PropertiesRe: BITSWORKS PROJECT MEMOIRS: Construction Of 4 Units Of 2 Bedrooms Flat Mowo Nla by BITSWORKS(op): 11:38am On Sep 23, 2018
More reinforcements work progress in pictures.

PropertiesRe: BITSWORKS PROJECT MEMOIRS: Construction Of 4 Units Of 2 Bedrooms Flat Mowo Nla by BITSWORKS(op): 11:35am On Sep 23, 2018
Alkanelly:
nice job, am also building 4 units of two bedrooms in port harcourt now, my building area is 21.710m x 11.580m. we on the digging of foundation now
God speed as you build sir. Thanks for the compliment. Are you a builder or the client? Best regards.
PropertiesRe: BITSWORKS PROJECT MEMOIRS: Construction Of 4 Units Of 2 Bedrooms Flat Mowo Nla by BITSWORKS(op): 11:28am On Sep 23, 2018
Reinforcement work in progress.

PropertiesRe: BITSWORKS PROJECT MEMOIRS: Construction Of 4 Units Of 2 Bedrooms Flat Mowo Nla by BITSWORKS(op): 4:39pm On Sep 22, 2018
Still on the carpentry formwork, almost completed.

PropertiesRe: BITSWORKS PROJECT MEMOIRS: Construction Of 4 Units Of 2 Bedrooms Flat Mowo Nla by BITSWORKS(op):
Carpentry formwork on the first floor suspended slab (decking).

PropertiesRe: BITSWORKS PROJECT MEMOIRS: Construction Of 4 Units Of 2 Bedrooms Flat Mowo Nla by BITSWORKS(op): 4:56am On Sep 06, 2018
seunben:
Excluding blocks used for foundation, what is the total number of blocks used so far for the ground floor. Also, how many blocks are you estimating for the first floor.
For the ground floor block setting work, we stacked and used up 3100 blocks but we couldn't have laid more than 3000 because we will have breakages and half's, some will also be used to fill up the hollows of half's.

We will use about the same numbers on the first floor because the spatial dimensions are the same. We might just have more breakages/waste due to carrying upstairs.
PropertiesRe: BITSWORKS PROJECT MEMOIRS: Construction Of 4 Units Of 2 Bedrooms Flat Mowo Nla by BITSWORKS(op): 4:50am On Sep 06, 2018
Level work completed, preparation for the decking work in progress.

PropertiesRe: BITSWORKS PROJECT MEMOIRS: Construction Of 4 Units Of 2 Bedrooms Flat Mowo Nla by BITSWORKS(op): 4:49am On Sep 06, 2018
jp130:
Oga any update so far?
Apologies for the long hiatus, I have been a bit under the weather. We have taken levels and set for the decking work.
PropertiesRe: BITSWORKS PROJECT MEMOIRS: Construction Of 4 Units Of 2 Bedrooms Flat Mowo Nla by BITSWORKS(op): 8:04am On Aug 21, 2018
The architectural drawings showing:
1. Ground floor plan
2. First floor plan
3. Front Elevation

PropertiesRe: BITSWORKS PROJECT MEMOIRS: Construction Of 4 Units Of 2 Bedrooms Flat Mowo Nla by BITSWORKS(op): 7:49am On Aug 21, 2018
Casting of the front unit lintels, beams and columns. To save cost, we are using the planks from the rear unit for the formwork and that is why it took a bit of a while.

PropertiesRe: BITSWORKS PROJECT MEMOIRS: Construction Of 4 Units Of 2 Bedrooms Flat Mowo Nla by BITSWORKS(op): 7:41am On Aug 21, 2018
jp130:
Nice n neat work that u r doing here, i feel like i am d owner of d work. My dream will com to pass someday
Thank you sir for the kind words. You will definitely build yours and we will be at your service if you need us.
PropertiesRe: BITSWORKS PROJECT MEMOIRS: Construction Of 4 Units Of 2 Bedrooms Flat Mowo Nla by BITSWORKS(op): 7:19pm On Aug 20, 2018
UncleRovas:
This plan is just perfect for me. Nice job BITSWORKS
Thank you sir. Regards.
PropertiesRe: BITSWORKS PROJECT MEMOIRS: Construction Of 4 Units Of 2 Bedrooms Flat Mowo Nla by BITSWORKS(op): 7:17pm On Aug 20, 2018
EgunMogaji:
Oh, that’s really nice. I’m doing really good Sir, thanks for asking.

Did you ever get consent to post the plans? I’ll love to read them.
Yes, the client has given us a go ahead and I will post it ASAP.
PropertiesRe: BITSWORKS PROJECT MEMOIRS: Construction Of 4 Units Of 2 Bedrooms Flat Mowo Nla by BITSWORKS(op): 11:41am On Aug 13, 2018
Drone shots from BITSWORKS ONE.

PropertiesRe: BITSWORKS PROJECT MEMOIRS: Construction Of 4 Units Of 2 Bedrooms Flat Mowo Nla by BITSWORKS(op):
EgunMogaji:
How are you getting the aerial pictures?

Thanks.
I own and pilot a DJI Phantom drone for my projects and for commercial rentals. How are you doing sir.
PropertiesRe: BITSWORKS PROJECT MEMOIRS: Construction Of 4 Units Of 2 Bedrooms Flat Mowo Nla by BITSWORKS(op):
Casting of the columns, beams and lintels.

PropertiesRe: BITSWORKS PROJECT MEMOIRS: Construction Of 4 Units Of 2 Bedrooms Flat Mowo Nla by BITSWORKS(op): 3:02am On Aug 10, 2018
Carpentry formwork for the lintels and columns ongoing.

PropertiesRe: BITSWORKS PROJECT MEMOIRS: Construction Of 4 Units Of 2 Bedrooms Flat Mowo Nla by BITSWORKS(op):
Aerial shots of ongoing construction.

PropertiesRe: BITSWORKS PROJECT MEMOIRS: Construction Of 4 Units Of 2 Bedrooms Flat Mowo Nla by BITSWORKS(op):
More block setting pictures at lintel level.

PropertiesRe: BITSWORKS PROJECT MEMOIRS: Construction Of 4 Units Of 2 Bedrooms Flat Mowo Nla by BITSWORKS(op):
Lintel level achieved, almost 100% done but we will definitely wrap it up today to begin the carpentry formwork next week.

PropertiesRe: BITSWORKS PROJECT MEMOIRS: Construction Of 4 Units Of 2 Bedrooms Flat Mowo Nla by BITSWORKS(op): 3:01pm On Aug 04, 2018
seunben:
You have been very honest with ur answers. God bless you sir.
Was the german floor was done in stages over a period of more than one day?
Secondly if u don't mind what is the total size and cost of the damp proof membrane (nylon)
Apologies for the late response, have been a bit busy lately.
Yes, the german floor was casted in 2 stages since we had a step down level from the foundation work, that made it easy to cast it over 2 days.

The size of the german floor is 9.5m x 26.5m and the DPM material covered this. We bought 4 rolls of double layer nylon unlike the black one readily available in the market that comes in small sizes. I will have to check the nylon wrapper to get the coverage of one roll which is in grams anyway.
PropertiesRe: BITSWORKS PROJECT MEMOIRS: Construction Of 4 Units Of 2 Bedrooms Flat Mowo Nla by BITSWORKS(op):
Block setting getting to lintel level gradually.

PropertiesRe: BITSWORKS PROJECT MEMOIRS: Construction Of 4 Units Of 2 Bedrooms Flat Mowo Nla by BITSWORKS(op): 6:09am On Jul 28, 2018
Block setting ongoing.

PropertiesRe: BITSWORKS PROJECT MEMOIRS: Construction Of 4 Units Of 2 Bedrooms Flat Mowo Nla by BITSWORKS(op):
Block setting in motion, slow, steady and neat...thats how we do it.

PropertiesRe: BITSWORKS PROJECT MEMOIRS: Construction Of 4 Units Of 2 Bedrooms Flat Mowo Nla by BITSWORKS(op): 5:44am On Jul 27, 2018
Block setting layout.

PropertiesRe: BITSWORKS PROJECT MEMOIRS: Construction Of 4 Units Of 2 Bedrooms Flat Mowo Nla by BITSWORKS(op): 7:02am On Jul 26, 2018
We started the block setting for the ground floor on Wednesday 25th July. Laying out the first coach blockwork to show the spatial arrangement.

PropertiesRe: BITSWORKS PROJECT MEMOIRS: Construction Of 4 Units Of 2 Bedrooms Flat Mowo Nla by BITSWORKS(op):
German floor casting concluded.

PropertiesRe: BITSWORKS PROJECT MEMOIRS: Construction Of 4 Units Of 2 Bedrooms Flat Mowo Nla by BITSWORKS(op): 10:07pm On Jul 25, 2018
seunben:
keep the flag flying. pls update us on the quantities of material use for the german floor.
Thank you. For the material, we did a bulk purchase of most of the materials used but I will try and do a breakdown based on usage
1. Granite - We purchased 30 tons and probably used close to 20 tons for the short pillars and german floor
2. Sharp sand - We purchased 20 tons and used it up, what's left is just little.
3. Cement - We used 82 bags using a mix ratio of 1:2:4
PropertiesRe: BITSWORKS PROJECT MEMOIRS: Construction Of 4 Units Of 2 Bedrooms Flat Mowo Nla by BITSWORKS(op): 1:51am On Jul 24, 2018
Front half of the german floor casting completed.

PropertiesRe: BITSWORKS PROJECT MEMOIRS: Construction Of 4 Units Of 2 Bedrooms Flat Mowo Nla by BITSWORKS(op):
Still ongoing.

PropertiesRe: BITSWORKS PROJECT MEMOIRS: Construction Of 4 Units Of 2 Bedrooms Flat Mowo Nla by BITSWORKS(op): 3:17pm On Jul 23, 2018
Casting of the german floor in progress.

PropertiesRe: BITSWORKS PROJECT MEMOIRS: Construction Of 4 Units Of 2 Bedrooms Flat Mowo Nla by BITSWORKS(op):
Backfilling, compacting, DPM laying and reinforcements mat concluded.