PropertiesRe: Construction Journal | Browne Mews By Nexthome by brabus(op): 2:30am On Dec 04, 2015
Day 12

PropertiesRe: Nexthome Builders: 2014/2015 New and Ongoing Projects by brabus(op): 10:29pm On Dec 03, 2015
Seascape Villa by NextHome | Attracting Key Figures

I can see my dream is within reach. The seascape villa is gradually getting out of grounds. Guess who came visiting today! It's my dad (my mentor). He wanted to see what his baby is doing at the seascape villa and chip in some more interesting tips on how to build one-of-it's-kind beachfront resort.

Happy 43rd Anniversary to you Dad and Mum!

PropertiesRe: Nexthome Builders: 2014/2015 New and Ongoing Projects by brabus(op): 9:52pm On Dec 03, 2015
Spotlight: Seascape Villa by NextHome

The basement slab formwork preparation ongoing.

PropertiesRe: Nexthome Builders: 2014/2015 New and Ongoing Projects by brabus(op): 9:48pm On Dec 03, 2015
Spotlight: Seascape Villa by NextHome

Pouring the basement septic tank. Thinking out of the box to create a surface septic tank in a waterlogged site such as this.

PropertiesRe: Nexthome Builders: 2014/2015 New and Ongoing Projects by brabus(op): 9:37pm On Dec 03, 2015
Spotlight: Atlantic View by NextHome

Grande Entry Door

PropertiesRe: Nexthome Builders: 2014/2015 New and Ongoing Projects by brabus(op): 9:33pm On Dec 03, 2015
Spotlight: Atlantic View by NextHome

More pictures and more coming. The fence, the septic tank and the pool.

PropertiesRe: Nexthome Builders: 2014/2015 New and Ongoing Projects by brabus(op): 9:29pm On Dec 03, 2015
Spotlight: Atlantic View by NextHome

Picking up the doors that fits the job.

PropertiesRe: Nexthome Builders: 2014/2015 New and Ongoing Projects by brabus(op): 9:25pm On Dec 03, 2015
Spotlight: Atlantic View by NextHome

The first floor slab formwork now removed

PropertiesRe: Nexthome Builders: 2014/2015 New and Ongoing Projects by brabus(op): 9:22pm On Dec 03, 2015
I can see clearly now! | Atlantic View Contemporary Living by NextHome

We are on the second floor (the pent floor) and the Atlantic Beach was a beautiful sight to behold from here.

PropertiesRe: Nexthome Builders: 2014/2015 New and Ongoing Projects by brabus(op): 9:16pm On Dec 03, 2015
befto:
That's good to hear. If you stick to your words you will very well by your clients.
Best of luck and hope 2016 brings a much better chapter for NextHome
"If I stick to my words" or "If clients stick to their contract with NextHome." If clients gets realistic with their expectations. If clients stops using cheap blackmails to address less trivia issues. If clients are more professional in their dealings.

Again, NextHome is not a "Baba Risi" the bricklayer. With Milestone Payments, things has never gone wrong with anyone who followed it to the letter.
Milestone payments does deny owners the right to supply whatever they wish to supply. Just ensure you keep to your part of the contract before we move to site.

2016 will be more interesting as we have lawyered up the business. No more "he told me to tell you." We will be here to build for the selected few who can afford the peace of mind that comes with our services.
PropertiesRe: Nexthome Builders: 2014/2015 New and Ongoing Projects by brabus(op): 8:58pm On Dec 03, 2015
Thanks ahmodu4real. Comment such as this inspires us to do more.

There's nothing Julius Berger than the processes and set rules which her people follows by heart. The people are the same people we meet on our site on a daily basis and the equipment they use aren't heavenly. We will continually improve our processes to serve our clients better.
HealthRe: Health Benefits Of Coconut Water You Probably Don't Know by brabus(m): 8:46pm On Dec 03, 2015
Nice tip OP
PropertiesRe: Before & After: Renovation/Remodelling Jobs Full Of Surprises by brabus(op): 5:36am On Dec 03, 2015
barakah:
Can we meet your friend Sir?
The door looks quite neat for a made in Nigeria product.
Are there more samples to see please, 4 feet doorsfor instance.
Not made in Nigeria Doors. Philox 08033472979
PropertiesRe: Construction Journal | Browne Mews By Nexthome by brabus(op): 3:03am On Dec 03, 2015
Don't mind that old man (spyder880). He's always good at innovations.

Demistifying construction myths since 1808 - na spyder880 be dat.

EgunMogaji:
This is what I intend to use. I think Spyder880 is using it in his existing house.
PropertiesRe: Construction Journal | Browne Mews By Nexthome by brabus(op): 2:23am On Dec 03, 2015
New Equipment Coming!!!

A refurbished pumper from Mayco. The HR 30-40 from UES United States can pump 1 1/2" rock and will go over 250' vertical
and 1,200' horizontal. Discussions ongoing.

Now a quality build can also be cheap and fast.

PropertiesRe: Nexthome Builders: 2014/2015 New and Ongoing Projects by brabus(op): 2:16am On Dec 03, 2015
New Equipment Coming!!!

A refurbished pumper from Mayco. The HR 30-40 from UES United States can pump 1 1/2" rock and will go over 250' vertical
and 1,200' horizontal. Discussions ongoing.

Now a quality build can also be cheap and fast.

PropertiesRe: Construction Journal | Browne Mews By Nexthome by brabus(op): 2:02am On Dec 03, 2015
We lead, They follow. | Precast Inspection Chambers by NextHome

Call it packaging or anything you like. It has become our way of life. We are from the "New School" and tends to do things differently. In Olamide's voice "I do my things my way"

We are almost in the 22nd century. Which inspection chamber will you choose? It doesn't cost fortune. It only cost the ability of your builder to think-outside-the-box.

Precast or Traditional?

PropertiesRe: Construction Journal | Browne Mews By Nexthome by brabus(op): 1:48am On Dec 03, 2015
EgunMogaji:
Are the two vertical pipes going to come out of the howl in the foundation there?
Maybe a clearer picture of plumbing. Thanks.
Yes, they're coming out straight into the inspection chambers (precast in this case).


_____________
Pics of what we did back in 2013.

PropertiesRe: Nexthome Builders: 2014/2015 New and Ongoing Projects by brabus(op): 1:27am On Dec 03, 2015
Coming Soon! NextHome's First Master Planned Residential Community.

Country Living with City Convenience. A Place You Can't Resist.

Project to be Pre-Launched Mid 2016.
PropertiesRe: Construction Journal | Browne Mews By Nexthome by brabus(op): 1:25am On Dec 03, 2015
Coming Soon! NextHome's First Master Planned Residential Community.

Country Living with City Convenience. A Place You Can't Resist.

Project to be Pre-Launched Mid 2016.
PropertiesRe: Construction Journal | Browne Mews By Nexthome by brabus(op):
11 days of non-stop activities | Here we are.

Over 4,000 sandcrete blocks, Fence raft and walls raised, Foundation raft completed, Sandfilling almost completed and more.

Good speed, Good progress, Wonderful budget! Happy Client, Happy Builder! No hungry relatives or interfering parties. No ammendment on site. All changes and ammendment were done on paper. No Land urchins. No stealing of materials because we can't steal from ourselves. No stories. No heartache.

First milestone of the Browne Mews is to be completed soon.

Remember, payment are made to NextHome based on milestones achieved. NextHome will not receive payment for milestones yet to be completed. It's part of the contract.

Can you beat that?

PropertiesRe: Construction Journal | Browne Mews By Nexthome by brabus(op): 12:43am On Dec 03, 2015
14 days ago | A bare land

PropertiesRe: Construction Journal | Browne Mews By Nexthome by brabus(op): 5:45pm On Dec 02, 2015
End of Day 11 | More Pictures

The sand we used to sandfill and the block we produced.

PropertiesRe: Construction Journal | Browne Mews By Nexthome by brabus(op): 5:17pm On Dec 02, 2015
End of Day 11 | What was achieved

Just pictures.

PropertiesRe: Construction Journal | Browne Mews By Nexthome by brabus(op): 4:35pm On Dec 02, 2015
NL1960:
Is this N65,000,000.00 the cost to build one(1) unit or the cost to build the four(4) units?.
65,000,000:00 is the cost to build all (4 unit). Just as we spent N54,000,000:00 to build The Reserve (3 Unit).
PropertiesRe: Construction Journal | Browne Mews By Nexthome by brabus(op): 1:21pm On Dec 02, 2015
EgunMogaji:
Are you going to build this?
Yes that's what we are building.
PropertiesRe: Construction Journal | Browne Mews By Nexthome by brabus(op): 1:05pm On Dec 02, 2015
Happening Now!

1. Sand filling advancing to the 4th Apartment

2. Preparation of reinforcement for the DPC ongoing.

3. Fence column preparation ongoing. Marine board for shuttering.

4. Block production non-stop

5. NextHome dump truck and Van on standby for deliveries.

The best doesn't have to cost fortune!

PropertiesRe: Construction Journal | Browne Mews By Nexthome by brabus(op): 12:24pm On Dec 02, 2015
We've done it before, We're going to do it again!

The Reserve by NextHome cost us N54m (land, fence, carcass, documentation and the finishes)

PropertiesRe: Construction Journal | Browne Mews By Nexthome by brabus(op):
Browne Mews by NextHome | 4 Unit of 4 Bed Terrace Houses

Client: Private
Designer/Architect/Builder: NextHome Builders
Project Location: Lekki Scheme II, Lagos
Delivery Method: General Contractor
Sector: Residential
Status: Ongoing
Budget: N65,000,000 (1000m2 Land, Carcass, Fence, and Finishes)

Can you beat that?

PropertiesRe: Construction Journal | Browne Mews By Nexthome by brabus(op): 9:54am On Dec 02, 2015
Fence So Straight

PropertiesRe: Before & After: Renovation/Remodelling Jobs Full Of Surprises by brabus(op): 5:56am On Dec 02, 2015
barakah:
Oga Brabus,
This door.
Did you get it also at Amu market?
For how much please?
A friend in Ikota Lagos supplied the door. N65,000