The Construction Of 14 Class Room At Emuhoa Community Rivers State - Properties - Nairaland

Nairaland Forum / Nairaland / General / Properties / The Construction Of 14 Class Room At Emuhoa Community Rivers State (11417 Views)

Photos From The Construction Of Asaba Mall (shoprite) From Inception To Completi / The Construction Of 2-bedroom Twin Flats In Calabar / Simple Guild To The Construction Of Timber Roof Truss In Nigeria (2) (3) (4)

(1) (2) (3) (4) (Reply) (Go Down)

The Construction Of 14 Class Room At Emuhoa Community Rivers State by abdulwastecx(m): 9:38pm On Mar 07, 2015
the construction of 14 block ube primary school at emuhoa community rviers state.

project duration = 3 months
starting date = 1st march 2015

1 Like

Re: The Construction Of 14 Class Room At Emuhoa Community Rivers State by abdulwastecx(m): 9:41pm On Mar 07, 2015
site clearance
equipment = bulldozer
duration of work = 2 days
cost of clearance = 200k
Re: The Construction Of 14 Class Room At Emuhoa Community Rivers State by abdulwastecx(m): 9:53pm On Mar 07, 2015
pics

Re: The Construction Of 14 Class Room At Emuhoa Community Rivers State by abdulwastecx(m): 10:07pm On Mar 07, 2015
more pics

Re: The Construction Of 14 Class Room At Emuhoa Community Rivers State by emmadejust(m): 10:08pm On Mar 07, 2015
abdulwastecx Abeg position wella incase there is any running bush meat on d lose..... na weekends tinz oooo



1 Like

Re: The Construction Of 14 Class Room At Emuhoa Community Rivers State by abdulwastecx(m): 10:11pm On Mar 07, 2015
emmadejust:
abdulwastecx Abeg position wella incase there is any running bush meat on d lose..... na weekends tinz oooo




na only be say I still dey fear ebola

1 Like

Re: The Construction Of 14 Class Room At Emuhoa Community Rivers State by Dieumerci(m): 10:17pm On Mar 07, 2015
Correct guy!
Re: The Construction Of 14 Class Room At Emuhoa Community Rivers State by abdulwastecx(m): 10:19pm On Mar 07, 2015
more picture

Re: The Construction Of 14 Class Room At Emuhoa Community Rivers State by abdulwastecx(m): 10:29pm On Mar 07, 2015
setting out:
material includes the following
1. pegs : 7 boundle @ N1000 = N7, 000
2. profile board = 120 2" x 2" @ N250 = N30, 000
3. line, builder's square, claw hammer, heavy hammer, meter rule = N20, 000
4. miscellaneous = N10, 000
total = N67, 000

1 Like

Re: The Construction Of 14 Class Room At Emuhoa Community Rivers State by abdulwastecx(m): 10:33pm On Mar 07, 2015
setting out picture

Re: The Construction Of 14 Class Room At Emuhoa Community Rivers State by abdulwastecx(m): 10:36pm On Mar 07, 2015
more pics

Re: The Construction Of 14 Class Room At Emuhoa Community Rivers State by abdulwastecx(m): 10:37pm On Mar 07, 2015
more

1 Like

Re: The Construction Of 14 Class Room At Emuhoa Community Rivers State by abdulwastecx(m): 10:50pm On Mar 07, 2015
setting out procedures
1. establishement of the building line
2. the other corners of the building is set at right angle to the building line using builder's square to get the correct andgle and a meter rule to measure the horizontal distance. allowance is made to allow for sagging of the meter rule.
4. the four cotners of the building is set and pegged.
5. A nail is placed ontop of the four pegs and each ate connected to form a perfect rectangle or square as the case may be.
6. from these four corners, an ofset of 1.2m or 1.5m ( to allow for digging and carting away of excavated material) is allowed from these four corners pegs.
7. The four offsets pegs are nailed an line connected to them to form another perfect rectangle and square as the case may be.
8. across the new line pegs are spaced at 2m c/c fo form a continuous chain of peg to wish profile boards are nailed to form a profile.
9 The structural building plans is transferred carefully to the profile.
10. at each grid line on the drawing a corresponding 5 nails are placed on the profile as follows. the center nail represent the grid, the next two nail represent the width of block while the last two nail represent the width of the foundation

2 Likes

Re: The Construction Of 14 Class Room At Emuhoa Community Rivers State by mufutau55(m): 4:48am On Mar 08, 2015
Good work.. I dey class oh! Learning as usual.

Hajji M.
Re: The Construction Of 14 Class Room At Emuhoa Community Rivers State by abdulwastecx(m): 5:57am On Mar 08, 2015
mufutau55:
Good work.. I dey class oh! Learning as usual.

Hajji M.

welcome sir
Re: The Construction Of 14 Class Room At Emuhoa Community Rivers State by abdulwastecx(m): 5:58am On Mar 08, 2015
more pics

Re: The Construction Of 14 Class Room At Emuhoa Community Rivers State by abdulwastecx(m): 5:59am On Mar 08, 2015
more

Re: The Construction Of 14 Class Room At Emuhoa Community Rivers State by abdulwastecx(m): 6:01am On Mar 08, 2015
more
Re: The Construction Of 14 Class Room At Emuhoa Community Rivers State by abdulwastecx(m): 6:12am On Mar 08, 2015
excavation work.
depth of excavation = 900mm
width of excabavation = 675mm
calculated perimeter of excavation =880m
rate of excavation = N500/m
expected duration of excavation assuming 40 labourers with capacity of 15m/ day
= 880/(15 × 40) = 1.48days.

actual excavation
perimeter of excavation = 860m( very close to the calculated perimeter)
duration of excavation : it took us two days to complete the excavation. the work was completed 2.0pm the next day.

cost of excavation = 500 x 860 = N430, 000
logistics = N15, 000
total = N445, 000

1 Like

Re: The Construction Of 14 Class Room At Emuhoa Community Rivers State by abdulwastecx(m): 6:18am On Mar 08, 2015
pics

Re: The Construction Of 14 Class Room At Emuhoa Community Rivers State by emmadejust(m): 8:35am On Mar 08, 2015
abdulwastecx:


na only be say I still dey fear ebola

#neveragain should you fear any plague or diseases

in the land....

we are free to enjoy the good of the land and our labour.......

Happy Sunday ......!!!!

OUR FAITH, OUR REALITY IN LIFE....
Re: The Construction Of 14 Class Room At Emuhoa Community Rivers State by abdulwastecx(m): 11:11pm On Mar 17, 2015
it has been a while on nairaland for me...I am back for more update.
Re: The Construction Of 14 Class Room At Emuhoa Community Rivers State by Dieumerci(m): 11:44pm On Mar 17, 2015
abdulwastecx:
it has been a while on nairaland for me...I am back for more update.

Welcome back sir, eku ewu omo. Olohun abawa wooo!
Let the lectures begin.
Re: The Construction Of 14 Class Room At Emuhoa Community Rivers State by abdulwastecx(m): 11:46pm On Mar 17, 2015
foundation footing
summary

foundation footing
1.thickness of footing = 225mm
2.bags of cement = 380bags
3.trip of sharp sand = 6
4. gravel = 120tonnes

1. No of column type A = 157
size of column type A = 225 x 225mm
2. No of column type B = 450mm diameter column

block work
1.quantities of block = 8500
2.cement = 140bags of cement
Re: The Construction Of 14 Class Room At Emuhoa Community Rivers State by abdulwastecx(m): 11:47pm On Mar 17, 2015
Dieumerci:

Welcome back sir, eku ewu omo. Olohun abawa wooo!
Let the lectures begin.

thank you sir
Re: The Construction Of 14 Class Room At Emuhoa Community Rivers State by podosci(m): 9:38pm On Mar 20, 2015
Update from the ongoing work

Re: The Construction Of 14 Class Room At Emuhoa Community Rivers State by podosci(m): 9:40pm On Mar 20, 2015
abdulwastecx:
the construction of 14 block ube primary school at emuhoa community rviers state.

project duration = 3 months
starting date = 1st march 2015

more pictures

Re: The Construction Of 14 Class Room At Emuhoa Community Rivers State by podosci(m): 9:41pm On Mar 20, 2015
more pictures

Re: The Construction Of 14 Class Room At Emuhoa Community Rivers State by engrgordon(m): 9:56pm On Mar 20, 2015
good job going on here, Kudos..... I love my profession........ Can part of the project be sublet to me? DOUBLE INTEGRATION MULTI-PROJECTS SERVICES(DIMS) , WE BASED IN PORT HARCOURT.
Re: The Construction Of 14 Class Room At Emuhoa Community Rivers State by mufutau55(m): 12:31am On Mar 21, 2015
podosci:
Update from the ongoing work

Welcome back.. I know you have been very busy, so I decided not to bother you..
How is our new girl and the Mummy.. Congrats.

Hajji M.

(1) (2) (3) (4) (Reply)

For sale: Ibafo uncompleted 4bdrms bungalow & House @ Mowe / Cheap Brand New Stunning Duplex To Let In Megamound Estate Ikota Ajah. 1yr Rent / My 3 Bedroom Bungalow At Shimawa

(Go Up)

Sections: politics (1) business autos (1) jobs (1) career education (1) romance computers phones travel sports fashion health
religion celebs tv-movies music-radio literature webmasters programming techmarket

Links: (1) (2) (3) (4) (5) (6) (7) (8) (9) (10)

Nairaland - Copyright © 2005 - 2024 Oluwaseun Osewa. All rights reserved. See How To Advertise. 20
Disclaimer: Every Nairaland member is solely responsible for anything that he/she posts or uploads on Nairaland.