Abuja Airport Repairs 40% Completed, We’re Set To Meet Target – Faan - Politics - Nairaland

Nairaland Forum / Nairaland / General / Politics / Abuja Airport Repairs 40% Completed, We’re Set To Meet Target – Faan (304 Views)

Photos: 2nd Niger Bridge Is 40% Completed. To Be Commissioned In 2022 / 2019: We’re Set To Confront Buhari On Order Of Polls – Senate / Abuja Airport Repairs, 40% Completed (2) (3) (4)

(1) (Reply) (Go Down)

Abuja Airport Repairs 40% Completed, We’re Set To Meet Target – Faan by alphonsojaybaz: 6:29am On Mar 28, 2017
ABUJA AIRPORT REPAIRS 40% COMPLETED, WE’RE SET TO MEET TARGET – FAAN
source: http://www.eyesoflagos.com/2017/03/abuja-airport-repairs-40-completed-were.html

The Federal Airport Authority of Nigeria (FAAN) and Julius Berger, the contractor handling the repair of Nnamdi Azikiwe International Airport, Abuja runway, have said that the work is 40 per cent completed.
The duo gave made this known in Abuja on Monday when members of the House of Representatives Committee on Aviation led by its Chairman, Mrs Nkeiruka Onyejeocha, inspected the project.
Mr Yemi Ayelesan, Resident Engineer, FAAN, told the committee that the hardest part of the work, which is mailing of the 3.6 kilometres runway, had been completed.
He explained that the laying of ‘’fibre glide rubber’’ which prevents water from going deep underground and also prevent runway from cracking has also been completed.
Ayelesan told the committee that the contractors are working to specifications and would deliver on schedule, expressing confidence that the six weeks period for reopening of the airport was feasible.
According to him, the contractors are working round the clock to ensure that they meet the deadline.
Ayelesan said the repair work was a total reconstruction and not partial rehabilitation, explaining that the entire runway had been excavated for laying of asphalt.
He said there were isolated areas that were so bad that required digging deeper beyond mailing and laying of asphalt, stating that the entire surface were mailed to a certain depth. According to him, there is nothing like partial rehabilitation, even the taxi way is being repaired.
“Laying asphalt does not take time; it is the easiest part of the work.
“The lighting system is the next step, and the cable can be fixed within two days, as things are now, we will start fixing the light cable on March 29,’’ he said.
Dr Lai’s Richter, Project Manager, Julius Berger, said the work was being done in line with the programme of work.
Richter said the fixing of the lighting cable would commence on Wednesday, restating that the runway repairs would be completed before April 19 deadlines.
The Chairman of the House Committee, Onyejeocha, said their visit was to seek explanation on the level of work so far in line with the project agreement.
She also raised concern as to whether the repair work was a total reconstruction or partial repair, urging the contractor to ensure the completion of the project as scheduled.
“We want them to know that Nigerians are concerned and that there should be no extension of the completion date based on the agreement that we have put in place, ’’she said.
The contractors have recorded progress within 19 days since the commencement of work. The runway was shut on March 8 for six weeks for its total repair and Abuja flights diverted to Kaduna pending the completion of the repair work.
Meanwhile, the Minister of State Aviation, Senator Hadi Sirika has debunked allegations of extension of repair works at the Abuja Airport by 18 weeks, stressing that he would resign his appointment if his ministry fails to meet up targeted period. Although Sirika pointed out that the entire airport runway was scheduled to be completed within a six month period but that the airport must be opened for flights to land safely after six-weeks of closure.
“We chose Julius Berger because they have been in the site already. We have tested them before. Nigeria will not forgive us, if we fail to meet up the six weeks period. I will resign if I don’t meet the deadline of six weeks”, Sirika said.
According to the minister, the ongoing work has incured extra N150 million which was used by the contractors to charter planes that was used to ferry some of the equipment used in the repair works. Sirika who was speaking at an interactive session between his ministry, Ministry of Information and Culture and members of the Aviation Round Table (ART) in Ikeja GRA, Lagos yesterday said that when completed, the Abuja runway will be used in excess of 10 Years.

Re: Abuja Airport Repairs 40% Completed, We’re Set To Meet Target – Faan by Lucy001(f): 6:30am On Mar 28, 2017
ok
Re: Abuja Airport Repairs 40% Completed, We’re Set To Meet Target – Faan by fastguy10: 6:54am On Mar 28, 2017
ok
Re: Abuja Airport Repairs 40% Completed, We’re Set To Meet Target – Faan by Amberon: 6:57am On Mar 28, 2017
Lol
Re: Abuja Airport Repairs 40% Completed, We’re Set To Meet Target – Faan by Funlordjnr: 7:19am On Mar 28, 2017
LIES.....why have they now added almost 10 weeks to the original date if they are certain of meeting the target? angry

1 Like

(1) (Reply)

Senate Didn’t Buy Any Vehicle At N298m / Ndc Calls For Resignation Of Security Chiefs And Arrest Of Ken Agyepong / PHOTOS: Melaye Returns To ABU For Cerificate

(Go Up)

Sections: politics (1) business autos (1) jobs (1) career education (1) romance computers phones travel sports fashion health
religion celebs tv-movies music-radio literature webmasters programming techmarket

Links: (1) (2) (3) (4) (5) (6) (7) (8) (9) (10)

Nairaland - Copyright © 2005 - 2024 Oluwaseun Osewa. All rights reserved. See How To Advertise. 13
Disclaimer: Every Nairaland member is solely responsible for anything that he/she posts or uploads on Nairaland.