Properties › Re: The Making Of The Asaba "Stepped" Block Of 6 Flats Of 2 Bedrooms by spyder880(op): 6:32am On Dec 10, 2023 |
Then we started to install the WC in all the bathrooms.............
|
Properties › Re: The Making Of The Asaba "Stepped" Block Of 6 Flats Of 2 Bedrooms by spyder880(op): 6:30am On Dec 10, 2023 |
Then we supplied all the sanitary wares needed for this house this week.............
|
Properties › Re: The Making Of The Asaba "Stepped" Block Of 6 Flats Of 2 Bedrooms by spyder880(op): 6:26am On Dec 10, 2023*. Modified: 10:43pm On Feb 06, 2025 |
After tiling all the rooms in this house, we are now completing the tiles of the staircase ..............
|
Properties › Re: The Making Of The Asaba "Stepped" Block Of 6 Flats Of 2 Bedrooms by spyder880(op): 3:21pm On Dec 09, 2023 |
Chidimercy: Please engineer, what's the size of this soakaway, and what's the labour cost for digging the soakaway? This soakaway is 13 feet deep, 14 foot length, 7 feet wide. Labour N80,000 for digging only. |
Properties › Re: The Making Of The "7 Bedrooms High Ceiling Bungalow" In Anambra by spyder880(op): 8:24pm On Dec 07, 2023 |
Around the compound floor..........
|
Properties › Re: The Making Of The "7 Bedrooms High Ceiling Bungalow" In Anambra by spyder880(op): 8:23pm On Dec 07, 2023 |
Pictures from the repainting of the outside walls of this house.............
|
Properties › Re: How To build A 6 Bedrooms Duplex In 5 Months, The Fight For Timely Delivery. by spyder880(op): 6:52pm On Dec 06, 2023 |
Final sand filling works going on today, ready to complete the increte floor works in 12 days.
More pictures tomorrow. |
Properties › Re: The Making Of The "7 Bedrooms High Ceiling Bungalow" In Anambra by spyder880(op): 8:40pm On Dec 05, 2023 |
We have completed the borehole repairs for this house. We have used it to pump water into the overhead tank.
We have also completed the the increte works, remaining only thr polishing to make it shine brightly.
My painter resumed works here today, he has started repainting the inner walls of this house.
More workers will arrive tomorrow morning, swimming pool and door fixers will be coming later this week.
More pictures later. |
Properties › Re: Buy Land, Build Your House At "Royal Palms Estates" Ogbeke Nike, Enugu East LGA. by spyder880(op): 8:37pm On Dec 05, 2023 |
tivta: Does the N10 million include soak away, plumbing and electric fittings for the one room house? Yes, however this soakaway will be the makeshift type that will only be adequate for the one room house, not the main building. Just a small 4 ft 6 inches cubed structure buried in the ground. Thanks. |
Properties › Re: Buy Land, Build Your House At "Royal Palms Estates" Ogbeke Nike, Enugu East LGA. by spyder880(op): 4:59pm On Dec 05, 2023 |
Still selling, N10m for one plot with gate house and fence with gate.
Buy peace of mind. |
Properties › Re: The Making Of The Asaba "Stepped" Block Of 6 Flats Of 2 Bedrooms by spyder880(op): 9:46am On Dec 05, 2023 |
Staircase tiles ongoing...........
|
Properties › Re: The Making Of The Asaba "Stepped" Block Of 6 Flats Of 2 Bedrooms by spyder880(op): 9:43am On Dec 05, 2023 |
Working on the decking of the generator base for this house............
|
Properties › Re: The Making Of The "7 Bedrooms High Ceiling Bungalow" In Anambra by spyder880(op): 9:39am On Dec 05, 2023 |
More pictures.......
|
Properties › Re: The Making Of The "7 Bedrooms High Ceiling Bungalow" In Anambra by spyder880(op): 9:37am On Dec 05, 2023 |
More of the compound floor.............
|
Properties › Re: The Making Of The "7 Bedrooms High Ceiling Bungalow" In Anambra by spyder880(op): 9:28am On Dec 05, 2023 |
Let's see more of the compound floor of this house as we resurface it................
|
Properties › Re: How To build A 6 Bedrooms Duplex In 5 Months, The Fight For Timely Delivery. by spyder880(op): 9:24am On Dec 05, 2023 |
Pictures as we sand fill this compound, over 45 trips of sand bought and still we haven't got to the required level to take water out of the compound. Very big compound of over 1100 square metres. Very high filling of over 1 metre depth in some places.
|
Properties › Re: How To build A 6 Bedrooms Duplex In 5 Months, The Fight For Timely Delivery. by spyder880(op): 3:23pm On Dec 04, 2023 |
kopell: Congratulation, you always amaze me with quality attention to details of your job. I'm still saving my koko to bring you to Lagos to build my event center IN ShA ALLAH. Perfect color combination Thank you Sir. |
Properties › Re: How To build A 6 Bedrooms Duplex In 5 Months, The Fight For Timely Delivery. by spyder880(op): 9:12am On Dec 04, 2023 |
tranxo: Jisi ike brother Thank you Nwanne. |
Properties › Re: How To build A 6 Bedrooms Duplex In 5 Months, The Fight For Timely Delivery. by spyder880(op): 8:17am On Dec 04, 2023 |
tranxo: The master builder himself. Back to doing finishes too instead of when you tend to do just carcass.
The comment to which you made the quoted comment made me take a look at the 3D Design of this building on page 1. Spyder, I was blown away. What caused a deviation from the brick facade in the 3D Design to the gray belts?
EVERYTHING about the colour mix and brick work in that design was fabulous. I was simply acting on the instructions from the owner of the house. He asked me to go nearer to whites and grays. I still managed to copy some of the old designs like the bricks in the pillars and on the sides of the house. On the other hand, the original design is a very old design which we built in the last 10 years, it has gone out of style. |
Properties › Re: How To build A 6 Bedrooms Duplex In 5 Months, The Fight For Timely Delivery. by spyder880(op): 12:11pm On Dec 03, 2023 |
More..............
|
Properties › Re: How To build A 6 Bedrooms Duplex In 5 Months, The Fight For Timely Delivery. by spyder880(op): 12:06pm On Dec 03, 2023 |
A look from the top front balcony............
|
Properties › Re: How To build A 6 Bedrooms Duplex In 5 Months, The Fight For Timely Delivery. by spyder880(op): 12:01pm On Dec 03, 2023 |
Every room fitted with wardrobe cabinets............
|
Properties › Re: How To build A 6 Bedrooms Duplex In 5 Months, The Fight For Timely Delivery. by spyder880(op): 11:57am On Dec 03, 2023 |
A look at the progress of kitchen cabinets ..............
|
Properties › Re: How To build A 6 Bedrooms Duplex In 5 Months, The Fight For Timely Delivery. by spyder880(op): 11:52am On Dec 03, 2023 |
Some already mounted dropping lights and ceiling lights, more to be mounted soon.............
|
Properties › Re: How To build A 6 Bedrooms Duplex In 5 Months, The Fight For Timely Delivery. by spyder880(op): 11:50am On Dec 03, 2023 |
Some completed bathroom fittings............
|
Properties › Re: How To build A 6 Bedrooms Duplex In 5 Months, The Fight For Timely Delivery. by spyder880(op): 11:39am On Dec 03, 2023 |
Painting the main living room area..........
|
Properties › Re: How To build A 6 Bedrooms Duplex In 5 Months, The Fight For Timely Delivery. by spyder880(op): 11:36am On Dec 03, 2023 |
Barbed security wires over the plastered sections of the fence.............
|
Properties › Re: How To build A 6 Bedrooms Duplex In 5 Months, The Fight For Timely Delivery. by spyder880(op): 6:30am On Dec 03, 2023 |
brightk: baba i greet u ooo.
U don fit get any information concerning this geothermal cooling of houses... No, I haven't been free for some weeks now. Thanks. |
Properties › Re: The Making Of The "Captivating" 5 Bedrooms Duplex In Enugu by spyder880(op): 11:05pm On Dec 02, 2023 |
InvertedHammer: /
Any plug for who did this windows and balcony in Anambra/Enugu area?
/ Good evening Sir, I will send you the information tomorrow. Thanks. |
Properties › Re: How To build A 6 Bedrooms Duplex In 5 Months, The Fight For Timely Delivery. by spyder880(op): 11:15am On Dec 02, 2023 |
Plastering of the whole fence walls ............
|
Properties › Re: How To build A 6 Bedrooms Duplex In 5 Months, The Fight For Timely Delivery. by spyder880(op): 11:13am On Dec 02, 2023 |
Closer...........
|
Properties › Re: How To build A 6 Bedrooms Duplex In 5 Months, The Fight For Timely Delivery. by spyder880(op): 10:10am On Dec 02, 2023 |
mexxy1: Nice job. But, if I may, in my opinion the gray bands do not sit well in my eyes both on the window hoods and the belts. I can retain the ones in the hoods but, for the belts, because of how seemingly close they are, I would have preferred them painted same colour as the body of the building but, if they were more spaced, then, the gray would have been very okay.
Just my own perception as to how I'd have liked it if I were making the choice. But, the job is beautiful generally.
Keep it up. Thank you very much for this honest feedback. I know the owner of the house is reading this and if he asks us to make the change, we will at no extra cost as we are still on site. Thanks. |