Procured nig pipes and PPR.
|
Installation of waste pipes going on concurrently.
|
Concreting.
|
We are concreting already. Procured nig pipes for wastes and PPR for supply. |
MrDraey:Both are of the same strength (42.5N) and will serve the same purpose. |
Materials arriving site.
|
Blessedsunny2:You are wrong. |
rukyboy:For doors which the leaf can be detached from the frame, the frames can be installed then tiling done before the door leaf is installed. This is mostly done for wooden doors. But for metal doors, one has to install the door fully before tiling. |
We will be working on the approach risers and risers to the individual halls soon.
|
Good day good nairalanders. We have successfully completed the earth filling and placement of rubbles as hardcore for this structure. Iron fitting for beams to connect the columns together and placement BRC wire mesh ongoing. Materials are being delivered to site for casting of the oversite concrete. We budgeted 200bags of cement. 90 tons of granite. 80 tons of sharp sand. 14 rolls of 4mm BRC wire mesh. 85 lengths of 16mm for beams. 10mm available from the Left over purchased before. All earth filling material was from the demolished building and some part of the excavated earth.
|
It has been raining since these few days. Earth filling ongoing. We may not be buying laterite as the rubbles and earth on site may be enough.
|
Charisdesigns:Good morning sir. I am concerned about the electric wires I am seeing in the first picture. Hope you have adequate setback for it? |
Three bedroom apartment of five units. Ground floor parking. Boy's quarter.
|
We have some isolated pad foundation at the center of the mini halls.
|
Happy Sunday to everyone. We are doing the column formworks, casting of the columns and today we are kicking off earth filling of the backstage and hall areas. While tomorrow, we set out other parts of the building which we haven't done due to want of space. Please keep following.
|
Amarisco:Thanks. I will update that right away. |
Amarisco:As stated on the introduction, the project is a mini event center, consists of 3 mini halls measuring 6m*12.3m each at the ground floor and a bigger hall measuring about 13.5m*18m at the first floor with other ancillary spaces. There is also a detached 4bedroom guest suites and a security house. We are expected to deliver this project upto practical completion level in 6months time. Thanks for following up ma. |
Making use of a water level to get desired block level.
|
Erecting the foundation walls. By tomorrow column formworks will commence.
|
We are gradually making progress. Casting of column base continued today. Tomorrow we will kick off formation and erection of the foundation walls and complete the casting of the remaining column base.
|
We made some progress. Installation of column reinforcement bars and casting of R.C column base.
|
ejikeme:Thank you sir. |
Refreshments on site. Courtesy of our client. #Teambuilding
|
25 tons of granite, a trip of sand, 50 bags of cement arrived at this site today. We are adopting a just in time approach due to the site being congested with rubbles and remnants of the demolished building. Once we start backfilling we would have enough space to store materials on site.
|
kkonsults:Exactly. Thanks for following up boss. |
Happened to meet this 16mm rebar used on the demolished building here. Mehn!!! The country has really retrogressed.
|
God willing tomorrow we will be installing the reinforcement mats and starter bars.
|
We commenced casting of the foundation footing and blinding for column base today.
|
Columns We have 3 different columns for this project. 230*230mm (4y16) 300*450mm (10y16) 230*750mm (10y16) 10mm stirrup@200mmc/c Mat 900*900mm 1350mm*1350mm 1500*1500mm respectively.
|
Excavation continues. It has not been easy cutting through the old foundation on this site.
|
We got some materials for a start. Cement. Granite. 16mm rod. 10mm rod. Awaiting sharp sand. Binding wire.
|
Setting out done. Excavation ongoing.
|