U re correct. Some bldg collapse have been attributed to irregularities like this by expert. Such includes inadequate sectioning of structural members, wrong horizontal and vertical allignments/levels etc. As proffessional that is why i prefer to use framed merhod of construction as it helps to effectively controls all this irregularities. Good job my guy kip it up. Cheers! |
Services at its Best. Call now |
After completion of first floor columns. The carcass is abt 60% complete. The next is block laying. Watch out for more pix. |
Upper floor column work in pics
|
Next phase |
Good am! |
more pix
|
Yea i will upload more today. |
more pics of the slab
|
The first floor slab was a quite tasking but intresting. the following pics will speaks more.
|
Material Break down for concrete columns of Grd floor@ 1. 1x12x12 planks 60 2. 2x3x12 80 3. Nails (bag) 1 4. 16mm Iron (ton) 1 5. 10mm iron (lengths) 30 6. B/Wire (roll) 1 7. Sharp sand (10Ton) 1 8. Granite left over from foundation wrk 9. Cement 30 Bags Next item of work now is first floor slab (decking). it comes soon. |
We ha 37 Columns on the Ground floor and 35 on th upper floor. We have 9 of this column to be round column and the diameter is 300mm while others are 23o x 230 mm square columns. |
what next? first floor slab, but b4 that i will do the material breakdown for the columns. BRB |
Pictures of columns.
|
After d completion of fdn. The consrtuction of columns follows. This aspect is technical because we are using the columns to define the spaces in d structure i:e rooms, living rms , kitchen etc. D first thing we do is to set out d kickers. The kickers is used in positioning d columns rightly b4 reinforcemnt , form work and concreting. Also we used plumb bulb to ensure d vertical uprightness of d column and we used levelling instrumen to set the horizontal level. Pix will follows shortly. |
Material Break Down for foundation: Description qty unit rate amouunt Cement 245 Bags Granites 3 30 tons Sharp Sand 6 20 tons Y10mm Iron 15 lenghts Y12mm iron 50 lenghts Y16mm Iron 31 lenghts Binding wire 2 rolls DPM 13 rolls Xypex admixture 3 20kg Laterite Sand 23 20 tons 1 x 12 x 12 40 nrs' Nails 1 bags Blocks 2000 nrs Plumbing Materials |
more pics of fdn completion. For more info contact abidoyventures@gmail.com 0r call 08023142108.
|
Quite a while i sstop updating this tread. Time wasnt on my side. But now By God grace the project has gone far infact at finishing stages. From now on i will update you to from where i stop to the present stage. Question and critism are welcome. Thanks The pics below shows the stages of work to fdn german floor level.
|
About 10 Acres of land together for sale at sango Ota Area. Covered with Agricultural C of O with a good layout. Intrested? contact 08023142108 |
![]() |
![]() |
For good services. check us out. |
![]() |
Aventures: I just completed stage 1 (foundation) power point presentation for construction process and cost of building four flats of 3-bedroom.If you will like to peruse this kindly contact me. Drop your email here and i will get back to you. I am sure you will find it educative and intresting. Thanks |
I just completed stage 1 (foundation) power point presentation for construction process and cost of building four flats of 3-bedroom.If you will like to peruse this kindly contact me. Drop your email here and i will get back to you. I am sure you will find it educative and intresting. Thanks |
still working on an intresting stuff |
gREAT dAY |
Willing to serve u better. |
1 2 3 4 5 6 7 8 ... 35 36 37 38 39 40 41 42 43 (of 60 pages)