Welcome, Guest: Register On Nairaland / LOGIN! / Trending / Recent / New
Stats: 3,152,669 members, 7,816,750 topics. Date: Friday, 03 May 2024 at 04:22 PM

CONSTRUCTION PROCESS OF TERRACE BUILDING &BLOCK OF FLAT AT LEKKI - Properties (63) - Nairaland

Nairaland Forum / Nairaland / General / Properties / CONSTRUCTION PROCESS OF TERRACE BUILDING &BLOCK OF FLAT AT LEKKI (226271 Views)

PILLING:CONSTRUCTION PROCESS OF TRIPLET WITH BLOCK OF FLAT AT LEKKI / PILE FOUNDATION FOR TERRACE BUILDING AT LEKKI / Construction Process Of A Wing Duplex+flat At Ajah (2) (3) (4)

(1) (2) (3) ... (60) (61) (62) (63) (64) (65) (66) ... (101) (Reply) (Go Down)

Re: CONSTRUCTION PROCESS OF TERRACE BUILDING &BLOCK OF FLAT AT LEKKI by Bodlade(m): 10:06am On Nov 09, 2017
CURRENT PRICES FOR MATERIALS

Cement Supplies (Dangote)
2600 per bag (transport inclusive for 300 bags upward)
2650 per bag (transport inclusive for 200 bags)

Granite Supplies
30 tons to Redeem Camp: =N=116,000
30 tons to Mowe/Ibafo : =N=120,000
30 tons to Berger Lagos: =N=125,000
30 tons to Lagos Mainland: =N=128,000
30 tons to Lagos Island: =N=140,000

Stone Dust Supplies
30 tons : 78,000

Sharp Sand Supplies
20 tons to Redeem Camp: =N=45,000
20 tons to Mowe/Ibafo : =N=47,000
20 tons to Berger Lagos: =N=47,000

Dagbolu Sand Supplies
20 tons to Redeem Camp: =N=35,000
20 tons to Mowe/Ibafo : =N=35,000


Plaster Sand Supplies
20 tons to Redeem Camp: =N=32,000
20 tons to Mowe : =N=33,000
20 tons to Ibafo : =N=36,000
20 tons to Berger Lagos: =N=38,000

Fillings/Laterite Supplies
20 tons to Redeem Camp: =N=15,000
20 tons to Mowe : =N=18,000
20 tons to Ibafo : =N=20,000
20 tons to Berger Lagos: =N=23,000

1x12 wood= 1250
2x2 wood=250
2x3 wood=350
Bamboo=200
Nail=9000 per bag

Iron rod
12mm= 150,000/ton
16mm= 150,000/ton
10mm= 155,000/ton

For your supplies ( Full & accurate )
Call Sorted Impact Company on
08020535537, 08077257811
Address: Flat 4, Delta province chalet, Redeem camp.

**INTEGRITY IS OUR WATCHWORD**
Re: CONSTRUCTION PROCESS OF TERRACE BUILDING &BLOCK OF FLAT AT LEKKI by GREATESTPIANIST: 4:02pm On Nov 22, 2017
segcymoor:
Cool floor
pls sir, did dis project start since 2012?
Re: CONSTRUCTION PROCESS OF TERRACE BUILDING &BLOCK OF FLAT AT LEKKI by abbatoir(m): 6:11pm On Feb 03, 2018
GREATESTPIANIST:
pls sir, did dis project start since 2012?
No Sir, this is the compilation of our major project since 2012...as a matter of fact, we should be adding another shortly...
Re: CONSTRUCTION PROCESS OF TERRACE BUILDING &BLOCK OF FLAT AT LEKKI by GREATESTPIANIST: 1:51am On Feb 04, 2018
abbatoir:

No Sir, this is the compilation of our major project since 2012...as a matter of fact, we should be adding another shortly...
okay
Re: CONSTRUCTION PROCESS OF TERRACE BUILDING &BLOCK OF FLAT AT LEKKI by abbatoir(m): 8:47pm On Feb 07, 2018
Good to back here....
Having fully sale off the last terraces built we set to proceed with the 3 no's of detached house just by Lekki county estate, Ikota, Lekki

MOORE-DESIGNBUILD LTD
... we do structures right!

Re: CONSTRUCTION PROCESS OF TERRACE BUILDING &BLOCK OF FLAT AT LEKKI by abbatoir(m): 8:54pm On Feb 07, 2018
Interior Architecture!

Guys,we are back but for better.
.Trust me!

1 Like

Re: CONSTRUCTION PROCESS OF TERRACE BUILDING &BLOCK OF FLAT AT LEKKI by twinskenny(m): 10:45pm On Feb 07, 2018
abbatoir:
Good to back here....
Having fully sale off the last terraces built we set to proceed with the 3 no's of detached house just by Lekki county estate, Ikota, Lekki

MOORE-DESIGNBUILD LTD
... we do structures right!


beautiful boss
congratulations
Re: CONSTRUCTION PROCESS OF TERRACE BUILDING &BLOCK OF FLAT AT LEKKI by skimanski(m): 9:45am On Feb 08, 2018
Its been a while boss, we miss you here.
Re: CONSTRUCTION PROCESS OF TERRACE BUILDING &BLOCK OF FLAT AT LEKKI by skimanski(m): 9:45am On Feb 08, 2018
abbatoir:
Good to back here....
Having fully sale off the last terraces built we set to proceed with the 3 no's of detached house just by Lekki county estate, Ikota, Lekki

MOORE-DESIGNBUILD LTD
... we do structures right!


Lovely Design
Re: CONSTRUCTION PROCESS OF TERRACE BUILDING &BLOCK OF FLAT AT LEKKI by abbatoir(m): 9:46pm On Feb 08, 2018
skimanski:
Its been a while boss, we miss you here.
Thanks.. Well done so far
Re: CONSTRUCTION PROCESS OF TERRACE BUILDING &BLOCK OF FLAT AT LEKKI by abbatoir(m): 9:47pm On Feb 08, 2018
twinskenny:


beautiful boss
congratulations
Quite a while Kenny...
Re: CONSTRUCTION PROCESS OF TERRACE BUILDING &BLOCK OF FLAT AT LEKKI by twinskenny(m): 10:19pm On Feb 08, 2018
abbatoir:

Quite a while Kenny...

we are still sstanding sir.. how is it going?
Re: CONSTRUCTION PROCESS OF TERRACE BUILDING &BLOCK OF FLAT AT LEKKI by Bodlade(m): 9:02am On Feb 09, 2018
CURRENT PRICES FOR MATERIALS

Cement Supplies (Dangote)
2500 per bag (transport inclusive for 300 bags upward)
2550 per bag (transport inclusive for 200 bags)

Granite Supplies
30 tons to Redeem Camp: =N=120,000
30 tons to Mowe/Ibafo : =N=123,000
30 tons to Berger Lagos: =N=125,000
30 tons to Lagos Mainland: =N=130000-135000
30 tons to Lagos Island: =N=145,000
30 tons to Ajah & Beyond: =N=150000-170000

Stone Dust Supplies
30 tons : 75,000 and above

Sharp Sand Supplies
20 tons to Redeem Camp: =N=45,000
20 tons to Mowe/Ibafo/Arepo : =N=47,000-50,000
20 tons to Berger Lagos: =N=48,000

Dagbolu Sand Supplies
20 tons to Redeem Camp: =N=35,000
20 tons to Mowe/Ibafo : =N=35,000-38000


Plaster Sand Supplies
20 tons to Redeem Camp: =N=30,000
20 tons to Mowe : =N=32,000-35,000
20 tons to Ibafo : =N=36,000
20 tons to Berger Lagos: =N=38,000

Fillings/Laterite Supplies
20 tons to Redeem Camp: =N=15,000
20 tons to Mowe : =N=18,000
20 tons to Ibafo : =N=20,000
20 tons to Berger Lagos: =N=23,000

1x12 wood= 1250
2x2 wood=250
2x3 wood=350
Bamboo=200
Nail=9000 per bag

Iron rod
12mm= 180,000/ton
16mm= 180,000/ton
10mm= 185,000/ton

For your supplies ( Full & accurate )
Call Sorted Impact Company on
08020535537, 08077257811
Address: Flat 4, Delta province chalet, Redeem camp.

**INTEGRITY IS OUR WATCHWORD**
Re: CONSTRUCTION PROCESS OF TERRACE BUILDING &BLOCK OF FLAT AT LEKKI by abbatoir(m): 9:43pm On Feb 10, 2018
Activities on going:
Preliminary work
Setting out



------
Update shortly
Re: CONSTRUCTION PROCESS OF TERRACE BUILDING &BLOCK OF FLAT AT LEKKI by EndiaSami: 9:47pm On Feb 13, 2018
abbatoir:
Good to back here....
Having fully sale off the last terraces built we set to proceed with the 3 no's of detached house just by Lekki county estate, Ikota, Lekki

MOORE-DESIGNBUILD LTD
... we do structures right!


Congratulations BOSS.
Re: CONSTRUCTION PROCESS OF TERRACE BUILDING &BLOCK OF FLAT AT LEKKI by Chekitaut: 12:17am On Feb 14, 2018
The popular 5/8 Granite a.k.a 3/4down price will change from today now 2,400/ton
Hence 30tons to:-

Mainland @N148,000
V.I, Island, Lekki altru Ajah @N160,000

all other sizes remain the same.
Re: CONSTRUCTION PROCESS OF TERRACE BUILDING &BLOCK OF FLAT AT LEKKI by abbatoir(m): 1:24pm On Feb 14, 2018
EndiaSami:


Congratulations BOSS.
Thank guy..we go contact u for finishing as usual

1 Like

Re: CONSTRUCTION PROCESS OF TERRACE BUILDING &BLOCK OF FLAT AT LEKKI by abbatoir(m): 5:39am On Feb 15, 2018
Excavation process

Re: CONSTRUCTION PROCESS OF TERRACE BUILDING &BLOCK OF FLAT AT LEKKI by abbatoir(m): 5:41am On Feb 15, 2018
Conctrete Blinding

Re: CONSTRUCTION PROCESS OF TERRACE BUILDING &BLOCK OF FLAT AT LEKKI by abbatoir(m): 5:43am On Feb 15, 2018
Rebars...

Re: CONSTRUCTION PROCESS OF TERRACE BUILDING &BLOCK OF FLAT AT LEKKI by abbatoir(m): 5:45am On Feb 15, 2018
Delivery of trailer of cement

Re: CONSTRUCTION PROCESS OF TERRACE BUILDING &BLOCK OF FLAT AT LEKKI by Aventures(m): 11:15am On Feb 15, 2018
@moore, ride on bros.
Re: CONSTRUCTION PROCESS OF TERRACE BUILDING &BLOCK OF FLAT AT LEKKI by abbatoir(m): 9:02pm On Feb 15, 2018
Chekitaut:
The popular 5/8 Granite a.k.a 3/4down price will change from today now 2,400/ton
Hence 30tons to:-

Mainland @N148,000
V.I, Island, Lekki altru Ajah @N160,000

all other sizes remain the same.
Noted!
Re: CONSTRUCTION PROCESS OF TERRACE BUILDING &BLOCK OF FLAT AT LEKKI by abbatoir(m): 6:46pm On Feb 16, 2018
Aventures:
@moore, ride on bros.
Baba..how runs?
Re: CONSTRUCTION PROCESS OF TERRACE BUILDING &BLOCK OF FLAT AT LEKKI by abbatoir(m): 9:38pm On Feb 18, 2018
Men at works...

Re: CONSTRUCTION PROCESS OF TERRACE BUILDING &BLOCK OF FLAT AT LEKKI by abbatoir(m): 9:43pm On Feb 18, 2018
Arrival of the steel panel...

Re: CONSTRUCTION PROCESS OF TERRACE BUILDING &BLOCK OF FLAT AT LEKKI by Rubbiish(m): 9:47pm On Feb 18, 2018
abbatoir:
Arrival of the steel panel...
The oga patapata for building...the pioneer....i salute u sir...
I have a question; When doing this beam raft, why don't u guys do pad footings for the columns?
Re: CONSTRUCTION PROCESS OF TERRACE BUILDING &BLOCK OF FLAT AT LEKKI by abbatoir(m): 9:56pm On Feb 18, 2018
Rubbiish:

The oga patapata for building...the pioneer....i salute u sir...
I have a question; When doing this beam raft, why don't u guys do pad footings for the columns?
Some things were not expected to be done any how sir...This is strictly raft foundation suitable for this particular land.
Re: CONSTRUCTION PROCESS OF TERRACE BUILDING &BLOCK OF FLAT AT LEKKI by abbatoir(m): 9:59pm On Feb 18, 2018
Detailling work on angular design...

Re: CONSTRUCTION PROCESS OF TERRACE BUILDING &BLOCK OF FLAT AT LEKKI by Rubbiish(m): 10:01pm On Feb 18, 2018
abbatoir:

Some things were not expected to be done any how sir...This is strictly raft foundation suitable for this particular land.
True sir
Just want to know if all starter bars for the columns must start from the raft beam & not from a base below?
Re: CONSTRUCTION PROCESS OF TERRACE BUILDING &BLOCK OF FLAT AT LEKKI by abbatoir(m): 10:03pm On Feb 18, 2018
Our concept...




-----
MOORE-DESIGNBUILD LTD
...we do structures rights!

Re: CONSTRUCTION PROCESS OF TERRACE BUILDING &BLOCK OF FLAT AT LEKKI by abbatoir(m): 10:07pm On Feb 18, 2018
Rubbiish:

True sir
Just want to know if all starter bars for the columns must start from the raft beam & not from a base below?

The rebars below actually serve the purpose of what u consider as pad.that is why it is very crucial the starter bar must well placed on that 16mm below

1 Like

(1) (2) (3) ... (60) (61) (62) (63) (64) (65) (66) ... (101) (Reply)

Prices For These Paints / How Large Is 'A Plot' Of Land? / Best Architectural, Interior And Construction Works

(Go Up)

Sections: politics (1) business autos (1) jobs (1) career education (1) romance computers phones travel sports fashion health
religion celebs tv-movies music-radio literature webmasters programming techmarket

Links: (1) (2) (3) (4) (5) (6) (7) (8) (9) (10)

Nairaland - Copyright © 2005 - 2024 Oluwaseun Osewa. All rights reserved. See How To Advertise. 30
Disclaimer: Every Nairaland member is solely responsible for anything that he/she posts or uploads on Nairaland.