Properties › Re: BITSWORKS PROJECT MEMOIRS: Construction Of 4 Units Of 2 Bedrooms Flat Mowo Nla by BITSWORKS(op): 1:20pm On Jun 22, 2018 |
Wrapping up the rear unit foundation work.
|
Properties › Re: BITSWORKS PROJECT MEMOIRS: Construction Of 4 Units Of 2 Bedrooms Flat Mowo Nla by BITSWORKS(op): 5:01pm On Jun 21, 2018 |
Foundation block setting....slow and steady progress.
|
Properties › Re: BITSWORKS PROJECT MEMOIRS: Construction Of 4 Units Of 2 Bedrooms Flat Mowo Nla by BITSWORKS(op): 3:25pm On Jun 21, 2018*. Modified: 4:28pm On Jun 21, 2018 |
Foundation block setting in progress.
|
Properties › Re: BITSWORKS PROJECT MEMOIRS: Construction Of 4 Units Of 2 Bedrooms Flat Mowo Nla by BITSWORKS(op): 11:44am On Jun 21, 2018 |
First coach block setting for the foundation is laid on the footing(blinding)
|
Properties › Re: REPLAYNG: Office Fit-Out Project Victoria Island Lagos by BITSWORKS(op): 5:44am On Jun 21, 2018 |
The frameless glass partitioning gradually taking shape.
|
Properties › Re: BITSWORKS PROJECT MEMOIRS: Construction Of 4 Units Of 2 Bedrooms Flat Mowo Nla by BITSWORKS(op): 5:26am On Jun 21, 2018 |
Aerial pictures of the foundation layout. Shots by BITSWORKS-1.
|
Properties › Re: BITSWORKS PROJECT MEMOIRS: Construction Of 4 Units Of 2 Bedrooms Flat Mowo Nla by BITSWORKS(op): 3:49pm On Jun 20, 2018 |
Wrapping up with the foundation footing. Due to the topography of the land, we had to step the foundation footing.
|
Properties › Re: BITSWORKS PROJECT MEMOIRS: Construction Of 4 Units Of 2 Bedrooms Flat Mowo Nla by BITSWORKS(op): 1:44pm On Jun 20, 2018 |
More blinding pictures.
|
Properties › Re: BITSWORKS PROJECT MEMOIRS: Construction Of 4 Units Of 2 Bedrooms Flat Mowo Nla by BITSWORKS(op): 12:08pm On Jun 20, 2018 |
Foundation footing (blinding) casting in progress.
|
Properties › Re: BITSWORKS PROJECT MEMOIRS: Construction Of 4 Units Of 2 Bedrooms Flat Mowo Nla by BITSWORKS(op): 2:40pm On Jun 19, 2018*. Modified: 7:07pm On Jun 19, 2018 |
Aerial pictures of the foundation excavations. Shots by BITSWORKS-1.
|
Properties › Re: BITSWORKS PROJECT MEMOIRS: Construction Of 4 Units Of 2 Bedrooms Flat Mowo Nla by BITSWORKS(op): 1:16pm On Jun 19, 2018*. Modified: 2:37pm On Jun 19, 2018 |
Setting-out and excavations of the foundation started on the 18th of June 2018.
|
Properties › Re: REPLAYNG: Office Fit-Out Project Victoria Island Lagos by BITSWORKS(op): 1:55pm On Jun 15, 2018 |
Frameless glass partitioning work.
|
Properties › Re: BITSWORKS PROJECT MEMOIRS: Construction Of 4 Units Of 2 Bedrooms Flat Mowo Nla by BITSWORKS(op): 8:24am On Jun 15, 2018*. Modified: 10:29am On Jun 15, 2018 |
Block moulding ongoing.
|
Properties › Re: REPLAYNG: Office Fit-Out Project Victoria Island Lagos by BITSWORKS(op): 12:29pm On Jun 12, 2018*. Modified: 2:09pm On Jun 12, 2018 |
Frameless glass partitioning using 10mm tempered clear glass fixed with appropriate accessories.
|
Properties › Re: BITSWORKS PROJECT MEMOIRS: Construction Of 4 Units Of 2 Bedrooms Flat Mowo Nla by BITSWORKS(op): 12:21pm On Jun 12, 2018 |
Site has been cleared and the moulding of 9" blocks have commenced.
|
Properties › Re: BITSWORKS PROJECT MEMOIRS: Construction Of 4 Units Of 2 Bedrooms Flat Mowo Nla by BITSWORKS(op): 3:23pm On Jun 08, 2018*. Modified: 4:20pm On Jun 08, 2018 |
We are back to site this month to continue the project.
Land clearing and grubbing started today in preparation for the foundation work starting next week.
The client also prefers blocks moulded on site so we will be mobilizing our block making equipment to site this weekend to start moulding blocks.
|
Properties › Re: REPLAYNG: Office Fit-Out Project Victoria Island Lagos by BITSWORKS(op): 4:31pm On Jun 01, 2018 |
The first task was to mark out on the bare floor an exact representation of the floor plan design.
Once we measured out all the exact dimensions, work on the dry wall started. Dry wall is constructed using gypsum boards, U-channels and C-channels. The frame is constructed using the U-channel on the floor and ceiling horizontally. The C-channel is used as the supporting framework vertically at 600mm interval for a solid frame.
|
Properties › Re: REPLAYNG: Office Fit-Out Project Victoria Island Lagos by BITSWORKS(op): 4:20pm On Jun 01, 2018 |
The fit-out project was divided into 4 phases 1. Partition and Dry wall 2. Flooring - Rug and Vinyl wooden floor 3. Electrical wiring and fittings 4. Furniture's
The I.T part of the project was given to a company with that as their core skill.
We started with the dry wall and all glass partition using frameless glass with a thickness of 10mm.
|
Properties › Re: Bitsworks Project Memoirs: Construction Of A Church Auditorium Surulere Lagos by BITSWORKS(op): 3:52pm On Jun 01, 2018*. Modified: 4:42pm On Jun 01, 2018 |
Block setting, beams and window arches.
|
Properties › Re: Bitsworks Project Memoirs: Construction Of A Church Auditorium Surulere Lagos by BITSWORKS(op): 8:09am On May 30, 2018 |
Block setting on the first floor level.
|
Properties › Re: Bitsworks Project Memoirs: Construction Of A Church Auditorium Surulere Lagos by BITSWORKS(op): 7:32am On May 30, 2018 |
Casting of the columns and lintels.
|
Properties › Re: Scaffolds For Rent/lease : Galvanized Steel Pipes Scaffold For Building Works by BITSWORKS(op): 7:16am On May 30, 2018 |
mufutau55: Oga Seyi... Wow! Where have you been hiding?
Hajji M. LOL...its work sir but am a bit free to write again. |
Properties › Re: Bitsworks Project Memoirs: Construction Of A Church Auditorium Surulere Lagos by BITSWORKS(op): 10:06am On May 26, 2018 |
Block setting to lintel level.
|
Properties › Re: REPLAYNG: Office Fit-Out Project Victoria Island Lagos by BITSWORKS(op): 9:23am On May 26, 2018 |
We engaged with the client for about a month before mobilization to site deciding on the spatial design, spatial circulation/flow, branding, color scheme, material scheme and interior ambience.
The company is an international brand and already had a branding scheme for everything from Walls, Furnitures, Blinds, Signage, Flooring, Partition, Glass privacy e.t.c. |
Properties › Re: REPLAYNG: Office Fit-Out Project Victoria Island Lagos by BITSWORKS(op): 7:49pm On May 25, 2018 |
Spatial layout/plan.
|
Properties › Re: REPLAYNG: Office Fit-Out Project Victoria Island Lagos by BITSWORKS(op): 7:34pm On May 25, 2018*. Modified: 7:51pm On May 25, 2018 |
OFFICE FIT-OUT FOR CLIENT IN VICTORIA ISLAND.
Brief : The client just leased a 156.90sqm space in a new serviced office complex in VI and awarded us the contract of fitting out the bare space.
The office complex is a beauty to behold and the leased space has a water front view with enough day lighting.
|
Properties › Re: Bitsworks Project Memoirs: Construction Of A Church Auditorium Surulere Lagos by BITSWORKS(op): 6:53pm On May 24, 2018*. Modified: 7:36am On May 25, 2018 |
Regular checks with a plumb, line and range ensures we maintain a straight and firm blockwork course.
|
Properties › Re: Bitsworks Project Memoirs: Construction Of A Church Auditorium Surulere Lagos by BITSWORKS(op): 6:09pm On May 24, 2018 |
Block setting.
|
Properties › Re: Bitsworks Project Memoirs: Construction Of A Church Auditorium Surulere Lagos by BITSWORKS(op): 5:55pm On May 24, 2018 |
Block setting. The first coach run has to be properly bedded and plumb right to have a straight and consistent course.
|
Properties › Re: Bitsworks Project Memoirs: Construction Of A Church Auditorium Surulere Lagos by BITSWORKS(op): 5:51pm On May 24, 2018 |
Blockwork using 9inches sandcrete blocks as shell on the steel stanchions.
|
Properties › Re: Bitsworks Project Memoirs: Construction Of A Church Auditorium Surulere Lagos by BITSWORKS(op): 9:25am On May 24, 2018 |
Steel stanchions installation completed.
Aerial shots of steel stanchions taken by our DJI Phantom drone.
|
Properties › Re: Bitsworks Project Memoirs: Construction Of A Church Auditorium Surulere Lagos by BITSWORKS(op): 7:28am On May 24, 2018 |
EndiaSami: Welldone o. Oga bitsworks.... Welcome, we don miss u sha. Thank you, missed you too my brother. |