Re: Construction Ofsemi-detached Twin Duplex And Restructuring Of Bungalow In Magodo by lafolabi(m): 9:35pm On Mar 21, 2016 |
progressing |
Re: Construction Ofsemi-detached Twin Duplex And Restructuring Of Bungalow In Magodo by lafolabi(m): 10:03pm On Mar 21, 2016 |
|
Re: Construction Ofsemi-detached Twin Duplex And Restructuring Of Bungalow In Magodo by lafolabi(m): 10:05pm On Mar 21, 2016 |
thanks oga moor |
Re: Construction Ofsemi-detached Twin Duplex And Restructuring Of Bungalow In Magodo by lafolabi(m): 10:30pm On Mar 22, 2016 |
compacting. |
Re: Construction Ofsemi-detached Twin Duplex And Restructuring Of Bungalow In Magodo by Nobody: 11:54am On Mar 23, 2016 |
. |
Re: Construction Ofsemi-detached Twin Duplex And Restructuring Of Bungalow In Magodo by lafolabi(m): 8:38pm On Mar 23, 2016 |
thanks so much sir. |
Re: Construction Ofsemi-detached Twin Duplex And Restructuring Of Bungalow In Magodo by lafolabi(m): 8:51pm On Mar 23, 2016 |
Grand floor concrete work. |
Re: Construction Ofsemi-detached Twin Duplex And Restructuring Of Bungalow In Magodo by lafolabi(m): 9:14pm On Mar 23, 2016 |
septic tank block work. |
Re: Construction Ofsemi-detached Twin Duplex And Restructuring Of Bungalow In Magodo by lafolabi(m): 9:22pm On Mar 24, 2016 |
casting of 50% of grand floor column. |
Re: Construction Ofsemi-detached Twin Duplex And Restructuring Of Bungalow In Magodo by lafolabi(m): 10:16pm On Mar 24, 2016 |
columns. |
Re: Construction Ofsemi-detached Twin Duplex And Restructuring Of Bungalow In Magodo by lafolabi(m): 10:37pm On Mar 24, 2016 |
more pictures |
Re: Construction Ofsemi-detached Twin Duplex And Restructuring Of Bungalow In Magodo by lafolabi(m): 10:00pm On Mar 25, 2016 |
17 days. we finished casting the remaining columns for grand floor. Also working on soak away and septic tank |
Re: Construction Ofsemi-detached Twin Duplex And Restructuring Of Bungalow In Magodo by lafolabi(m): 10:40pm On Mar 25, 2016 |
form work materials for first floor slab |
Re: Construction Ofsemi-detached Twin Duplex And Restructuring Of Bungalow In Magodo by Aventures(m): 6:58pm On Mar 26, 2016 |
baba himself at work. speed + integrity = lafolabi. Thumbs up |
Re: Construction Ofsemi-detached Twin Duplex And Restructuring Of Bungalow In Magodo by townplanner(m): 9:55pm On Mar 26, 2016 |
lafolabi: 17 days. we finished casting the remaining columns for grand floor. Also working on soak away and septic tank I have to commend you ,NIce Job bro |
Re: Construction Ofsemi-detached Twin Duplex And Restructuring Of Bungalow In Magodo by lafolabi(m): 5:06am On Mar 27, 2016 |
God bless you sir. |
Re: Construction Ofsemi-detached Twin Duplex And Restructuring Of Bungalow In Magodo by lafolabi(m): 5:08am On Mar 27, 2016 |
thanks oga aventure |
Re: Construction Ofsemi-detached Twin Duplex And Restructuring Of Bungalow In Magodo by lafolabi(m): 9:15am On Mar 27, 2016 |
18 working days. first floor form work kick start. Glory be to GOD. |
Re: Construction Ofsemi-detached Twin Duplex And Restructuring Of Bungalow In Magodo by lafolabi(m): 9:26am On Mar 27, 2016 |
septic tank is part of 18 days achievement. |
Re: Construction Ofsemi-detached Twin Duplex And Restructuring Of Bungalow In Magodo by lafolabi(m): 9:35am On Mar 27, 2016 |
Septic tank is part of 18 days achievement. |
Re: Construction Ofsemi-detached Twin Duplex And Restructuring Of Bungalow In Magodo by lafolabi(m): 10:48pm On Mar 27, 2016 |
happy Easter to everyone. |
Re: Construction Ofsemi-detached Twin Duplex And Restructuring Of Bungalow In Magodo by Chekitaut: 11:13pm On Mar 27, 2016 |
Weldone Baba, Happy Easter |
Re: Construction Ofsemi-detached Twin Duplex And Restructuring Of Bungalow In Magodo by lafolabi(m): 11:54am On Mar 28, 2016 |
thanks so much.Enjoy your Easter. |
Re: Construction Ofsemi-detached Twin Duplex And Restructuring Of Bungalow In Magodo by lafolabi(m): 11:55am On Mar 28, 2016 |
Thanks so much.Enjoy your Easter. |
Re: Construction Ofsemi-detached Twin Duplex And Restructuring Of Bungalow In Magodo by lafolabi(m): 11:02pm On Mar 31, 2016 |
progressing 1 Like |
Re: Construction Ofsemi-detached Twin Duplex And Restructuring Of Bungalow In Magodo by lafolabi(m): 11:11pm On Mar 31, 2016 |
more pictures |
Re: Construction Ofsemi-detached Twin Duplex And Restructuring Of Bungalow In Magodo by lafolabi(m): 11:18pm On Mar 31, 2016 |
progressive work |
Re: Construction Ofsemi-detached Twin Duplex And Restructuring Of Bungalow In Magodo by Aventures(m): 9:03pm On Apr 01, 2016 |
Nice Speed, perfect Job. |
Re: Construction Ofsemi-detached Twin Duplex And Restructuring Of Bungalow In Magodo by lafolabi(m): 9:13pm On Apr 01, 2016 |
thanks |
Re: Construction Ofsemi-detached Twin Duplex And Restructuring Of Bungalow In Magodo by lafolabi(m): 9:26pm On Apr 01, 2016 |
reinforcement for first floor beams 1 Like |
Re: Construction Ofsemi-detached Twin Duplex And Restructuring Of Bungalow In Magodo by lafolabi(m): 9:55pm On Apr 04, 2016 |
first floor slab reinforcement |
Re: Construction Ofsemi-detached Twin Duplex And Restructuring Of Bungalow In Magodo by lafolabi(m): 10:00pm On Apr 04, 2016 |
electrical piping |