PropertiesRe: BITSWORKS PROJECT MEMOIRS: Construction Of 4 Units Of 2 Bedrooms Flat Mowo Nla by BITSWORKS(op): 4:51pm On Jul 20, 2018
Compacting of the backfilling ongoing. We initially planned to cast the german floor Thursday/Friday but I was not too pleased with the compacting done and told them to leave it for a day or two to get the rain to fall on it. That way, the backfilling compacts better and we top it off.

Casting of the german floor is shifted to next week, we should be able to lay the DPM and reinforcements mat tomorrow, Saturday.
PropertiesRe: BITSWORKS PROJECT MEMOIRS: Construction Of 4 Units Of 2 Bedrooms Flat Mowo Nla by BITSWORKS(op):
Backfilling task accomplished at last. We used a total of 230 tons laterite sand to backfill.

It was a slow process due to the incessant rain that affected the dump trucks loading and also the backfilling work.

PropertiesRe: BITSWORKS PROJECT MEMOIRS: Construction Of 4 Units Of 2 Bedrooms Flat Mowo Nla by BITSWORKS(op): 6:14am On Jul 17, 2018
Backfilling almost complete, just a tiny bit more. After 220 tons, it looks like the trenches is swallowing the backfill. We will require just another 10 tons which we won't use up.

PropertiesRe: BITSWORKS PROJECT MEMOIRS: Construction Of 4 Units Of 2 Bedrooms Flat Mowo Nla by BITSWORKS(op): 4:32am On Jul 14, 2018
Aerial pictures of the german floor reinforcement mat work. Shot by BITSWORKS-1.

PropertiesRe: BITSWORKS PROJECT MEMOIRS: Construction Of 4 Units Of 2 Bedrooms Flat Mowo Nla by BITSWORKS(op):
200 tons of backfilling dumped and filled and just a little more to go. We definitely need another 20 tons and we should be able to call it a wrap.

PropertiesRe: BITSWORKS PROJECT MEMOIRS: Construction Of 4 Units Of 2 Bedrooms Flat Mowo Nla by BITSWORKS(op):
Laying of the german floor mat reinforcements, all set for casting but we have to hold on and complete the second half backfilling, compacting and reinforcements work.

PropertiesRe: BITSWORKS PROJECT MEMOIRS: Construction Of 4 Units Of 2 Bedrooms Flat Mowo Nla by BITSWORKS(op): 2:32pm On Jul 10, 2018
Laying of the damp proof membrane (DPM) on the compacted backfilling.

PropertiesRe: BITSWORKS PROJECT MEMOIRS: Construction Of 4 Units Of 2 Bedrooms Flat Mowo Nla by BITSWORKS(op): 1:38pm On Jul 09, 2018
Half done, half to go. Compacting of the backfilled half in progress.

Rain has actually delayed this phase of the project but it also helped in solidifying the backfilling.

PropertiesRe: BITSWORKS PROJECT MEMOIRS: Construction Of 4 Units Of 2 Bedrooms Flat Mowo Nla by BITSWORKS(op): 8:31pm On Jul 07, 2018
Backfilling still ongoing, 180 tons dumped so far. Half of the span of the building almost done, at the stair section where we have a drop down level.

PropertiesRe: BITSWORKS PROJECT MEMOIRS: Construction Of 4 Units Of 2 Bedrooms Flat Mowo Nla by BITSWORKS(op): 10:36am On Jul 06, 2018
We received a dump of 20 tons backfilling yesterday and another 20 tons this morning making a total of 160 tons dumped so far. Let's see how far we can go with this and how much backfilling will be needed to complete the task.
PropertiesRe: REPLAYNG: Office Fit-Out Project Victoria Island Lagos by BITSWORKS(op): 12:54pm On Jul 04, 2018
The company branding stipulated grey color for the rug, no pattern nor stripes.

PropertiesRe: BITSWORKS PROJECT MEMOIRS: Construction Of 4 Units Of 2 Bedrooms Flat Mowo Nla by BITSWORKS(op): 11:51am On Jul 04, 2018
Backfilling still on hold due to bad road conditions to the Laterite site. We have lost 2 working days and today possibly will make it 3 days but am hoping for the best.
PropertiesRe: REPLAYNG: Office Fit-Out Project Victoria Island Lagos by BITSWORKS(op): 9:43am On Jul 04, 2018
The next stage is the flooring work which involves laying of rugs and wood vinyl floor.

Underlay for the rugs being laid.

PropertiesRe: BITSWORKS PROJECT MEMOIRS: Construction Of 4 Units Of 2 Bedrooms Flat Mowo Nla by BITSWORKS(op): 5:16pm On Jul 03, 2018
seunben:
sorry for the delay bro. How much are you paying for labour for each trip to do the backfilling.
For each 20 tons trip its N6,000 but I was able to negotiate to N5,000. For 10 tons its N3,000. They will rent wheel barrows and shovels themselves.
PropertiesRe: BITSWORKS PROJECT MEMOIRS: Construction Of 4 Units Of 2 Bedrooms Flat Mowo Nla by BITSWORKS(op): 8:00am On Jul 02, 2018
Backfilling on hold temporarily due to the incessant rain and bad road. The dump trucks will not be able to access the filling sand location.
PropertiesRe: BITSWORKS PROJECT MEMOIRS: Construction Of 4 Units Of 2 Bedrooms Flat Mowo Nla by BITSWORKS(op): 4:27am On Jun 30, 2018
After 120 tons of backfilling, we still have this much to do. By my rough calculation, we are looking at another 80 tons, hopefully no more than that.

PropertiesRe: BITSWORKS PROJECT MEMOIRS: Construction Of 4 Units Of 2 Bedrooms Flat Mowo Nla by BITSWORKS(op): 4:20am On Jun 30, 2018
Backfilling still ongoing at a steady pace, 120 tons dumped and we are still a long way from completion.

PropertiesRe: BITSWORKS PROJECT MEMOIRS: Construction Of 4 Units Of 2 Bedrooms Flat Mowo Nla by BITSWORKS(op): 8:46pm On Jun 28, 2018
Backfilling still ongoing, 100 tons dumped so far, 80 tons have been backfilled already. Today's dumping delivery was late in the day and we pushed the backfilling till tomorrow.

PropertiesRe: BITSWORKS PROJECT MEMOIRS: Construction Of 4 Units Of 2 Bedrooms Flat Mowo Nla by BITSWORKS(op): 8:38pm On Jun 28, 2018
seunben:
Good job as usual. Please what's the size of the building as I am waiting patiently to know how much tons was used to fill the building. it is a learning process for me.
Thanks for the good words.

The size of the building is L-23.759m, B-9.576m. As of today 100 tons (5 trips of 20tons truck) of filling has been dumped. Its looking like we will still do between another 40-80 tons but not more than that. Please take into cognizance the number of coaches laid. We have 4 coaches in the front unit and 5 coaches at the rear unit.

You can also calculate the volume (cu3) of the trenches and convert to tonnages. Depending on the type of soil, the multiplying factor is different if its dry sand or moist sand.
PropertiesRe: BITSWORKS PROJECT MEMOIRS: Construction Of 4 Units Of 2 Bedrooms Flat Mowo Nla by BITSWORKS(op): 10:46pm On Jun 27, 2018
Backfilling still ongoing, 60 tons of filling dumped so far.

PropertiesRe: BITSWORKS PROJECT MEMOIRS: Construction Of 4 Units Of 2 Bedrooms Flat Mowo Nla by BITSWORKS(op): 1:11pm On Jun 27, 2018
Backfilling of foundation trenches ongoing.

PropertiesRe: BITSWORKS PROJECT MEMOIRS: Construction Of 4 Units Of 2 Bedrooms Flat Mowo Nla by BITSWORKS(op): 6:23am On Jun 27, 2018
Aerial pictures of the substructure work. Shot by BITSWORKS-1.

PropertiesRe: BITSWORKS PROJECT MEMOIRS: Construction Of 4 Units Of 2 Bedrooms Flat Mowo Nla by BITSWORKS(op):
Substructure work concluded, getting set for the backfilling and damp proof membrane.

PropertiesRe: BITSWORKS PROJECT MEMOIRS: Construction Of 4 Units Of 2 Bedrooms Flat Mowo Nla by BITSWORKS(op): 5:06am On Jun 26, 2018
Plumbing work done at the substructure level before backfilling starts.

PropertiesRe: BITSWORKS PROJECT MEMOIRS: Construction Of 4 Units Of 2 Bedrooms Flat Mowo Nla by BITSWORKS(op):
Casting of the substructure columns ongoing.

PropertiesRe: BITSWORKS PROJECT MEMOIRS: Construction Of 4 Units Of 2 Bedrooms Flat Mowo Nla by BITSWORKS(op): 8:27am On Jun 24, 2018
Wrapping up the front unit foundation block setting.

PropertiesRe: REPLAYNG: Office Fit-Out Project Victoria Island Lagos by BITSWORKS(op): 5:29am On Jun 23, 2018
More finishing pictures.

PropertiesRe: REPLAYNG: Office Fit-Out Project Victoria Island Lagos by BITSWORKS(op): 5:24am On Jun 23, 2018
The open office setting now taking shape and making sense.

PropertiesRe: BITSWORKS PROJECT MEMOIRS: Construction Of 4 Units Of 2 Bedrooms Flat Mowo Nla by BITSWORKS(op): 5:17am On Jun 23, 2018
Still ongoing.

PropertiesRe: General Topic Thread-To Discuss Anything And Everything in Building Construction by BITSWORKS: 5:06am On Jun 23, 2018
mufutau55:
Tempered glass was used. Is that ordinary or safety?
Actually I would have preffered those hard chinese plastic o.

Hajji M.
Also known as safety glass, tempered glass breaks down into smaller pieces that have less sharp edges. This is possible because during the annealing process the glass is cooled down slowly, which makes the glass much stronger, & impact / scratch resistant compared to non-treated glass.
PropertiesRe: The Painting Pictures Of Hajji Mufutau's Kobo-kobo Project by BITSWORKS: 5:01am On Jun 23, 2018
Hajj M, this is majestic and beautiful. Well done sir. All on point!
PropertiesRe: BITSWORKS PROJECT MEMOIRS: Construction Of 4 Units Of 2 Bedrooms Flat Mowo Nla by BITSWORKS(op):
Starting work on the front unit foundation.