Wrapping up work on the block setting, we are laying the fourth and final coach and getting ready for the column casting and back-filling.
|
Blockwork setting continues today, we have achieved 4 coaches with the 2nd unit and will be putting the 4th coach on the 1st unit tomorrow.
|
Blockwork setting on 2nd unit in progress.
|
Blockwork setting on 1st unit done up to 3 coaches, 1 more coach going ontop before backfilling starts.
|
We continued with the block setting for the foundation this morning on the 1st unit and we are making good speed. We plan on doing between 3 - 4 coaches, taking into consideration the future road level, existing german floor level for houses close-by and the level of the compound landscaping when construction is done.
|
Foundation foot blinding completed for the 2nd unit, the first coach of blockwork has commenced.
|
Excavation work on the 2nd unit foundation is complete and we have commenced with the foundation foot blinding.
|
olumide4christ:Thank you for the vote of confidence. BR |
We are currently setting the 1st level of blockwork.
|
Excavation work on the 2nd unit going on concurrently.
|
We started with the floor blinding (concrete foundation footing) of the 1st unit of the 2 bedrooms apartment today while the excavation of the 2nd unit is also ongoing. Foundation setting prayers is very important, so the client committed the construction into Gods hand.
|
Excavation for the 1st unit of 2-bedroom apartments concluded today, we will excavate the 2nd unit tomorrow. The cost for the setting-out, excavation, blockwork and backfilling for both unit is N200,000.
|
More pictures showing excavation progress on site.
|
twinskenny:@Twinskenny, thank you. I will holla at you soon, got something we need to work on together. |
mufutau55:Thank you Hajj M for the vote of confidence. Hope you are doing well. |
Setting-out and excavation work on the foundation started this morning. We are digging to a dept of 12inches because the soil is firm.
|
For this phase of the project we are doing the sub-structure work, up to german floor level. Basically, the steps involve for this stage are 1. Site clearing/grubbing 2. Setting-out 3. Foundation excavation 4. Floor blinding 5. Foundation blockwork 6. Backfilling 7. Columns (for foundation) 8. Iron reinforcement work/BRC wire mesh laying 9. Carpentary formwork 10. Concrete slab casting (german floor) I might have omitted some steps that work hand-in-hand together so please take note. Materials have been dumped on site by the client.
|
No matter how SMALL or BIG our projects are, to God be the GLORY! |
BITSWORKS Nigeria is a multi-discipline construction company comprising of architects, builders, civil engineers and interior designers. We currently have a brief for a client to construct 2 units of a 2-bedroom prototype bungalow on a plot of land in Ikorodu. The Site is a virgin land, the size is 17m(55.77ft) x 36m(120ft). We will share the site plan, floor plan and elevations once permission has been given by the client. Size of land - 612.00 sqm Total area of building - 252.00 sqm Total unbuilt area - 360.00 sqm Percentage of site covered. - 38% Percentage unbuilt - 62% Client - Private individual, nairaland referral Estimated budget for construction - N10million PROJECT timeline - To be built in phases Mobilization to site and site clearing/grubbing started on Monday 22nd of August 2016, here are some pictures taken on site. Strip foundation will be used due to the nature of the soil and topology. Settting-out and foundation excavation will start this week.
|
BITSWORKS Nigeria is a multi-discipline construction company comprising of architects, builders, civil engineers and interior designers. We currently have a brief for a client to construct 2 units of a 2-bedroom prototype bungalow on a plot of land in Ikorodu. The Site is a virgin land, the size is 17m(55.77ft) x 36m(120ft). We will share the site plan, floor plan and elevations once permission has been given by the client. Size of land - 612.00 sqm Total area of building - 252.00 sqm Total unbuilt area - 360.00 sqm Percentage of site covered. - 38% Percentage unbuilt - 62% Client - Private individual, nairaland referral Estimated budget for construction - N10million PROJECT timeline - To be built in phases Mobilization to site and site clearing/grubbing started on Monday 22nd of August 2016, here are some pictures taken on site. Strip foundation will be used due to the nature of the soil and topology. Settting-out and foundation excavation will start this week.
|
Demolition was completed on Monday 22nd of August 2016. Next stage is to wait for the soil test report and structural drawing so we can start work on the sub-structure.
|
DInkMan:My professional fee is not included in the labour wage. Contact details are 08188569130 (Call and Whatsapp). |
alfablondy1:Cost for the foundation workmanship to the present stage is N120,000. |
Omonigeriarere:Project is located in the Aroje area of Ogbomosho. |
We carried out the soil test yesterday, the result will be used in designing the structural framework and for processing the approval. Doing a soil test helps determine the right type of foundation to be done on the site and saves the client from future regrets of the house tilting or sinking.
|
More demolition pictures.
|
Its been a long break but we are back on site this week to start with the old structure demolition and carry out the soil test also. 1 or 2 of the old tenants are still hanging around the premise and we have given them till weekend to move out completely.
|
skyface72:Done. Please check your mail. |
We have scaffoldings for rent/lease to construction companies, builders, contractors and artisans. Kindly contact BITSWORKS via the following channels to book your lease. We offer competitive rates and excellent customer service. Hotline - 08022228584 Whatsapp/Call - 08188569130 BBM - 33514F5C Email - seyisodiya@gmail.com |
More pictures of the fixed aluminium window and other window fixtures.
|
Aluminium profiles for the fixed glass window has been put in place.
|
We are done with the stretch of tiling we were working on in the marquee, that's about 40% of the total surface to be done. Work continues next week, this weekend the team is taking a well deserved break.
|