT YOU REFERRED TO AS A CHAIN LINTEL - I call it A WASTE OF MONEY (my opinion).... if its a bungalow its a luxury not a necessity, if its a storey building its a waste because you wld have a beam.. Thanks 1 Like |
Re: Construction Of 6self-contain Hostel Frm Start To Finish With Cost Saving Advice by buddie(m): 7:56am On Dec 20, 2018 |
Ok now..Quite a number of builders on this forum also agree with what you said below really. And again thank you. saydfact: |
Re: Construction Of 6self-contain Hostel Frm Start To Finish With Cost Saving Advice by Larminess: 10:29am On Dec 20, 2018 |
saydfact: |
Re: Construction Of 6self-contain Hostel Frm Start To Finish With Cost Saving Advice by Omopasito: 2:56pm On Dec 20, 2018 |
@saydfact, Well-done. Can I get your mail address. Mine is theo_igwiro@yahoo.ca |
Re: Construction Of 6self-contain Hostel Frm Start To Finish With Cost Saving Advice by saydfact(m): 2:43pm On Jan 08, 2019 |
Omopasito: sorry i've been away to the moon and back CADSOLUTIONS2009@GMAIL.COM Thanks |
Re: Construction Of 6self-contain Hostel Frm Start To Finish With Cost Saving Advice by Olassab: 6:51pm On Jan 18, 2019 |
Great work, very detailed, please could you give me an estimate cost for foundation and concreting for a 2 bedroom bungalow, land is pretty much dry thanks |
(1) (2) (3) (4) (5) (6) (7) (8) (9) (10) (Reply)
7-Storey Building Collapses In Banana Island, Workers Trapped / What Is That Diabolical Sign To Look Out For While Renting An Apartment? / Having Issues With My Landlady, I Need Your Honest Advise
(Go Up)
Sections: politics (1) business autos (1) jobs (1) career education (1) romance computers phones travel sports fashion health religion celebs tv-movies music-radio literature webmasters programming techmarket Links: (1) (2) (3) (4) (5) (6) (7) (8) (9) (10) Nairaland - Copyright © 2005 - 2024 Oluwaseun Osewa. All rights reserved. See How To Advertise. 76 |