Properties / Re: Photo Diary 2: Ongoing Remodeling And Reconstruction Works. (COMPLETED!!!) by Josnac(m): 6:59am On Feb 27, 2020
Electrical piping..

Properties / Re: Photo Diary 2: Ongoing Remodeling And Reconstruction Works. (COMPLETED!!!) by Josnac(m): 8:21am On Feb 21, 2020
Hello guys, good morning and sorry for the delayed updates.
We've rounded up the roofing job, just been busy with other assignments.
Will bring more photos as soon as I can.

Properties / Re: Photo Diary 2: Ongoing Remodeling And Reconstruction Works. (COMPLETED!!!) by Josnac(m): 4:51pm On Feb 13, 2020
Roof woodworks..

Properties / Re: Photo Diary 2: Ongoing Remodeling And Reconstruction Works. (COMPLETED!!!) by Josnac(m): 2:01pm On Feb 10, 2020
Hello guys,
I'm back to the site today as we commence the roofing work.
There was a little adjustment during the block works and we had to increase the entrance porch to the pharmacy, thus our previous roof design was dropped in favour of the new one.

Josnac:
Pictures
1. Old building before commencement of work.
2-3. Expected final finishing barring any last minute changes.

So, here I've got a few photos to share as usual.
Suffice it to say my clients brother is a Carpenter, he's handling the woodworks here and I believe he can do justice to the roof.

Properties / Re: Photo Diary 2: Ongoing Remodeling And Reconstruction Works. (COMPLETED!!!) by Josnac(m): 8:15am On Feb 07, 2020
Good morning and sorry for the delayed updates. we have levelled up and roofing will commence by next Monday. Got a picture here and a video, but can't send the video.

Properties / Re: Photo Diary 2: Ongoing Remodeling And Reconstruction Works. (COMPLETED!!!) by Josnac(m): 12:05pm On Feb 04, 2020
Some updates for today.
Lintels are done, front beams and leveling are in progress.

Properties / Re: Photo Diary 2: Ongoing Remodeling And Reconstruction Works. (COMPLETED!!!) by Josnac(m): 12:02pm On Feb 04, 2020
Perfecttouchade:
Great work @josnac..We fabricate Aluminium windows in Casement, casement burglary embedded, sliding, curtain walls /windows. You can reach out to us via 08153665659 WhatsApp.. thanks

Okay Sir.
Properties / Re: Photo Diary 2: Ongoing Remodeling And Reconstruction Works. (COMPLETED!!!) by Josnac(m): 4:02pm On Feb 02, 2020
Like I said earlier at the beginning of the thread, the 3-D image is the target output of the remodeling project except of course if there were changes midway, well, such a change occurred and I will update the design image accordingly, but later.
Properties / Re: Photo Diary 2: Ongoing Remodeling And Reconstruction Works. (COMPLETED!!!) by Josnac(m): 3:56pm On Feb 02, 2020
UPDATES!!

Good afternoon and a happy Sunday.
Been unavoidably absent from site for a couple of days, just returned today and went straight to appraise the level of work done..a few pictures below.
pillars have been cast up to lintel levels, with lintel reinforcements placed on and firmly hooked at the joints.
Windows openings have also been clearly marked out, save for a couple of them and a door opening which unavoidably fell in the position of an old wall..they will be opened up after the walls are firmly secured.

1 Like 1 Share

Properties / Re: Photo Diary 2: Ongoing Remodeling And Reconstruction Works. (COMPLETED!!!) by Josnac(m): 3:56pm On Feb 02, 2020
UPDATES!!

Good afternoon and a happy Sunday.
Been unavoidably absent from site for a couple of days, just returned today and went straight to appraise the label of work done..a few pictures below.
Properties / Re: Photo Diary 2: Ongoing Remodeling And Reconstruction Works. (COMPLETED!!!) by Josnac(m): 10:36am On Jan 29, 2020
Good morning to everyone following, sorry I couldn't update yesterday ad I had assignments on another site to follow up.
On my return this morning, this is how far we've gone.

Properties / Re: Photo Diary 2: Ongoing Remodeling And Reconstruction Works. (COMPLETED!!!) by Josnac(m): 6:43pm On Jan 27, 2020
Afternoon updates..

Properties / Re: Photo Diary 2: Ongoing Remodeling And Reconstruction Works. (COMPLETED!!!) by Josnac(m): 10:22am On Jan 27, 2020
Good morning an welcome back after the weekend break.
Saturday saw us begin and finish the foundation blinding. Today we start block works while also preparing rebar.

Properties / Re: Photo Diary 2: Ongoing Remodeling And Reconstruction Works. (COMPLETED!!!) by Josnac(m): 2:36pm On Jan 25, 2020
Foundation concrete works (Blinding), iron works.

Properties / Re: Photo Diary 2: Ongoing Remodeling And Reconstruction Works. (COMPLETED!!!) by Josnac(m): 8:29am On Jan 25, 2020
Good morning.
We're continuing with excavations..plan is to round up today and then cast the foundation concrete.
Depth: External walls is 900mm
Internal walls is 600mm.

Properties / Re: Photo Diary 2: Ongoing Remodeling And Reconstruction Works. (COMPLETED!!!) by Josnac(m): 4:42pm On Jan 24, 2020
Excavations...

Properties / Re: Photo Diary 2: Ongoing Remodeling And Reconstruction Works. (COMPLETED!!!) by Josnac(m): 4:41pm On Jan 24, 2020
ArcToyin:
Well done!!! Did you put up any design for old and new structure?

Thank you.
First picture is the old structure, second and third pictures are the model for the proposed structure.
Properties / Re: Photo Diary 2: Ongoing Remodeling And Reconstruction Works. (COMPLETED!!!) by Josnac(m): 1:03pm On Jan 24, 2020
Today..we're removing the unnecessary wall and moving the debris away from site.
I'm optimistic we can as well begin excavations for the new walls needed ASAP.


More photo updates on the way...stay tuned.

Properties / Re: Photo Diary 2: Ongoing Remodeling And Reconstruction Works. (COMPLETED!!!) by Josnac(m): 12:59pm On Jan 24, 2020
Pictures
1. Old building before commencement of work.
2-3. Expected final finishing barring any last minute changes.

Properties / Photo Diary 2: Ongoing Remodeling And Reconstruction Works. (COMPLETED!!!) by Josnac(m): 12:57pm On Jan 24, 2020
Good afternoon and happy new year.
Welcome to my new photo diary of an ongoing remodeling job.
Project info:
Existing building had a pharmacy, a dispensing room, a store room, two small bedrooms and a lounge.

New structure is to have a pharmacy, one bedroom with convenience facilities, a store room, a dispensing room, a lounge and an extra convenience for pharmacy staffs.

Project Location: Azumini Ndoki I'm Ukwa East L.GA Abia State.
Estimated cost 4million naira.
Expected project duration: 1months and 3weeks.
Properties / Re: Photo Diary: Remodeling And Reconstruction Of An Old 4-bedroom Bungalow. by Josnac(m): 7:04pm On Jan 13, 2020
ITbomb:
That was fast, well it should be when money is available
You said you are yet to get the cost, that means you just mention the figure and it is provided

Pity the man had to die before the building was renovated

Sorry for the delayed response ITbomb..yea, funds were available as at when I needed it.
we spent just a bit over #3m on it.

1 Like

Properties / Re: Photo Diary: Remodeling And Reconstruction Of An Old 4-bedroom Bungalow. by Josnac(m): 10:31pm On Dec 23, 2019
debbydee:

Good job
Thank you @debbydee

1 Like

Properties / Re: Photo Diary: Remodeling And Reconstruction Of An Old 4-bedroom Bungalow. by Josnac(m): 7:49pm On Dec 23, 2019
Final photos... hope the hazy weather due to harmattan doesn't make it too blurry.

3 Likes

Properties / Re: Photo Diary: Remodeling And Reconstruction Of An Old 4-bedroom Bungalow. by Josnac(m): 6:42am On Dec 14, 2019
Hello, welcome back.
I initially planned to travel few days ago but it was put off...so here's a few more photo updates.

1 Like

Politics / Re: Femi Fani-kayode Replies Femi Adesina On Buhari Earning The Rank ‘major General’ by Josnac(m): 8:25pm On Dec 11, 2019
Hmmm...

Come FFK, I don tell you say you get bad mouth before

Properties / Re: Photo Diary: Remodeling And Reconstruction Of An Old 4-bedroom Bungalow. by Josnac(m): 8:43am On Dec 10, 2019
I must commend the doggedness and commitment of the guys working with me here..they deserve some real accolades.
Would be going off site today or tomorrow for some other engagements, so it means next updates would most probably be at the finished stage.
Thanks for staying tuned
Josnac

3 Likes

Properties / Re: Photo Diary: Remodeling And Reconstruction Of An Old 4-bedroom Bungalow. by Josnac(m): 8:36am On Dec 10, 2019
Updates:
All internal doors are fixed and being dressed.
Floors are primed in readiness for tiling...and we also commenced installation of the window hoods.
Everything about plastering is to be rounded up today hopefully, the burial fast approaches.

3 Likes

Politics / Re: NBS Report: Kogi Leads Gombe, Rivers As Most Corrupt State In Nigeria by Josnac(m): 7:48pm On Dec 08, 2019
Lol..
Nigerian police, those lots are wonderful.

They will park an "Anti-crime" patrol van in an abandoned filling station while operating a roadblock where vehicles pay between #50-#200 to pass.

This their number one position has been retained with vigor and pride.

2 Likes

Events / Re: Bleak Christmas Looms by Josnac(m): 7:39pm On Dec 08, 2019
Next level Christmas.. it will be a Christmas to remember.
Our God is alive!

modified:
Bia, where is fergie001??
FTC on your thread and I'm rightly qualified for a bag of "Osikapa Abia", throw in some G-oil and Tomatoes and my village people will give you a chieftaincy title this Christmas...
How e go be

5 Likes

Properties / Re: Photo Diary: Remodeling And Reconstruction Of An Old 4-bedroom Bungalow. by Josnac(m): 7:03pm On Dec 07, 2019
tonididdy:
Well done �
Thanks you Sir.
Properties / Re: Photo Diary: Remodeling And Reconstruction Of An Old 4-bedroom Bungalow. by Josnac(m): 6:37pm On Dec 07, 2019
We continue with the plastering, doors and window dressing.
Window hoods being moulded also while PVC ceiling is 90% complete.

1 Like

Properties / Re: Photo Diary: Remodeling And Reconstruction Of An Old 4-bedroom Bungalow. by Josnac(m): 12:20pm On Dec 05, 2019
Hum2020:
@josnac you are doing wonderful job there but I may ask how much is total cost of this building work and how is the cost of Labour's down in the east thanks

Thank you Sir.
To your question, we are yet to recalculate how much that has been spent so far..being a structure in the village, some materials like wood and sand were sourced locally at a far cheaper rate than what was in the initial estimates.
Now for labour in the East, I would say its relatively low based on how I work with my team. But I'm certain it differs from contractor to contractor.

2 Likes

(1) (2) (3) (4) (5) (6) (7) (8) (9) (10) (11) (of 24 pages)

(Go Up)

Sections: politics (1) business autos (1) jobs (1) career education (1) romance computers phones travel sports fashion health
religion celebs tv-movies music-radio literature webmasters programming techmarket

Links: (1) (2) (3) (4) (5) (6) (7) (8) (9) (10)

Nairaland - Copyright © 2005 - 2024 Oluwaseun Osewa. All rights reserved. See How To Advertise. 34
Disclaimer: Every Nairaland member is solely responsible for anything that he/she posts or uploads on Nairaland.