Properties › Re: BITSWORKS PROJECT MEMOIRS: Construction Of 4 Units Of 2 Bedrooms Flat Mowo Ikrd by BITSWORKS(op): 6:03am On Mar 31, 2017 |
chuksjuve: Nice one...keep us updated..
for your landscape and beautification, kindly contact us by checking our profile for more details..
keep it up Noted sir. Thanks for the kind words. |
Properties › Re: BITSWORKS PROJECT MEMOIRS: Construction Of 4 Units Of 2 Bedrooms Flat Mowo Ikrd by BITSWORKS(op): 5:57am On Mar 31, 2017 |
More block setting work pictures.
|
Properties › Re: BITSWORKS PROJECT MEMOIRS: Construction Of 4 Units Of 2 Bedrooms Flat Mowo Ikrd by BITSWORKS(op): 8:00pm On Mar 30, 2017 |
Block setting of the foundation, we are using 9" vibrated blocks .
|
Properties › BITSWORKS PROJECT MEMOIRS: Construction Of 4 Units Of 2 Bedrooms Flat Mowo Ikrd by BITSWORKS(op): 7:52pm On Mar 30, 2017 |
BITSWORKS Nigeria is a multi-discipline construction company comprising of architects, builders, civil engineers and interior designers.
We currently have a brief for a client to construct 4 units of 2 bedrooms flats on a plot of land in Mowo-Kekere, Ikorodu. There is an existing bungalow in the land already but it is a fairly flat terrain.
We will share the floor plan, elevations and 3D views once we have finalized on the design and permission has been given by the client.
Size of land - 640 sqm Total area of building - 168.4sqm
Estimated budget for construction - currently unknown PROJECT timeline - 10 months
We have started with the foundation work and work is moving at a steady pace. Excavation and blinding of the foundation has been completed.
|
Properties › Re: Bitsworks Project Memoirs: Construction Of 4 Units Of 2 Bedrooms Flat Ikorodu by BITSWORKS(op): 5:54am On Mar 28, 2017*. Modified: 6:12am On Mar 28, 2017 |
Block setting for the foundation has been completed and backfilling of the foundation is in progress.
|
Properties › Re: Bitsworks Project Memoirs: Construction Of 4 Units Of 2 Bedrooms Flat Ikorodu by BITSWORKS(op): 7:03am On Mar 25, 2017 |
Blinding and foundation blockwork has been done. Due to the slope in terrain, the level at the back of the building will be a step lower. We ended up using 7 coaches to make level with the front of the building even with the step down.
We used a RC beam to tie the blockwork in place with the foundation short columns.
|
Properties › Bitsworks Project Memoirs: Construction Of 4 Units Of 2 Bedrooms Flat Ikorodu by BITSWORKS(op): 6:40am On Mar 25, 2017*. Modified: 6:56am On Mar 25, 2017 |
BITSWORKS Nigeria is a multi-discipline construction company comprising of architects, builders, civil engineers and interior designers.
We currently have a brief for a client to construct 4 units of 2 bedrooms flats on a plot of land in Mowo-Kekere, Ikorodu. The Site is a virgin land, dry and slopy terrain.
We will share the floor plan, elevations and 3D views once we have finalized on the design and permission has been given by the client.
Size of land - 640 sqm Total area of building - 204sqm Total unbuilt area - 436sqm Percentage of site covered. - 31% Percentage unbuilt - 69.0%
Estimated budget for construction - currently unknown PROJECT timeline - 10 months
We have started with the foundation work after sorting out all the omo-onile issues and payments
|
Properties › Re: DIY: Construction Of Residential Units At Harmony Villa [isheri OPIC] by BITSWORKS(op): 6:10am On Feb 05, 2017 |
Columns and lintel formwork in progress on the first floor.
|
Properties › Re: DIY: Construction Of Residential Units At Harmony Villa [isheri OPIC] by BITSWORKS(op): 11:04am On Feb 03, 2017 |
Block setting on the first floor completed, work on the lintel and columns about to start.
|
Properties › Re: DIY: Construction Of Residential Units At Harmony Villa [isheri OPIC] by BITSWORKS(op): 6:36pm On Jan 27, 2017 |
Much progress has been made on the block setting, we are getting set for the lintel and columns work.
|
Properties › Re: DIY: Construction Of Residential Units At Harmony Villa [isheri OPIC] by BITSWORKS(op): 11:45am On Jan 25, 2017 |
Block setting in progress.
|
Properties › Re: DIY: Construction Of Residential Units At Harmony Villa [isheri OPIC] by BITSWORKS(op): 6:51pm On Jan 24, 2017 |
Block setting work on the first floor started after leaving the decking to cure for 3 weeks but the bamboo props are still going to be in place for another 2 weeks.
|
Properties › Re: DIY: Construction Of Residential Units At Harmony Villa [isheri OPIC] by BITSWORKS(op): 4:25pm On Jan 20, 2017 |
timmiezone: Hello,
Can I get the number of your borehole installer. I have a project around Ojodu and I'm in need of one.
Thanks. Hello, kindly call Yemi 08035950388. Best regards. |
Properties › Re: DIY: Construction Of Residential Units At Harmony Villa [isheri OPIC] by BITSWORKS(op): 7:14am On Jan 07, 2017 |
jossy26: great job sir, but its like this decking doesnt have beams as always advised by you professionals, any reason for that? and also the no nylon was used to prevent water seepage......, please am not condemning the good job oo, just an observation out of my curiosity There are indeed beams all around and at the internal transverse. The iron bender also included hidden beams at intervals and our structural engineer approved it for casting. I have not used nylon on any of my decking work but maybe I will look into it and see if it's a added benefit against seepage. Thank you sir for the comment. |
Properties › Re: DIY: Construction Of Residential Units At Harmony Villa [isheri OPIC] by BITSWORKS(op): 7:08am On Jan 07, 2017 |
twinskenny: boss weldone and happy new year @twinskenny, thanks and a happy new year to you too. How's family and business doing? |
Properties › Re: DIY: Construction Of Residential Units At Harmony Villa [isheri OPIC] by BITSWORKS(op): 3:17pm On Jan 06, 2017 |
Elevated POV pictures of the decking.
|
Properties › Re: DIY: Construction Of Residential Units At Harmony Villa [isheri OPIC] by BITSWORKS(op): 3:23pm On Jan 05, 2017 |
1st floor suspended floor slab concluded. Thank you God for the grace to start and end it without any mishap.
|
Properties › Re: DIY: Construction Of Residential Units At Harmony Villa [isheri OPIC] by BITSWORKS(op): 3:17pm On Jan 05, 2017 |
mufutau55: How many hours for casting from the 10am starting time? Thx.
Hajji M. We just finished now at 3:15pm Hajji M. |
Properties › Re: DIY: Construction Of Residential Units At Harmony Villa [isheri OPIC] by BITSWORKS(op): 3:11pm On Jan 05, 2017 |
We are casting the suspended floor slab t(decking) today and this is the progress of work so far. We should be done in like 30 minutes. Casting started at 10am and we used a total of 22 labour.
|
Properties › Re: DIY: Construction Of Residential Units At Harmony Villa [isheri OPIC] by BITSWORKS(op): 7:33am On Jan 04, 2017 |
olumide4christ: Knowing the cost of a raft foundation alone is not enough information required to go ahead and buy a swampy or waterlogged land. NOTE THAT before you even begin to construct a raft foundation, you would have to do a large amount of sand filling of the plot of land, of which the cost could even be more than the cost of the raft foundation depending on what depth the sand filling would be.
See my thread on lands that could increase your construction cost... https://www.nairaland.com/2954604/beware-buying-these-lands-may Thank you sir for this contribution, your professional insight are always a delight. |
Properties › Re: DIY: Construction Of Residential Units At Harmony Villa [isheri OPIC] by BITSWORKS(op): 7:29am On Jan 04, 2017 |
mufutau55: Good work my brother. I hope in this new Year 2017 I have enough money to engage you. You are doing good. Keep it up.
Hajji M. Lol... Hajji, spend this money, you are more than capable already. I look forward to that day, 2017 will be a year of uncommon favor for us. |
Properties › Re: DIY: Construction Of Semi-detached Duplexes At Harmony Villa [isheri OPIC] by BITSWORKS(op): 3:45pm On Jan 03, 2017 |
More block setting pictures of the perimeter wall.
|
Properties › Re: DIY: Construction Of Residential Units At Harmony Villa [isheri OPIC] by BITSWORKS(op): 2:16pm On Jan 03, 2017 |
Electrical piping on the decking platform, all getting set for the casting of the suspended floor.
|
Properties › Re: DIY: Construction Of Residential Units At Harmony Villa [isheri OPIC] by BITSWORKS(op): 9:08am On Dec 30, 2016*. Modified: 7:24am On Dec 31, 2016 |
Reinforcement work ongoing.
|
Properties › Re: DIY: Construction Of Semi-detached Duplexes At Harmony Villa [isheri OPIC] by BITSWORKS(op): 8:57am On Dec 30, 2016 |
Ongoing perimeter wall.
|
Properties › Re: DIY: Construction Of Residential Units At Harmony Villa [isheri OPIC] by BITSWORKS(op): 7:52pm On Dec 29, 2016*. Modified: 9:04am On Dec 30, 2016 |
Decking platform taking shape and work is going on at a steady pace.
|
Properties › Re: DIY: Construction Of Semi-detached Duplexes At Harmony Villa [isheri OPIC] by BITSWORKS(op): 7:32am On Dec 23, 2016*. Modified: 10:05am On Dec 23, 2016 |
Block setting of the perimeter wall in progress
|
Properties › Re: DIY: Construction Of Residential Units At Harmony Villa [isheri OPIC] by BITSWORKS(op): 6:32am On Dec 22, 2016*. Modified: 6:51am On Dec 22, 2016 |
Carpentry formwork for the 1st floor suspended slab in progress.
|
Properties › Re: DIY: Construction Of Semi-detached Duplexes At Harmony Villa [isheri OPIC] by BITSWORKS(op): 3:46pm On Dec 17, 2016*. Modified: 2:18pm On Dec 19, 2016 |
Casting of the raft has been completed and the formwork is being removed.
|
Properties › Re: DIY: Construction Of Semi-detached Duplexes At Harmony Villa [isheri OPIC] by BITSWORKS(op): 1:02pm On Dec 16, 2016 |
Reinforcement work in progress. We are using 16mm rebars and 10mm for the rings.
|
Properties › Re: DIY: Construction Of Residential Units At Harmony Villa [isheri OPIC] by BITSWORKS(op): 11:37am On Dec 15, 2016*. Modified: 3:50pm On Dec 15, 2016 |
Block setting on lintel level in progress.
|
|