Welcome, Guest: Register On Nairaland / LOGIN! / Trending / Recent / New
Stats: 3,152,214 members, 7,815,242 topics. Date: Thursday, 02 May 2024 at 09:30 AM

The Making Of The "4 Bedrooms Contemporary Style Duplex" (2 units) In Anambra - Properties (12) - Nairaland

Nairaland Forum / Nairaland / General / Properties / The Making Of The "4 Bedrooms Contemporary Style Duplex" (2 units) In Anambra (29103 Views)

The Making Of The "7 Bedrooms High Ceiling Bungalow" In Anambra / The Making Of The "Owerri Royal Manor" / The Making Of The Enugu 6 Bedroom Duplex (2) (3) (4)

(1) (2) (3) ... (9) (10) (11) (12) (13) (14) (15) ... (19) (Reply) (Go Down)

Re: The Making Of The "4 Bedrooms Contemporary Style Duplex" (2 units) In Anambra by Newcreation22: 9:56pm On Dec 23, 2021
Hello all,
Does anyone know where we can rent wood for decking in Abuja. It a 3 bedroom duplex that I'm supervising, so I don't need much

1 Like

Re: The Making Of The "4 Bedrooms Contemporary Style Duplex" (2 units) In Anambra by spyder880(m): 9:52am On Dec 25, 2021
Merry Christmas to you all ..........

1 Like

Re: The Making Of The "4 Bedrooms Contemporary Style Duplex" (2 units) In Anambra by MrUkim: 3:34am On Dec 26, 2021
Good day sir. I've been following your work on this 4 bedroom duplex. I would love to build a similar one. Please, how much is the plan?
Re: The Making Of The "4 Bedrooms Contemporary Style Duplex" (2 units) In Anambra by spyder880(m): 7:51am On Dec 26, 2021
MrUkim:
Good day sir. I've been following your work on this 4 bedroom duplex. I would love to build a similar one. Please, how much is the plan?

Good morning, please contact 08061116988 for the building plans. He's an architect.

Thanks.

1 Like

Re: The Making Of The "4 Bedrooms Contemporary Style Duplex" (2 units) In Anambra by buzzcypha(m): 8:38am On Dec 26, 2021
spyder880:
Our walls here has gotten to the lintel level after 10 courses of blocks.
Sir, why 10 courses of blocks, I thought it use to be 9 courses. Or is it that 4 feet doors will be used instead of 3 feet
Re: The Making Of The "4 Bedrooms Contemporary Style Duplex" (2 units) In Anambra by michlins(m): 8:41am On Dec 26, 2021
buzzcypha:

Sir, why 10 courses of blocks, I thought it use to be 9 courses. Or is it that 4 feet doors will be used instead of 3 feet
current height of doors is now 7ft. Doing nine coaches will mean the doors will be just 78-80" high

3 Likes

Re: The Making Of The "4 Bedrooms Contemporary Style Duplex" (2 units) In Anambra by spyder880(m): 9:01am On Dec 26, 2021
michlins:
current height of doors is now 7ft. Doing nine coaches will mean the doors will be just 78-80" high

Sure, a lot of importers and door makers are now providing in taller doors.

2 Likes

Re: The Making Of The "4 Bedrooms Contemporary Style Duplex" (2 units) In Anambra by michlins(m): 9:16am On Dec 26, 2021
spyder880:


Sure, a lot of importers and door makers are now providing in taller doors.
it's a house and not a shrine one needs to bend before entering.

People like me can get in without bending but not for you

1 Like

Re: The Making Of The "4 Bedrooms Contemporary Style Duplex" (2 units) In Anambra by spyder880(m): 5:52am On Jan 12, 2022
We bough a lot of blocks for this site yesterday, my workers will be moving to this site today, work resumes as from this afternoon. More pictures later.

1 Like

Re: The Making Of The "4 Bedrooms Contemporary Style Duplex" (2 units) In Anambra by spyder880(m): 7:11pm On Jan 13, 2022
Starting with the parapet wall blocks this morning.......

Re: The Making Of The "4 Bedrooms Contemporary Style Duplex" (2 units) In Anambra by spyder880(m): 7:15pm On Jan 13, 2022
More pictures

Re: The Making Of The "4 Bedrooms Contemporary Style Duplex" (2 units) In Anambra by spyder880(m): 10:34pm On Jan 15, 2022
A lot of work going on at this building, more pictures later.
Re: The Making Of The "4 Bedrooms Contemporary Style Duplex" (2 units) In Anambra by spyder880(m): 10:38pm On Jan 19, 2022
Work will resume here as from tomorrow.
Re: The Making Of The "4 Bedrooms Contemporary Style Duplex" (2 units) In Anambra by spyder880(m): 8:03pm On Jan 22, 2022
At this site, we are working on the parapet walls, and the coping of it................

1 Like

Re: The Making Of The "4 Bedrooms Contemporary Style Duplex" (2 units) In Anambra by spyder880(m): 8:06pm On Jan 22, 2022
Plus the staircase covering........

1 Like

Re: The Making Of The "4 Bedrooms Contemporary Style Duplex" (2 units) In Anambra by spyder880(m): 8:09pm On Jan 22, 2022
Surveying the work from the top...........

1 Like

Re: The Making Of The "4 Bedrooms Contemporary Style Duplex" (2 units) In Anambra by spyder880(m): 10:42pm On Jan 22, 2022
More pictures of this ongoing building today.........

1 Like

Re: The Making Of The "4 Bedrooms Contemporary Style Duplex" (2 units) In Anambra by spyder880(m): 9:32am On Jan 27, 2022
We're still working on this building.........

1 Like

Re: The Making Of The "4 Bedrooms Contemporary Style Duplex" (2 units) In Anambra by spyder880(m): 9:35am On Jan 27, 2022
We have completed the concrete cast of the decking over the stairs........

1 Like

Re: The Making Of The "4 Bedrooms Contemporary Style Duplex" (2 units) In Anambra by Kk4(m): 10:34am On Jan 28, 2022
Hey man.
I'd love to see the finishing in this project.

Kudos to you mate
Re: The Making Of The "4 Bedrooms Contemporary Style Duplex" (2 units) In Anambra by spyder880(m): 6:26pm On Jan 28, 2022
Kk4:
Hey man.
I'd love to see the finishing in this project.

Kudos to you mate

Thank you, we are steadily moving to the finishing.

2 Likes

Re: The Making Of The "4 Bedrooms Contemporary Style Duplex" (2 units) In Anambra by spyder880(m): 8:06pm On Jan 29, 2022
More pictures of our work in this house yesterday.......

1 Like

Re: The Making Of The "4 Bedrooms Contemporary Style Duplex" (2 units) In Anambra by spyder880(m): 8:11pm On Jan 29, 2022
The coping we did on the parapet walls..........

1 Like

Re: The Making Of The "4 Bedrooms Contemporary Style Duplex" (2 units) In Anambra by michlins(m): 8:13pm On Jan 29, 2022
This is truly beautiful

1 Like

Re: The Making Of The "4 Bedrooms Contemporary Style Duplex" (2 units) In Anambra by spyder880(m): 8:14pm On Jan 29, 2022
michlins:
This is truly beautiful

Thank you bro.

1 Like

Re: The Making Of The "4 Bedrooms Contemporary Style Duplex" (2 units) In Anambra by spyder880(m): 8:21pm On Jan 29, 2022
Looking around the top, while standing on the top deck.......

1 Like

Re: The Making Of The "4 Bedrooms Contemporary Style Duplex" (2 units) In Anambra by xklusivej(m): 7:21am On Jan 30, 2022
[You are truly right sir....I was in a Anambra for a building project.....I had similar experiences with the supply of clippings....we need to wait for supply to be made from Edo state or ebony state.....Anambra has no quarry site....
Re: The Making Of The "4 Bedrooms Contemporary Style Duplex" (2 units) In Anambra by spyder880(m): 11:44am On Jan 30, 2022
xklusivej:
[You are truly right sir....I was in a Anambra for a building project.....I had similar experiences with the supply of clippings....we need to wait for supply to be made from Edo state or ebony state.....Anambra has no quarry site....

Hmmm, Anambra may have no quarries, but there is no shortage of chippings here. A lot of dealers bring in chippings on a large scale and sell from different dump sites. The picture below is from a site in Anambra state.

Re: The Making Of The "4 Bedrooms Contemporary Style Duplex" (2 units) In Anambra by xklusivej(m): 12:39pm On Jan 30, 2022
spyder880:


Hmmm, Anambra may have no quarries, but there is no shortage of chippings here. A lot of dealers bring in chippings on a large scale and sell from different dump sites. The picture below is from a site in Anambra state.
Nice work sir.....I have been following your works from the foundation to this level.....may God continue to bless you....am an Architect i really do enjoy your works......

3 Likes

Re: The Making Of The "4 Bedrooms Contemporary Style Duplex" (2 units) In Anambra by spyder880(m): 3:52pm On Jan 30, 2022
xklusivej:

Nice work sir.....I have been following your works from the foundation to this level.....may God continue to bless you....am an Architect i really do enjoy your works......

Thank you bro, hope you have a thread for you to showcase your architectural works, I will really like to follow some of your designs.
Re: The Making Of The "4 Bedrooms Contemporary Style Duplex" (2 units) In Anambra by spyder880(m): 3:48am On Feb 03, 2022
We have taken delivery of the roofing sheets we intend to use for this building............

0.55 gauge aluminium roofing sheets.

1 Like

Re: The Making Of The "4 Bedrooms Contemporary Style Duplex" (2 units) In Anambra by spyder880(m): 3:50am On Feb 03, 2022
Inspecting some of the works done on the front of this building.........

1 Like

(1) (2) (3) ... (9) (10) (11) (12) (13) (14) (15) ... (19) (Reply)

A Nairanlander's Building Project / 10 Risky Areas In Lekki/Ajah To Verify Before You Buy A Property / PMB Okays Centenary City Project

(Go Up)

Sections: politics (1) business autos (1) jobs (1) career education (1) romance computers phones travel sports fashion health
religion celebs tv-movies music-radio literature webmasters programming techmarket

Links: (1) (2) (3) (4) (5) (6) (7) (8) (9) (10)

Nairaland - Copyright © 2005 - 2024 Oluwaseun Osewa. All rights reserved. See How To Advertise. 23
Disclaimer: Every Nairaland member is solely responsible for anything that he/she posts or uploads on Nairaland.