PropertiesRe: Documenting The Construction Of A Mini Event Centre by UC92(op): 2:36pm On Jul 17, 2022
Procured nig pipes and PPR.

PropertiesRe: Documenting The Construction Of A Mini Event Centre by UC92(op): 2:32pm On Jul 17, 2022
Installation of waste pipes going on concurrently.

PropertiesRe: Documenting The Construction Of A Mini Event Centre by UC92(op): 2:21pm On Jul 17, 2022
Concreting.

PropertiesRe: Documenting The Construction Of A Mini Event Centre by UC92(op): 2:09pm On Jul 17, 2022
We are concreting already.
Procured nig pipes for wastes and PPR for supply.
PropertiesRe: General Topic Thread-To Discuss Anything And Everything in Building Construction by UC92: 6:59pm On Jul 14, 2022
MrDraey:
Good evening my ogas,

Please is this dangote's blocmaster a better choice for chocking and plastering?

Seller is recommending it as against the 3X
Both are of the same strength (42.5N) and will serve the same purpose.
PropertiesRe: Documenting The Construction Of A Mini Event Centre by UC92(op): 6:31pm On Jul 14, 2022
Materials arriving site.

PropertiesRe: General Topic Thread-To Discuss Anything And Everything in Building Construction by UC92: 6:23pm On Jul 14, 2022
Blessedsunny2:
It depend on the plan of the building, a well-planned house should be fixed tiles first before installation of doors, if not you will been expecting rat visit cheesy
You are wrong.
PropertiesRe: General Topic Thread-To Discuss Anything And Everything in Building Construction by UC92: 3:40pm On Jul 14, 2022
rukyboy:
Isn't someone supposed to tile first before installing doors?
For doors which the leaf can be detached from the frame, the frames can be installed then tiling done before the door leaf is installed. This is mostly done for wooden doors. But for metal doors, one has to install the door fully before tiling.
PropertiesRe: Documenting The Construction Of A Mini Event Centre by UC92(op): 3:29pm On Jul 14, 2022
We will be working on the approach risers and risers to the individual halls soon.

PropertiesRe: Documenting The Construction Of A Mini Event Centre by UC92(op): 3:12pm On Jul 14, 2022
Good day good nairalanders.

We have successfully completed the earth filling and placement of rubbles as hardcore for this structure.
Iron fitting for beams to connect the columns together and placement BRC wire mesh ongoing.
Materials are being delivered to site for casting of the oversite concrete.

We budgeted
200bags of cement.
90 tons of granite.
80 tons of sharp sand.
14 rolls of 4mm BRC wire mesh.
85 lengths of 16mm for beams.
10mm available from the Left over purchased before.

All earth filling material was from the demolished building and some part of the excavated earth.

PropertiesRe: Documenting The Construction Of A Mini Event Centre by UC92(op): 5:54pm On Jul 11, 2022
It has been raining since these few days.
Earth filling ongoing.
We may not be buying laterite as the rubbles and earth on site may be enough.

PropertiesRe: General Topic Thread-To Discuss Anything And Everything in Building Construction by UC92: 6:53am On Jul 04, 2022
Charisdesigns:
Meanwhile, your honest review will be appreciated on this our design and build thread

https://www.nairaland.com/6781323/construction-droyal-apartments-charisdesigns/1
Good morning sir.
I am concerned about the electric wires I am seeing in the first picture.
Hope you have adequate setback for it?
PropertiesRe: General Topic Thread-To Discuss Anything And Everything in Building Construction by UC92: 7:16am On Jul 03, 2022
Three bedroom apartment of five units.
Ground floor parking.
Boy's quarter.

PropertiesRe: Documenting The Construction Of A Mini Event Centre by UC92(op): 7:05am On Jul 03, 2022
We have some isolated pad foundation at the center of the mini halls.

PropertiesRe: Documenting The Construction Of A Mini Event Centre by UC92(op): 6:55am On Jul 03, 2022
Happy Sunday to everyone.

We are doing the column formworks, casting of the columns and today we are kicking off earth filling of the backstage and hall areas.
While tomorrow, we set out other parts of the building which we haven't done due to want of space.

Please keep following.

PropertiesRe: Documenting The Construction Of A Mini Event Centre by UC92(op): 6:53am On Jul 03, 2022
Amarisco:
It wasn’t in the intro o. Keep up the good work either way smiley
Thanks. I will update that right away.
PropertiesRe: Documenting The Construction Of A Mini Event Centre by UC92(op): 1:02am On Jun 30, 2022
Amarisco:
Interesting cool

What’s the schedule of works?
As stated on the introduction, the project is a mini event center, consists of 3 mini halls measuring 6m*12.3m each at the ground floor and a bigger hall measuring about 13.5m*18m at the first floor with other ancillary spaces. There is also a detached 4bedroom guest suites and a security house.

We are expected to deliver this project upto practical completion level in 6months time.

Thanks for following up ma.
PropertiesRe: Documenting The Construction Of A Mini Event Centre by UC92(op): 12:37am On Jun 30, 2022
Making use of a water level to get desired block level.

PropertiesRe: Documenting The Construction Of A Mini Event Centre by UC92(op): 11:55pm On Jun 29, 2022
Erecting the foundation walls.
By tomorrow column formworks will commence.

PropertiesRe: Documenting The Construction Of A Mini Event Centre by UC92(op): 6:20pm On Jun 27, 2022
We are gradually making progress.
Casting of column base continued today.
Tomorrow we will kick off formation and erection of the foundation walls and complete the casting of the remaining column base.

PropertiesRe: Documenting The Construction Of A Mini Event Centre by UC92(op): 7:18pm On Jun 25, 2022
We made some progress.
Installation of column reinforcement bars and casting of R.C column base.

PropertiesRe: Documenting The Construction Of A Mini Event Centre by UC92(op): 2:01pm On Jun 25, 2022
ejikeme:
Congratulations spot.....
Thank you sir.
PropertiesRe: Documenting The Construction Of A Mini Event Centre by UC92(op): 7:06pm On Jun 24, 2022
Refreshments on site. Courtesy of our client.
#Teambuilding

PropertiesRe: Documenting The Construction Of A Mini Event Centre by UC92(op):
25 tons of granite, a trip of sand, 50 bags of cement arrived at this site today.
We are adopting a just in time approach due to the site being congested with rubbles and remnants of the demolished building. Once we start backfilling we would have enough space to store materials on site.

PropertiesRe: Documenting The Construction Of A Mini Event Centre by UC92(op): 5:57pm On Jun 24, 2022
kkonsults:
Thicker than what is available now.

Well done bro
Exactly.
Thanks for following up boss.
PropertiesRe: Documenting The Construction Of A Mini Event Centre by UC92(op): 3:58pm On Jun 24, 2022
Happened to meet this 16mm rebar used on the demolished building here. Mehn!!! The country has really retrogressed.

PropertiesRe: Documenting The Construction Of A Mini Event Centre by UC92(op): 3:44pm On Jun 24, 2022
God willing tomorrow we will be installing the reinforcement mats and starter bars.

PropertiesRe: Documenting The Construction Of A Mini Event Centre by UC92(op):
We commenced casting of the foundation footing and blinding for column base today.

PropertiesRe: Documenting The Construction Of A Mini Event Centre by UC92(op): 12:09pm On Jun 21, 2022
Columns

We have 3 different columns for this project.
230*230mm (4y16)
300*450mm (10y16)
230*750mm (10y16)
10mm stirrup@200mmc/c

Mat 900*900mm
1350mm*1350mm
1500*1500mm respectively.

PropertiesRe: Documenting The Construction Of A Mini Event Centre by UC92(op):
Excavation continues.

It has not been easy cutting through the old foundation on this site.

PropertiesRe: Documenting The Construction Of A Mini Event Centre by UC92(op): 8:29pm On Jun 18, 2022
We got some materials for a start.
Cement.
Granite.
16mm rod.
10mm rod.
Awaiting sharp sand.
Binding wire.

PropertiesRe: Documenting The Construction Of A Mini Event Centre by UC92(op): 8:22pm On Jun 18, 2022
Setting out done.
Excavation ongoing.