Icecream4U:Yes it is. But double doors are the ones that doesn't make noise when jammed. Like it doesn't make noise at all. |
timay1:Almost everything that has advantages have disadvantages. |
Video editing, search engine optimization, email marketing, web analytics, Google ads, etc. |
Good for them. Nothing bad in this because both genders are being rewarded for their work. |
Why not wait until you're ready to campaign for election before lifting the ban? I thought you all said you'll arrest people that are still using twitter despite the ban. Anyway, if anyone needs help with Google ads, i am the specialist you can count on. |
Digiprof:What exactly is your complaint? Are you complaining about getting low CPC from your ads or this post is about your AdSense earnings? |
Icecream4U:Yes, 35 bags for the interior. I'm sure the interior will consume more than the exterior, however, i am yet to plaster the exterior for now. Will do next month. I think 100 bags is outrageous. |
Icecream4U:Ceiling for the 3 rooms, kitchent, toilets, and laundry. White POP for the 2 sitting rooms, corridor, and veranda. Check the attached video in one of the previous updates. |
Icecream4U:Plaster and sharp. Mixed |
Icecream4U:7 Doors. 3 of the doors are for entrances. 1 in the front, 1 for the kitchen to the backyard, and 1 for the private sitting room exit. 4 of the doors are inside. 2 of the doors are double, and the rest single. Each of the double doors is 70k and single is 35k |
Your trusted mechanic might also be manipulated or not having enough knowledge of the car you're buying. I remember when i went to buy a car alongside with my brother's long time mechanic. He consider a couple of things "minor issues" but when it's time to buy those stuffs, they are not cheap. If you've been driving for a while, it will do you good to test-drive the car yourself. As is today, i can easily pick faults in cars than most mechanic. Sometimes, what all these mechanics consider normal are really not normal. |
Iseoluwani:I will update as we progress. |
noonee:I am slightly above 12M at the moment. |
Before installing the white POP on the veranda, we mount a burglary on top of the veranda for additional security.
|
By the way, i have done the first phase of the plumbing and electrical work before the plastering. I have just got the quote for the cables, totaling 385,000 Naira. I will post more update as we progress. Thanks for reading. |
I completed the white POP work on August, 2021. I got a quote for the tiling. Total square meters for the tiling is 360. I bought the tiles. 60by60 at the rate of 5,400 Naira per pack. 30by60 at the rate of 2,400 Naira per pack. 40by40 at the rate of 4,200 Naira per pack. I bought 45 bags of cement for the tiling. Each bag at the rate of 3,600 Naira. I bought 2 trips of sand. Plaster and sharp sand. The tiler charge 400 Naira per square meters. The tiling was completed on Sept, 8th, 2021.
|
After the plastering, i proceeded with the POP work, both the arc, pillars and the white POP. I bought 40 bags of POP cement. Each bag is 5,500 Naira. 20KG fillers. Workmanship is per square meters. So total cost of white POP plus the TV stand was 170,000 Naira For the arc and pillars, I bought 5 bags of cement and the workmanship was 30,000 Naira. Each bag of cement was 3,700 Naira.
|
After completing the ceiling, I drop another trip of sand at the rate of 28,000 Naira. Then we did the plastering (interior). We used about 35 bags of cement for the plastering. Each bag cost 3,700 Naira. Workmanship was 70,000 plus |
Kwamecron:More than that |
After fitting the windows, doors, and burglary, i proceeded with the ceiling for the rooms, toilets, laundry, and the kitchen. I got 2ft by 2ft ceiling at the rate of 4000 Naira per pack. I got 30 packs. I bought wood and nails. Workmanship was 45,000 Naira. |
Next, i got a quote for the doors and burglary. The doors and burglary cost 450,000 Naira. And also, a quote for the windows. The windows and toilet doors cost 600,000 Naira. |
After the roofing, i did the German flooring. I bought 1 trip granite at 40,000 Naira, plus the remaining granite from the 140k trip i bought during the foundation. I bought 2 trips of sand at 28,000 each. I bought 35 bags of Dangote cement. As at that time, a bag was 3700 Naira. Workmanship for the German flooring was 60,000 Naira. |
I did the roofing towards the end of May, 2021. The steel roof specialists collected 70,000 Naira.
|
After setting the roof, we measured the total square meters. It is 380sqm. Then i proceeded to purchase steel coated roofing sheets (shingles) As at the time in May, 2021, 1sqm of the roofing sheet was 3,250 Naira. I bought 380 square meters. Gutter and ridges was 150,000 Naira. Transport was 40,000 Naira. |
Immediately after completing the parapet, i got a quote for the roof. I bought; 500 pieces of 2by4 (hardwood) 400 pieces of 2by3 (hardwood) nails The wood, nails and transport cost about 700,000 Naira. The carpenter collected 90,000 Naira. Pardon me for not giving the accurate cost.
|
After completing the block setting, i took a break. The whole process from block molding to foundation to block setting takes approximately 2 months. By May, 2021, i did the parapet. The parapet cost approximately 450,000 Naira.
|
ojasweb:By the way, the bricklaying work was 250,000 Naira including casting the lintel and setting the 2 couch after the lintel |
The building reached lintel level within 2 weeks. I got a welder to do the iron for linted and pillars. The lintel is for the entire building, no place is excluded. I paid the welder about 40,000 Naira for workmanship.
|
On the first week of December, 2020, we dug and lay the foundation of the building. due to the area and personal preference, we made the foundation four blocks. Then we waited few days and started with the sand filing. I got about 17 trips filing sand (dredging) at 22,000 Naira per trip.
|
Crossroad1:Egbon i have already stated that i am not a professional builder. I only use my intuition to do the sketch. |
While waiting for the blocks to dry, i went to purchase 10mm and 12mm iron. I don't really remember the quantity, but i paid 263,000 Naira as at the time in November, 2020. I got a trip of granite at 140,000 Naira. I also proceeded and paid the foundation fee to the community leaders. They asked for 150,000 but i paid 100,000 Naira.
|