New 6 Bedroom Duplex Construction By Tigerkenn Homes - Properties - Nairaland

Nairaland Forum / Nairaland / General / Properties / New 6 Bedroom Duplex Construction By Tigerkenn Homes (41223 Views)

Buy Lands From Tigerkenn Homes Ltd, Isiagu, Awka, Anambra State / Newest And Ongoing Building And Estate Developments From Tigerkenn Homes / Home Improvement Diaries By Tigerkenn Homes (2) (3) (4)

(1) (2) (3) (4) (5) (6) (7) (8) (9) (Reply) (Go Down)

New 6 Bedroom Duplex Construction By Tigerkenn Homes by spyder880(m): 8:01am On Mar 29, 2017
Ladies and gentlemen, we are starting yet another beautiful building project for a Nairalander this morning, the details of the project are as follows;

Project: Construction of a new 6 bedroom duplex
Client: A Nairalander
Contractor: Tigerkenn Homes Ltd
Project duration: 120 days
Budget: To be revealed later

Stay with us as we bring you all the daily construction details from this site

2 Likes

Re: New 6 Bedroom Duplex Construction By Tigerkenn Homes by spyder880(m): 8:04am On Mar 29, 2017
From the design of this building, these are some of the arrangement of the house

ON THE GROUND FLOOR

1 main lounge (voided at the top)
1 dining room
1 entrance porch
1 ante room
1 visitors w/c
1 gym
1 study room
1 bar
1 garage
1 kitchen with pantry, kitchen store
1 laundry room
2 en suit bedrooms

ON THE UPPER FLOOR

1 en suit master bedroom with big open air balcony
1 walk in closet for the master bedroom
3 en suit bedrooms
1 family lounge
1 balcony
1 gallery

Fully loaded house grin grin grin

6 Likes

Re: New 6 Bedroom Duplex Construction By Tigerkenn Homes by spyder880(m): 8:04am On Mar 29, 2017
We had moved into this site last week and did a fencing for the land, pictures from the fencing of this site........

1 Like

Re: New 6 Bedroom Duplex Construction By Tigerkenn Homes by spyder880(m): 8:05am On Mar 29, 2017
Some more parts of the fencing we did...........

Re: New 6 Bedroom Duplex Construction By Tigerkenn Homes by Baker77: 8:15am On Mar 29, 2017
Bro we can help with all electrical works on your building.

1 Like

Re: New 6 Bedroom Duplex Construction By Tigerkenn Homes by spyder880(m): 8:40am On Mar 29, 2017
We just set out the building space, its gonna be a big building.

Re: New 6 Bedroom Duplex Construction By Tigerkenn Homes by whirlwind7(m): 2:17pm On Mar 29, 2017
The architect who made this design, is he on this forum?
Re: New 6 Bedroom Duplex Construction By Tigerkenn Homes by spyder880(m): 7:11pm On Mar 29, 2017
whirlwind7:


The architect who made this design, is he on this forum?

This design was done by a gentleman called Blacklakehouse. He is on nairaland.

7 Likes 1 Share

Re: New 6 Bedroom Duplex Construction By Tigerkenn Homes by mank1234(m): 9:35pm On Mar 29, 2017
Baker77:
Bro we can help with all electrical works on your building.

Help as in free? Or are you requesting for the job? If the later, your tone isn't right. If the former, please extend the help to us o.

1 Like

Re: New 6 Bedroom Duplex Construction By Tigerkenn Homes by Baker77: 9:57pm On Mar 29, 2017
mank1234:


Help as in free? Or are you requesting for the job? If the later, your tone isn't right. If the former, please extend the help to us o.
(smile),not free sir i'm actually requesting for the job and i will be glad if we are given a chance ...thanks for the correction

1 Like

Re: New 6 Bedroom Duplex Construction By Tigerkenn Homes by spyder880(m): 5:16am On Mar 30, 2017
Foundation trench excavation starts.....

Re: New 6 Bedroom Duplex Construction By Tigerkenn Homes by spyder880(m): 5:50am On Mar 30, 2017
Still trenching..........

Re: New 6 Bedroom Duplex Construction By Tigerkenn Homes by Onyema1(m): 3:02am On Mar 31, 2017
@spyder880, please can you review this quote for plumbing works and electrical and help me out. I am doing the wordwork for roofing my 8 all ensuite bed room duplex. Now my builder has sent me this quote for the plumbing and electrical works. Please look at the quote and let me know whether it is within range, especially the labour costs. I plan to discuss it with him this afternoon and would appreciate your views before I meet him. You can see from the time I am making this post that I have not been able to sleep since he sent this quote. I don't really have time to go to the market to check these prices, I will allow him buy them if the prices are not way off. But the cost of labour seems high to me. The site is in Enugu.

MECHANICAL/ PLUMBING CONDUIT PIPING
1. 4” Pipe 52 lengths @1650 85,800.00
2. 11/2 “ pipe ( waste) 28 lengths @800 22,400.00
3. 11/4 “ pressure pipe 19lengths @800 15,200.00
4. 1” pressure pipe 35lenghts @1700 59,500.00
5. ¾ pipe 18lengths @1200 21,600.00
6. ½ “ pipe 8lengths @800 6400.00
7. 4” Bend 32nos @800 25,600.00
8. 11/2 bend 48 nos @250 12,000.00
9. 11/4 elbow 20nos @200 4,000.00
10. ¾ elbow 90 nos @50 4,500.00
11. 1” elbow 40nos @100 4,000.00
12. ½” elbow 40 nos @40 1,600.00
13. 11/4 Tee 10nos @200 2,000.00
14. 1” Tee 20nos @100 2,000.00
15. ¾ Tee 50nos @50 2,500.00
16. ½” Tee 40nos @40 1,600.00
17. 4” X 45o 14nos @600 8,400.00
18. 11/2 X 18nos @200 3,600.00
19. 11/4 X 1” elbow 18nos @200 3,600.00
20. 1” X ¾ elbow 24nos @100 2,400.00
21. ¾ X ½ elbow 24nos @50 1,200.00
22. 11/4 X 1” Tee 18nos @200 3,600.00
23. 1” X ¾ Tee 10nos @100 1,000.00
24. ¾ X ½ Tee 24nos @50 1,200.00
25. ½” Tick pipe white 24nos @1200 28,800.00
26. 4”blue tick pipe 1 @2300 23,000.00
27. ¾ female elbow 24nos @50 1,200.00
28. ½” female elbow 24nos @40 960.00
29. 11/2 Tee plug 34nos @400 13,600.00
30. ¾ stop cock 14 @1300 18,200.00
31. ¾ adapter 28 @60 1,680.00
32. Tangit gum medium 19tins @1700 32,300.00
33. Yarn 3 @200 600.00
34. 11/2 Y-Tee 18 @400 72,000.00
35. Floor waste 3 @500 1,500.00
36. 3”pipe A.C 27 @800 21,600.00
37. 3”x 45o 36 @450 16,200.00
38. 3”plug 40 @50 2,000.00
Transportation of materials 6000
TOTAL 450,840.00
Labour 230,000.00
GRAND TOTAL 680,840.00


ELECTRICAL CONDUIT PIPING
1. 20mm Niger pipe 55bundles @9000 495,000.00
2. 25mm ‘’ ‘’ 3 bundles @7000 21,000.00
3. 20mm male bush 8pkts @1200 9,600.00
4. 3 x3 knock out box 18pkts @600 10,800.00
5. 3 x 6 knock out box 4pkts @600 2,400.00
6. couplin 8pkts @1000 8,000
7. U way box 16pkts @1000 16000
8. Y way box 15pkts @1000 15000
9. 20mm 4 way box 11pkts @1400 15000
10. Looping Box 8pkts @1000 8000
11. Union Gum 11tins @800 8800
12. 6 x6 adaptable 5pkts @700 3500
13. 4 x 4 adaptable 5pkts @500 2500
14. 6 x 9 Adaptable 7pkts @900 6300
15. Cooker Unit Box 4 @800 3200
16. D8 consumer unit box(smart) 2 @40000 80000
17. Tee Box 10pkts @1000 10,000
18. Thru Box 5pkts @1000 5,000
19. D4 Consumer unit box (smart) 2 @35000 70000
20. Copper arrestor 2ft @12500 12500
21. Cooper basket @5000 5000
22. Industrial salt 1bag @3500 3500
23. Charcoal 1bag @1500 1500
24. Copper belt 80ft @750 60000
25. Transportation 5000
TOTAL 877,600

LABOUR 210000
SUPERVISION 50000
TOTAL 1,137,600.00
Re: New 6 Bedroom Duplex Construction By Tigerkenn Homes by spyder880(m): 3:49am On Mar 31, 2017
Onyema1:
@spyder880, please can you review this quote for plumbing works and electrical and help me out. I am doing the wordwork for roofing my 8 all ensuite bed room duplex. Now my builder has sent me this quote for the plumbing and electrical works. Please look at the quote and let me know whether it is within range, especially the labour costs. I plan to discuss it with him this afternoon and would appreciate your views before I meet him. You can see from the time I am making this post that I have not been able to sleep since he sent this quote. I don't really have time to go to the market to check these prices, I will allow him buy them if the prices are not way off. But the cost of labour seems high to me. The site is in Enugu.

MECHANICAL/ PLUMBING CONDUIT PIPING
1. 4” Pipe 52 lengths @1650 85,800.00
2. 11/2 “ pipe ( waste) 28 lengths @800 22,400.00
3. 11/4 “ pressure pipe 19lengths @800 15,200.00
4. 1” pressure pipe 35lenghts @1700 59,500.00
5. ¾ pipe 18lengths @1200 21,600.00
6. ½ “ pipe 8lengths @800 6400.00
7. 4” Bend 32nos @800 25,600.00
8. 11/2 bend 48 nos @250 12,000.00
9. 11/4 elbow 20nos @200 4,000.00
10. ¾ elbow 90 nos @50 4,500.00
11. 1” elbow 40nos @100 4,000.00
12. ½” elbow 40 nos @40 1,600.00
13. 11/4 Tee 10nos @200 2,000.00
14. 1” Tee 20nos @100 2,000.00
15. ¾ Tee 50nos @50 2,500.00
16. ½” Tee 40nos @40 1,600.00
17. 4” X 45o 14nos @600 8,400.00
18. 11/2 X 18nos @200 3,600.00
19. 11/4 X 1” elbow 18nos @200 3,600.00
20. 1” X ¾ elbow 24nos @100 2,400.00
21. ¾ X ½ elbow 24nos @50 1,200.00
22. 11/4 X 1” Tee 18nos @200 3,600.00
23. 1” X ¾ Tee 10nos @100 1,000.00
24. ¾ X ½ Tee 24nos @50 1,200.00
25. ½” Tick pipe white 24nos @1200 28,800.00
26. 4”blue tick pipe 1 @2300 23,000.00
27. ¾ female elbow 24nos @50 1,200.00
28. ½” female elbow 24nos @40 960.00
29. 11/2 Tee plug 34nos @400 13,600.00
30. ¾ stop cock 14 @1300 18,200.00
31. ¾ adapter 28 @60 1,680.00
32. Tangit gum medium 19tins @1700 32,300.00
33. Yarn 3 @200 600.00
34. 11/2 Y-Tee 18 @400 72,000.00
35. Floor waste 3 @500 1,500.00
36. 3”pipe A.C 27 @800 21,600.00
37. 3”x 45o 36 @450 16,200.00
38. 3”plug 40 @50 2,000.00
Transportation of materials 6000
TOTAL 450,840.00
Labour 230,000.00
GRAND TOTAL 680,840.00


ELECTRICAL CONDUIT PIPING
1. 20mm Niger pipe 55bundles @9000 495,000.00
2. 25mm ‘’ ‘’ 3 bundles @7000 21,000.00
3. 20mm male bush 8pkts @1200 9,600.00
4. 3 x3 knock out box 18pkts @600 10,800.00
5. 3 x 6 knock out box 4pkts @600 2,400.00
6. couplin 8pkts @1000 8,000
7. U way box 16pkts @1000 16000
8. Y way box 15pkts @1000 15000
9. 20mm 4 way box 11pkts @1400 15000
10. Looping Box 8pkts @1000 8000
11. Union Gum 11tins @800 8800
12. 6 x6 adaptable 5pkts @700 3500
13. 4 x 4 adaptable 5pkts @500 2500
14. 6 x 9 Adaptable 7pkts @900 6300
15. Cooker Unit Box 4 @800 3200
16. D8 consumer unit box(smart) 2 @40000 80000
17. Tee Box 10pkts @1000 10,000
18. Thru Box 5pkts @1000 5,000
19. D4 Consumer unit box (smart) 2 @35000 70000
20. Copper arrestor 2ft @12500 12500
21. Cooper basket @5000 5000
22. Industrial salt 1bag @3500 3500
23. Charcoal 1bag @1500 1500
24. Copper belt 80ft @750 60000
25. Transportation 5000
TOTAL 877,600

LABOUR 210000
SUPERVISION 50000
TOTAL 1,137,600.00



What! This quote for only your house or for the whole houses on your street or town? cheesy

I stopped reading when I saw 55 bundles of electrical pipes, that should be enough for at least 7 big houses.

The workmanship is wayy to much, and he still added supervision to it.

Renegotiate the whole quote.

1 Like

Re: New 6 Bedroom Duplex Construction By Tigerkenn Homes by spyder880(m): 3:56am On Mar 31, 2017
Completing the foundation.........

Re: New 6 Bedroom Duplex Construction By Tigerkenn Homes by spyder880(m): 4:04am On Mar 31, 2017
The type of stone we are digging out from inside this land is in no way indicative of the firmness. This soil is notoriously weak and we are planning on a foundation type that will provide a firm footing for this house.

Re: New 6 Bedroom Duplex Construction By Tigerkenn Homes by spyder880(m): 4:08am On Mar 31, 2017
We are getting the reinforcements and materials ready, my whole crew are on their way to this site..........

Re: New 6 Bedroom Duplex Construction By Tigerkenn Homes by spyder880(m): 7:33am On Mar 31, 2017
More work ongoing this morning as we start the column base excavations.
Re: New 6 Bedroom Duplex Construction By Tigerkenn Homes by Onyema1(m): 4:46pm On Mar 31, 2017
@Spyder880, as I mentioned, I sent you an e-mail check and respond. I have attached the picture of the house. Woodworks have advanced on the roofing though. I would like you to step in from wall rending and plastering if I can get a better deal and good work. To be fair, the guy so far is doing a good work, his labour cost is just too high for me. And he doesn't break it down for me to know the application of the bulk labour charges. I pay for supervision but he is hardly there, he leaves his foreman there and attend to other jobs - drives me crazy. I pay for ferari and he gives me bittles.


spyder880:


What! This quote for only your house or for the whole houses on your street or town? cheesy

I stopped reading when I saw 55 bundles of electrical pipes, that should be enough for at least 7 big houses.

The workmanship is wayy to much, and he still added supervision to it.

Renegotiate the whole quote.

1 Like

Re: New 6 Bedroom Duplex Construction By Tigerkenn Homes by Onyema1(m): 4:49pm On Mar 31, 2017
Sorry I am not able to upload the picture here, it seems too heavy for it.

Onyema1:
@Spyder880, as I mentioned, I sent you an e-mail check and respond. I have attached the picture of the house. Woodworks have advanced on the roofing though. I would like you to step in from wall rending and plastering if I can get a better deal and good work. To be fair, the guy so far is doing a good work, his labour cost is just too high for me. And he doesn't break it down for me to know the application of the bulk labour charges. I pay for supervision but he is hardly there, he leaves his foreman there and attend to other jobs - drives me crazy. I pay for ferari and he gives me bittles.


Re: New 6 Bedroom Duplex Construction By Tigerkenn Homes by spyder880(m): 6:46am On Apr 02, 2017
We are done with most column bases here, note how deep we made them be............

Re: New 6 Bedroom Duplex Construction By Tigerkenn Homes by spyder880(m): 6:48am On Apr 02, 2017
We are breaking a lot of stones from inside this foundation, we are using special tools to chisel the stones till it breaks.

1 Like

Re: New 6 Bedroom Duplex Construction By Tigerkenn Homes by spyder880(m): 6:50am On Apr 02, 2017
Getting ready with our materials........

Re: New 6 Bedroom Duplex Construction By Tigerkenn Homes by spyder880(m): 6:54am On Apr 02, 2017
We first did a filling with sharp sand, before the blinding was done, then we placed the floor mat, and starter bars. note the type of starter bars we use.......

Re: New 6 Bedroom Duplex Construction By Tigerkenn Homes by spyder880(m): 6:58am On Apr 02, 2017
More ........

Re: New 6 Bedroom Duplex Construction By Tigerkenn Homes by Yels: 11:07pm On Apr 02, 2017
@Spyder: Nice one spyder. Please what is the size of the plot for this 6 Bedroom Duplex Project?

1 Like

Re: New 6 Bedroom Duplex Construction By Tigerkenn Homes by BilginMarble(m): 11:45am On Apr 03, 2017
We are marble, onyx, travertine, granite manufacturer and exporter company from Turkey from our own quarries and factory.
Our abilities are supplying natural stones marble, Onyx and Granite as slabs, cut to size, custom dimensions and shapes as kitchen top, bathroom tops, bar designs etc. Other way is that: if you have any project, we may join with designing, application; especially villas, hotel and restaurants, office buildings etc. Depends on your position in market. My whatsapp is +905327607234 for more information and pictures.
And you may see our selections from following link:
https://www.facebook.com/exportmarble/?fref=ts
https://www.facebook.com/bilgin.muhendislik/photos_albums

Best Regards,
Eng Kayhan
www.bilginmuhendisliktr.com

1 Like

Re: New 6 Bedroom Duplex Construction By Tigerkenn Homes by MaxNdu: 11:53am On Apr 03, 2017
spyder880:
We are breaking a lot of stones from inside this foundation, we are using special tools to chisel the stones till it breaks.

grin cheesy wink I definitely recognise that hand. Its the hand that does great buildings at interesting speed. More power to your elbow Spyder, still praying for the time you will be starting my own project for me in Owerri.

2 Likes

Re: New 6 Bedroom Duplex Construction By Tigerkenn Homes by spyder880(m): 7:53am On Apr 06, 2017
MaxNdu:


grin cheesy wink I definitely recognise that hand. Its the hand that does great buildings at interesting speed. More power to your elbow Spyder, still praying for the time you will be starting my own project for me in Owerri.

Thank you bro, i will be looking forward to your call.
Re: New 6 Bedroom Duplex Construction By Tigerkenn Homes by spyder880(m): 7:55am On Apr 06, 2017
Yels:
@Spyder: Nice one spyder. Please what is the size of the plot for this 6 Bedroom Duplex Project?

This plot is about 800 sqm.
Re: New 6 Bedroom Duplex Construction By Tigerkenn Homes by spyder880(m): 8:02am On Apr 06, 2017
Foundation blinding with concrete...........

1 Share

Re: New 6 Bedroom Duplex Construction By Tigerkenn Homes by spyder880(m): 8:11am On Apr 06, 2017
On top of the concrete blinding, we did a ground reinforcement in preparation for a ground beam.........

(1) (2) (3) (4) (5) (6) (7) (8) (9) (Reply)

4 Bedroom Bungalow Enquiries on Design, Construction and Cost / How To Buy A Lagos State Government Residential Housing Scheme. Dos And Donts / Beechwood Estate Another Hidden Treasure That Is Unbelievably Priced

(Go Up)

Sections: politics (1) business autos (1) jobs (1) career education (1) romance computers phones travel sports fashion health
religion celebs tv-movies music-radio literature webmasters programming techmarket

Links: (1) (2) (3) (4) (5) (6) (7) (8) (9) (10)

Nairaland - Copyright © 2005 - 2024 Oluwaseun Osewa. All rights reserved. See How To Advertise. 46
Disclaimer: Every Nairaland member is solely responsible for anything that he/she posts or uploads on Nairaland.