PropertiesRe: The Making Of The "Enugu Urban 5 Bedroom Duplex" by Nbg4real: 3:45pm On Jun 13, 2020
good afternoon please how many is five inches ok between door and area to ne tile i mean the floor. my interior doors (American panel doors) are5 inchs above the ground, is it ok pls?
PropertiesRe: PICK YOUR QUALITY WALL / FLOOR TILES HERE WITH PICTURE by Nbg4real: 3:43pm On Jun 13, 2020
good afternoon please how many is five inches ok between door and area to ne tile i mean the floor. my interior doors (American panel doors) are5 inchs above the ground, is it ok pls?
PropertiesRe: Best Of Price On Tiles,water Closet,pipes And Fitting Free Home Delivery by Nbg4real: 3:42pm On Jun 13, 2020
good afternoon please how many is five inches ok between door and area to ne tile i mean the floor. my interior doors (American panel doors) are5 inchs above the ground, is it ok pls?
PropertiesRe: General Topic Thread-To Discuss Anything And Everything in Building Construction by Nbg4real: 3:41pm On Jun 13, 2020
good afternoon please how many is five inches ok between door and area to ne tile i mean the floor. my interior doors (American panel doors) are5 inchs above the ground, is it ok pls?
PropertiesRe: General Topic Thread-To Discuss Anything And Everything in Building Construction by Nbg4real: 12:55pm On Jun 03, 2020
ChiefSupplier55:
Before tiling
thank you Sir
PropertiesRe: General Topic Thread-To Discuss Anything And Everything in Building Construction by Nbg4real: 10:00am On Jun 02, 2020
Good Morning house. Please when is it proper to install ameriacna panel door, before or after tiling?
PropertiesRe: General Topic Thread-To Discuss Anything And Everything in Building Construction by Nbg4real: 8:59am On May 21, 2020
[quote author=Adedward post=89764769]Boss, it's gud to install the windows before plaster, (1) so that the bricklayer can have anough chance to fill the provided places, with cements (2) if u are doing embedded casement with burglaries, u really have to do that, becouse most iron need to enter inside the wall before plaster, (3) all ur windows must install with lylon taper, to avoid dirty, thank you Sir
PropertiesRe: General Topic Thread-To Discuss Anything And Everything in Building Construction by Nbg4real: 9:24am On May 20, 2020
[quote author=saydfact post=89749371]It is better to rough plaster it, so you can protect the wall and also make the wall level for a good tiling work..

Goodluck[thank you Sir
PropertiesRe: General Topic Thread-To Discuss Anything And Everything in Building Construction by Nbg4real: 8:46am On May 20, 2020
Good Morning all. please is there any need for rough plaster for the walls that are going to be tiled like bathrooms, kitchen and exterior walls. or just leave it as it is?
PropertiesRe: General Topic Thread-To Discuss Anything And Everything in Building Construction by Nbg4real: 6:08am On May 19, 2020
[quote author=DFAMEGUY11S post=89706518]follow your engineer idea you can get the door and pack it then after plastering you can fix it [thank you Sir
PropertiesRe: The Making Of The "Enugu Urban 5 Bedroom Duplex" by Nbg4real: 6:07am On May 19, 2020
[quote author=spyder880 post=89706644]Good morning, apart from staining the doors and windows, there is also the increased risk of breaking the window glass. I have also seen where keys or handles were broken or damaged. It is always better to conclude plastering before doors and windows, except it you want to move into the house before completing the plastering process.

Better install the frames and doors at the same time. [thank you Sir]
PropertiesRe: The Making Of The "Enugu Urban 5 Bedroom Duplex" by Nbg4real: 4:45am On May 19, 2020
Good Morning all. @ Oga spyder Please i have 2 queations; 1) I roofed my house (4 bedroom duplex) i want to install windows and doors now as thier price is hacking. later i will do the plastering but the engineer surpervising the project insisted that i must plaster the whole house before installation of doors and windows. please what are pron and cons of my idea aprt from dirtying the windows and doors with cement?
2) In case of American panel door, can we install the frame only and later we mount the door or must we install it togather? thank you all.
PropertiesRe: General Topic Thread-To Discuss Anything And Everything in Building Construction by Nbg4real: 4:44am On May 19, 2020
Good Morning all. Please i have 2 queations; 1) i roofed my house (4 bedroom duplex) i want to install windows and doors now as thier price is hacking. later i will do the plastering but the engineer surpervising the project insisted that i must plaster the whole house before installation of doors and windows. please what are pron and cons of my idea aprt from dirtying the windows and doors with cement?
2) In case of American panel door, can we install the frame only and later we mount the door or must we install it togather? thank you all.
PropertiesRe: Plastering Of 5 Bedroom Duplex by Nbg4real: 8:47am On May 16, 2020
[quote author=murphyrichy post=74496381]Its more than Three much oga, I did same with 220k for plastering both inside and outside of the building, including the windows hoods as well. The guy did a perfect job for me. Please how many bag of cement did you used to plaster the whole building including under deck?
Business To BusinessRe: BUY ON EBAY.COM, AMAZON.COM, 1688, TAOBAO, ALIBABA - WE SHIP TO NIGERIA by Nbg4real: 6:06pm On May 06, 2020
please i need guide, I want to start mini importation of children wear and kitchen utensils. which estore.is best for beginner? amzon, alibaba 1688 or aliexpress? amd how can I go about it please.
HealthRe: Funeral Prayers For Multiples As Kano Death Toll Mounts by Nbg4real: 11:07am On Apr 25, 2020
Tissaia:
Fake news (also known as junk news, pseudo-news, or hoax news)[1][2] is a form of news consisting of deliberate disinformation or hoaxes spread via traditional news media (print and broadcast) or online social media.[3][4] Digital news has brought back and increased the usage of fake news, or yellow journalism.[5] The news is then often reverberated as misinformation in social media but occasionally finds its way to the mainstream media as well.[6]

Fake news is written and published usually with the intent to mislead in order to damage an agency, entity, or person, and/or gain financially or politically,[7][8][9] often using sensationalist, dishonest, or outright fabricated headlines to increase readership. Similarly, clickbait stories and headlines earn advertising revenue from this activity.[7]

The relevance of fake news has increased in post-truth politics. For media outlets, the ability to attract viewers to their websites is necessary to generate online advertising revenue. Publishing a story with false content that attracts users benefits advertisers and improves ratings. Easy access to online advertisement revenue, increased political polarization and the popularity of social media, primarily the Facebook News Feed,[3] have all been implicated in the spread of fake news,[7][10] which competes with legitimate news stories. Hostile government actors have also been implicated in generating and propagating fake news, particularly during elections.[11][12]

Confirmation bias and social media algorithms like those used on Facebook and Twitter further advance the spread of fake news. Modern impact is felt for example in vaccine hesitancy.[13]

Fake news undermines serious media coverage and makes it more difficult for journalists to cover significant news stories.[14] An analysis by BuzzFeed found that the top 20 fake news stories about the 2016 U.S. presidential election received more engagement on Facebook than the top 20 election stories from 19 major media outlets.[15] Anonymously-hosted fake news websites[3] lacking known publishers have also been criticized, because they make it difficult to prosecute sources of fake news for libel.[16]

The term "lying press"[17][18] is at times used to cast doubt upon legitimate news from an opposing political standpoint. During and after his presidential campaign and election, Donald Trump popularized the term "fake news" in this sense, regardless of the truthfulness of the news, when he used it to describe the negative press coverage of himself.[19][20] In part, as a result of Trump's misuse, the term has come under increasing criticism, and in October 2018 the British government decided that it will no longer use the term because it is "a poorly-defined and misleading term that conflates a variety of false information, from genuine error through to foreign interference in democratic processes."[21]
it is not fake news, I'm in contact with my relatives in kano, their are even seeking forgiveness incase they pass too. some are thinking it is maningities due to very hot weather.
PropertiesRe: General Topic Thread-To Discuss Anything And Everything in Building Construction by Nbg4real: 11:57am On Dec 24, 2019
twinskenny:
good step
thank you Sir. I thought it is a bad approach and i want it that way, that is why I asked. I'm Happy you regarded it as good step.
PropertiesRe: General Topic Thread-To Discuss Anything And Everything in Building Construction by Nbg4real: 11:09am On Dec 24, 2019
Good morning all. i just finished roofing my house and i want to put windows and doors before wiring and plumbing is there no be problem?
PropertiesRe: General Topic Thread-To Discuss Anything And Everything in Building Construction by Nbg4real: 2:48pm On Jun 27, 2019
jceesquare:
Tiling with air tight gaps in-between tiles and good moderate slope for drainage.
thank you, but is it possible to have an air tight tiling? sorry for my ignorance.
PropertiesRe: General Topic Thread-To Discuss Anything And Everything in Building Construction by Nbg4real: 1:00pm On Jun 27, 2019
Good Afternoon all. please house which is the best way to treat dampness on tank deck, tiling or pelting with (bitimus/ coaltar)?
PropertiesRe: General Topic Thread-To Discuss Anything And Everything in Building Construction by Nbg4real: 10:09am On May 17, 2019
please house how many sqaure meter is a buldle of PCV ceiling?
PropertiesRe: Calculating The Numbers Of Blocks You Need For Your Fence by Nbg4real: 9:31am On May 16, 2019
very cleared Sir, thank you.
PropertiesRe: Calculating The Numbers Of Blocks You Need For Your Fence by Nbg4real: 12:02pm On May 15, 2019
please if my room wall is 13 coaches including linter, what is the actual length in meters? i.e 9 coaches, linter and 3 coaches after linter.
PropertiesRe: General Topic Thread-To Discuss Anything And Everything in Building Construction by Nbg4real: 4:39pm On May 12, 2019
[quote author=Adaowerri111 post=78319574]I don't have the quote for woodwork, the 2*4 was 200, 2*2 150, Im not too sure of the rest, the first carpenter gave twice as much as what I spent, get estimates from different roofer, loof for roofers around and tell them you already got an estimate but you will to for lesser one, quotation for the metrotiles

quotation of metro tiles,total meter of metro tiles 180 and each is #2800=504000, reage cap 35 pieces by 2 miter, each #1500=#52500,cilant two packet=#5000,nail three packets=#15000,transport=#8000,labour=60,000,total=#644500[i found your post very helpful as i'm about to roof my house. please what is the lineaner measurement of yoir building in meter i mean lenthgth amd breath.]
PropertiesRe: General Topic Thread-To Discuss Anything And Everything in Building Construction by Nbg4real: 4:35pm On May 12, 2019
[quote author=Adaowerri111 post=78319574]please can you upload the pocture of your building for us ti see.
PropertiesRe: Architectural Designs For Nairalanders Who Want To Build by Nbg4real: 4:05pm On Mar 07, 2019
[quote author=ihebrooke post=76265832]Side view is this a deck or hidden (Aluminum roof)
PropertiesRe: Architectural Designs For Nairalanders Who Want To Build by Nbg4real: 4:05pm On Mar 07, 2019
[quote author=ihebrooke post=76265832]Side view is this a deck or hidden (Aluminum roof)
PropertiesRe: Roofing Sheets: The Cost Of Various Types Of Roofing Sheet In Nigeria by Nbg4real: 8:37am On Feb 24, 2019
[quote author=money121 post=75989431]Job Done!!
Another Successful Roofing Project Completed
Site Location: @ Abaren Area Ofada Ogun State
Roof Design : Bond Design
Colour: Brown with Black dotted
Roof meters: =248Sqm

To get the Cost that Roofed this Building Call/WhatsApp 080853103 Please I'm interested in the above cost. Thank You. ]
PropertiesRe: How To Build Your Comfortable House Earning Little (detailed) Pt 2 by Nbg4real: 1:53pm On Jan 31, 2019
saydfact:
Based on the many questions asked the last time out (see: https://www.nairaland.com/3502464/how-build-comfortable-house-earning ) we would go more into details, best working practice, cost implications and questions & answer using the attached plan as our case studies.... i.e we would arrive at an approximate cost of building the house attached.

(We would not be considering government determined processes e.g approval - it is practically impossible to get that info here - visit your local authorities for help)


No1: Preliminaries:
Under Preliminaries we refer to those activities that should be done, considered or made ready before the actual construction process begins. Most times we ignore this process forgetting how important it is. On a couple of occasion, I've visited people's site to help with foundation works only to discover there is a big tree or root where the building is located..

Other times, there is no access to drop materials or there is no provision for water (both for work and for workers to have their bath)

Now what are the important preliminaries we would be considering?

* Clear the bushes, cut the trees & uproot, except trees fall about 3m from building location.
* Buy a small tank for water storage or rent one for the time being (we would safe cash on this later).
* Ensure the tipper delivering materials can get to your site i.e all materials are dropped on your site.
* Ensure you negotiate with the Omo-onile on how much you're expected to pay before the day of foundation - but preferably, don't give them the money until the day of actual foundation works. Most times there is a fraction, and the fraction that didnt get the money would still disturb you. Giving while work is ongoing is perfect because both fraction would have representatives present.

COST IMPLICATION:
* Clearing and uprooting of trees (N5,000-7N,000 would clear your site while N10,000 would clear and uproot all trees)
* Water (find out how much a small tank goes for but it cost about N3,000 to rent & fill a tank of water)
* Workmen usually charge you extra if the material is not dropped on your site, because they also have to pay workers to move the material to the site. This sometimes is a lot we're talking about.
* Omo-onile could charge as much as N50k to 100k depending on your location.

>> Labour Cost: 10k

SUMMARY: The cost in this section are dependent on so many factors; its almost impossible to put a figure to it; my advice would be to safe about N100k for this section; most of that being fees paid to Omo-onile.



No2: Works Below Ground

Works in this sections include (but not limited to)
a. Setting Out
b. Digging
c. Foundation
d. Block-works to foundation
e. Filling
f. German floor

A. Setting Out: The bricklayers claim we waste money by using profiles (setting out using wood and ropes) but they often create problems with their method of setting out using blocks. Since this thread is not about anybody but professional practices, we'll consider setting out with profiles.

Materials Needed: (Based on the attached design)
1x12 plank = 4pcs, each sliced into 4 each.
Pegs = 32 pcs approx 3 dozen
Nails = 2" and 3" - buy about N1000 worth
Ropes = 4 bundles each at about N200

Workmen Needed:
One carpenter or anyone that can handle the hammer = Daily pay
One experienced Supervisor = If its an experienced bricklayer Zero Naira except he's not also doing the actual work, if you're getting a supervisor for this price would be around N10k.
The diggers or at least one of them = Cost wld be analyzed below.


COST IMPLICATION:
* Planks: 4 x 1200 = 4800
Cost of Slicing per line = N70 x 3lines = N210 x 4planks = N840
* Pegs: 3 dozens x 1200 = 3600
* Nails = N1000
* Ropes = N1000

>> Labour Cost - 12.5K

With a total of about N11,500 (material cost) - paying this amount to ensure your house is properly set out isn't bad investment - if your bricklayer is experienced thats good, you can however get someone to set it out for you for additional N5-N10K depending on your relationship with him or her. (Personally I do this most time for free if I designed the structure to ensure some in-experienced guys don't spoil/change my hard worked design)

B. Digging: The books recommend about 900mm depth for foundation but practically, its almost impossible to achieve this on very solid soil we're considering. If you can get your workers to achieve 450mm - 600mm depth great and a width of 675mm

If your plan like mine is to do a German floor, there is no need to dig out some wall partition - but if you have a plan to continue without German floor, then all wall partition should be dug (although I don't advice my clients to use the second method; I must be realistic that it comes with an initial cost most are not willing to spend)

ADVICE: I still recommend using experienced guys, people who are used to digging foundation (don't get the Hausa guy that cleared your site to dig because he did a good clearing work, or the Ibo / Yoruba guy because he claims he's done it before). The advantages are those doing this work are:
- Quicker
- They dig straight and ensure a level surface (makes it easy for the bricklayer)
- Saves time and material
- They charge appropriately.

The attached structure would cost you about 30K to dig; with six (6) quality hands digging, you should have it completed in a day or early hours of day 2; still in time for the foundation (concrete pouring) works.

COST IMPLICATION:
* Digging = N30,000 - N35,000
* Water for workmen = N1,000 (about 5 bags of pure water).

>> Labour cost - N35k

Note: We would give individual cost, but after each section add up to help your bargaining power - it means if all works sum up to say 30 naira, you can give all works out to the bricklayer at 25 naira - you're only asking for discount for giving him so much at once. #wink

C. Foundation: This is the first of many important works and where most people unnecessary save material and money; infact most bricklayers would even help you save here NOT BECAUSE THEY CARE but because it means less work for them at the same price of the actual work.

Normally the standard foundation thickness should be at about 150 - 175mm for bungalows (remember we're building on solid soil) yet you find some people using as little as 50mm - 75mm ie 2" - 3" - You end up using about 15 bags of cement, then claim the professional wanted to cheat you by recommending 35 bags - NO; the professionals' calculation was based on a standard 150mm thick foundation, what you did was 50mm or 75mm. Lets hope your house can withstand the weight to come.

MY ADVICE: Ensure your bricklayer starts from one corner and transfer levels across to the others - to ensure a level plain for the block works, if the foundation was dug well leveled, this should be a easy process. Every good bricklayer knows the importance of having a level plain; cheap labour is most times bad for the job. avoid picking your workmen based on cost only, especially if you're doing it yourself.

Materials Needed:
Volume of Concrete = 101.55m x 0.675m x 0.10m = 6.85m3 (based on attached design)
Cement (approx) = 27 - 30 bags
Sand: 20 tonnes (this should serve for all works minus German floor)
Granite: 30 tonnes (recommended) or 15 tonnes (being the minimum you should purchase)

* If you cant afford Granite, then buy Double tipper of gravel, however ask your supplier to ensure it doesn't have too much of sand, you could add the phrase "I'll reject it if sand is too much" - makes the supplier more alert to ensuring you get the best possible. Don't expect a miracle, gravel are mined with sand.


COST IMPLICATION:
Material Cost:
Granite (15 tonnes) = 60k - 65k
Granite (30 tonnes) = about 110k - 125k
Gravel (Double tipper) = 35k to Ikorodu;
Sharp sand (Double tipper) = 30k in Ikorodu; 55k to Mowe/Ibafo
Cement = N2,350 / bag (including transportation)

>> Labour cost - 25k

Note: Depending on your negotiation with your bricklayer, you might have to pay for renting of tools eg shovels, wheelbarrow etc, however, this shouldn't cost too much its about N100-N200 per day for most tools.

D. Block-works to Foundation: My recommendation here is even when you intend to build with 150mm (6"wink blocks, ensure you use quality 225mm (9"wink blocks for the foundation. We can't guarantee the strongest 6" is what you've brought so; spend a little more and safe your building. (I am aware that Ghanaian however build with 6" - solid block even in storey building)

Materials Needed:
9" Block @ 4 courses = 910 pcs (including waste). 9" cost btw N150 - N180 while 6" cost about N160 each, depending on quality and location.
Cement = 15 bags should do the job (Most times, there is a few left over from the foundation - so you'll only buy the balance) - Don't forget all calculation considers waste, so the less you waste, they more you save.

Sand? No, we've got enough

>> Labour cost - 50k

Since I recommended in my previous article that we negotiate all works above at once, lets see how much labour cost we have:
Setting out = 10k
Digging = 35k
Foundation = 25k
Block setting = 50k (see previous post if you need a hint on how we arrived at 50k)

Total: 122.5k we didn't add the 10k for site clearing (Now, how well can you negotiate?) - Put that to good use.

E. Filling: I actually don't advice anyone buys filling solely for this purpose, you would dig your septic tank / soak away one day, where would you put the filling? Probably pay to get it out of your site or sell at very cheap price. SO! DIG YOUR SEPTIC TANK and use the discarded filling for this purpose.

If you don't get enough filling to level your site, you'll only need to buy a few more trucks. see No3 below for detail of material and cost implication on septic tank.

Note: If you're using this option, then ensure you have enough cash to complete the septic tank/soak away 90% - 10% being the slab cover.

F. German floor: I recommend you do this, but I most also note that it comes with some cost implication. We'll analyze the cost below, then you can weigh your pocket.

Total Floor Area: 113.63m2
Volume of Concrete: 11.34m3

We'll try and generate a rate per m3 in-case you have a different design and volume.....hmmm, that rate would be N2500. (pls note that this rate does not work for decking and doesn't work if you're using machine)

Keep 5K at hand, the omo oniles' no dey take eye see concrete...

COST IMPLICATION:
Materials Needed:
Cement: 35 - 40 bags (4" thick)
Sand: 20 tonnes
Granite: 15 tonnes (but if you brought 30 tonnes initially, you're covered)

>> Labour Cost: 30K

No3: Septic Tank & Soak Away

Lets pick a size; but depending on your site that site might vary. In the previous article, my cousin had very little setback (remember I told you the site is less than half plots (18x18) - so, we picked a narrow width and a very long length to compensate.

Let's use Septic-Tank size of 2.4m width 3.0m length x 3.0m depth and Soak-Away 1.8m x 1.8m x 1.8m

COST IMPLICATION:
Materials Needed:
Septic Tank = 280 (9" blocks) & Soak away = 110 (6" blocks)
Cement = 8 bags (including concrete footing for septic tank and plastering of the inside)
Note: only septic tank has a concrete base, as the name implies soak-away is left natural so the water can be soaked into the underworld. #wink

>> Labour Cost:
* Bricklayer = 33.5k (all inclusive plus plastering) Normally I'll pay less, the bricklayer has justed finished foundation works and he's assured of the super-structure, this is where I tell him, look - you have a lot to do together, I can only pay 25k for all works....
* Digging only = 20k-25k


GENERAL SUMMARY: (Using the highest options i.e If cost above says 30k-50k; we'll be using 50k for this section)

TOTAL MATERIAL COST: N721,590
TOTAL LABOUR COST: N331,000

I EXPECT YOU WOULD SPEND LESS, BECAUSE WE USED THE WORST CASE SCENARIO.

Attached:
1. 3 Bedroom design used for this calculation
2. Excel Sheet for Break-Down


Note:
* Follow this thread or my account - we would not close this thread until we have completely built this house online. (Foundation - Painting) using Construction standards only.
* Our site is assumed to be a very solid clayey soil (if your site is waterlogged, swampy or sandy - discuss with a professional on visiting your site or share pictures here for help)


No4: Super Structure (Blockworks)

WE WOULD CONTINUE FROM THE ABOVE WORK ON THIS SAME THREAD NEXT WEEK; ASK YOUR QUESTIONS NOW.

Thanks.
I am an Architect for those who would be asking....
good job oga saydfact. pls what is the measurement of the rooms, kitchen, dinning and living? thanks.