PILLING:CONSTRUCTION PROCESS OF TRIPLET WITH BLOCK OF FLAT AT LEKKI by segcymoor(m): 4:45pm On Mar 16, 2015 |
We set to embark on the construction process of Triplet with block of flats. As usual we advise our clients to carried out soil test and investigation because the subject site is questionable to carry 2 slab. From the result, we decided to adopt short bore pile. The contract agreement has been signed after various discussion with our clients.. In the process of this construction, you will see where over 16 nos of 16mm reinforcement is being used for beam as against normal 4 or 6 . .........watch out as we proceed! MOORE - DESIGNBUILD LTD | We do structure right! 1 Like 1 Share |
Re: PILLING:CONSTRUCTION PROCESS OF TRIPLET WITH BLOCK OF FLAT AT LEKKI by segcymoor(m): 8:48pm On Mar 16, 2015 |
DAY 1:Mobilisation
|
Re: PILLING:CONSTRUCTION PROCESS OF TRIPLET WITH BLOCK OF FLAT AT LEKKI by segcymoor(m): 6:44am On Mar 17, 2015 |
Artistic impression for the proposed development! 1 Share
|
Re: PILLING:CONSTRUCTION PROCESS OF TRIPLET WITH BLOCK OF FLAT AT LEKKI by eudoh940(m): 8:24am On Mar 17, 2015 |
Good mng boss. Nice one. Pls sir keep us updated.. Tnks. I am following Patiently 1 Like |
Re: PILLING:CONSTRUCTION PROCESS OF TRIPLET WITH BLOCK OF FLAT AT LEKKI by segcymoor(m): 9:54am On Mar 17, 2015 |
eudoh940:Definitely! |
Re: PILLING:CONSTRUCTION PROCESS OF TRIPLET WITH BLOCK OF FLAT AT LEKKI by mufutau55(m): 3:01pm On Mar 17, 2015 |
This design is very nice... keeping my eyes on the construction.. Hajji M. |
Re: PILLING:CONSTRUCTION PROCESS OF TRIPLET WITH BLOCK OF FLAT AT LEKKI by segcymoor(m): 5:53pm On Mar 17, 2015 |
Delivered of reinforcement
|
Re: PILLING:CONSTRUCTION PROCESS OF TRIPLET WITH BLOCK OF FLAT AT LEKKI by Onuokwu: 7:33pm On Mar 17, 2015 |
segcymoor: Any idea about the size of the plot? |
Re: PILLING:CONSTRUCTION PROCESS OF TRIPLET WITH BLOCK OF FLAT AT LEKKI by segcymoor(m): 10:12am On Mar 18, 2015 |
Onuokwu:Virtually a plot |
Re: PILLING:CONSTRUCTION PROCESS OF TRIPLET WITH BLOCK OF FLAT AT LEKKI by segcymoor(m): 2:37pm On Mar 18, 2015 |
DAY 2:setting out of piling points
|
Re: PILLING:CONSTRUCTION PROCESS OF TRIPLET WITH BLOCK OF FLAT AT LEKKI by segcymoor(m): 4:37pm On Mar 18, 2015 |
Establishing pilling points. ..........ensuring getting it right from the onset
|
Re: PILLING:CONSTRUCTION PROCESS OF TRIPLET WITH BLOCK OF FLAT AT LEKKI by eudoh940(m): 7:16am On Mar 19, 2015 |
Choi. I am missing alot o. I do enjoy this part of d project. Pegging of pile points. So interesting. But more interesting wen one is pegging in water. Smiles...... |
Re: PILLING:CONSTRUCTION PROCESS OF TRIPLET WITH BLOCK OF FLAT AT LEKKI by eudoh940(m): 7:24am On Mar 19, 2015 |
Tnk you sir. I learnt alot |
Re: PILLING:CONSTRUCTION PROCESS OF TRIPLET WITH BLOCK OF FLAT AT LEKKI by segcymoor(m): 5:54pm On Mar 19, 2015 |
We established piling machine. .....set to go!
|
Re: PILLING:CONSTRUCTION PROCESS OF TRIPLET WITH BLOCK OF FLAT AT LEKKI by segcymoor(m): 10:40am On Mar 20, 2015 |
DAY 3;first point
|
Re: PILLING:CONSTRUCTION PROCESS OF TRIPLET WITH BLOCK OF FLAT AT LEKKI by segcymoor(m): 10:45am On Mar 20, 2015 |
segcymoor:
|
Re: PILLING:CONSTRUCTION PROCESS OF TRIPLET WITH BLOCK OF FLAT AT LEKKI by segcymoor(m): 1:49pm On Mar 20, 2015 |
2nd point in progress! |
Re: PILLING:CONSTRUCTION PROCESS OF TRIPLET WITH BLOCK OF FLAT AT LEKKI by segcymoor(m): 7:36am On Mar 21, 2015 |
This particular piling is not far from our previous project: 450 diameter with 6m depth |
Re: PILLING:CONSTRUCTION PROCESS OF TRIPLET WITH BLOCK OF FLAT AT LEKKI by segcymoor(m): 5:24pm On Mar 24, 2015 |
Pilling work in progress!
|
Re: PILLING:CONSTRUCTION PROCESS OF TRIPLET WITH BLOCK OF FLAT AT LEKKI by Chekitaut: 11:15pm On Mar 24, 2015 |
Weldone... |
Re: PILLING:CONSTRUCTION PROCESS OF TRIPLET WITH BLOCK OF FLAT AT LEKKI by eudoh940(m): 7:21am On Mar 25, 2015 |
Weldone. Sir. Oga check it out I hail oo |
Re: PILLING:CONSTRUCTION PROCESS OF TRIPLET WITH BLOCK OF FLAT AT LEKKI by Chekitaut: 8:42pm On Mar 26, 2015 |
eudoh940:I thro salute bros... Oga segcymoor, we will do this again... Chekitaut, just accurate quantity materials you need for project... Call us: Cement, Granite, Sand, Iron Rod |
Re: PILLING:CONSTRUCTION PROCESS OF TRIPLET WITH BLOCK OF FLAT AT LEKKI by Chekitaut: 9:15pm On Mar 26, 2015 |
From Lagos-Island, Victoria-Island, Banana Island, Ikoyi, Lekki to Songotedo [size=14pt]Granite= N4,350/Ton[/size](Transportation Fee included) Minimum Order=60tons [size=14pt]Stone Dust= N2,800/ton[/size](Transportation Fee included) Minimum Order=60tons Call Now: 08055545355, 08032887233 |
Re: PILLING:CONSTRUCTION PROCESS OF TRIPLET WITH BLOCK OF FLAT AT LEKKI by segcymoor(m): 10:08pm On Mar 26, 2015 |
Grade 25 conctrete mixture
|
Re: PILLING:CONSTRUCTION PROCESS OF TRIPLET WITH BLOCK OF FLAT AT LEKKI by segcymoor(m): 10:11pm On Mar 26, 2015 |
Chekitaut:Will surely do.... |
Re: PILLING:CONSTRUCTION PROCESS OF TRIPLET WITH BLOCK OF FLAT AT LEKKI by segcymoor(m): 1:53pm On Mar 28, 2015 |
DAY:7 schedule to complete the Piling points by this coming week.
|
Re: PILLING:CONSTRUCTION PROCESS OF TRIPLET WITH BLOCK OF FLAT AT LEKKI by segcymoor(m): 9:25pm On Mar 31, 2015 |
I see a change.....where cement is being sold for a thousand! 3 Likes |
Re: PILLING:CONSTRUCTION PROCESS OF TRIPLET WITH BLOCK OF FLAT AT LEKKI by eudoh940(m): 9:22am On Apr 01, 2015 |
@#Boss as per builder concern. Hehehe |
Re: PILLING:CONSTRUCTION PROCESS OF TRIPLET WITH BLOCK OF FLAT AT LEKKI by jodeci01: 1:19am On Apr 02, 2015 |
Nice design! |
Re: PILLING:CONSTRUCTION PROCESS OF TRIPLET WITH BLOCK OF FLAT AT LEKKI by segcymoor(m): 9:05pm On Apr 02, 2015 |
We are rounding up the Pilling points tomorrow
|
Re: PILLING:CONSTRUCTION PROCESS OF TRIPLET WITH BLOCK OF FLAT AT LEKKI by segcymoor(m): 9:56pm On Apr 03, 2015 |
As schedule we round up the Pilling points
|
Re: PILLING:CONSTRUCTION PROCESS OF TRIPLET WITH BLOCK OF FLAT AT LEKKI by segcymoor(m): 5:06pm On Apr 06, 2015 |
Have a blessed Easter! 1 Like |
(1) (2) (3) (4) (5) (6) (7) (8) (9) (10) ... (43) (Reply)
Photos Of My Apartment After Renovation For Christmas -phoros / Most Expensive Real Estate Locations In Nigeria (2021) / I Built My Own House After Following Some Of Nairalanders' Advice
(Go Up)
Sections: politics (1) business autos (1) jobs (1) career education (1) romance computers phones travel sports fashion health religion celebs tv-movies music-radio literature webmasters programming techmarket Links: (1) (2) (3) (4) (5) (6) (7) (8) (9) (10) Nairaland - Copyright © 2005 - 2024 Oluwaseun Osewa. All rights reserved. See How To Advertise. 16 |