Nairaland Forum / Nairaland / General / Properties / Construction Process Of Terrace Building (5 Duplex) at Lekki (15705 Views)
Construction Process Of A Wing Duplex+flat At Ajah / Construction Process Of A 2wing Duplex At Omole Phase 1(learning Thread) / Cost Of Building A 5-duplex In Abuja (1) (2) (3) (4)
(0) (1) (2) (3) (4) (5) (6) (7) (8) (9) ... (11) (Reply) (Go Down)
| Re: Construction Process Of Terrace Building (5 Duplex) at Lekki by segcy.moor(m): 8:08pm On Sep 20, 2012 |
DAY 19..Formwork |
| Re: Construction Process Of Terrace Building (5 Duplex) at Lekki by segcy.moor(m): 9:52pm On Sep 21, 2012 |
DAY 20...Formwork |
| Re: Construction Process Of Terrace Building (5 Duplex) at Lekki by toba: 12:24am On Sep 22, 2012 |
Farm+:i dont believe this cos a standard plot is 18m X 36m. for 7m X 13m hardly will u get car parking space of at least 2 cars per unit. remember other domestic structures must be provided on site. |
| Re: Construction Process Of Terrace Building (5 Duplex) at Lekki by toba: 12:28am On Sep 22, 2012 |
segcy.moor:tumbs up man. my questions. pls whats the exact land size in square metres. also will the buildings be luxury or the regular kind of duplexes? are they going to be terraces or detached houses or semi-detached? |
| Re: Construction Process Of Terrace Building (5 Duplex) at Lekki by segcy.moor(m): 7:43am On Sep 22, 2012 |
Anyway, here is review plan |
| Re: Construction Process Of Terrace Building (5 Duplex) at Lekki by segcy.moor(m): 7:44am On Sep 22, 2012 |
lay-out |
| Re: Construction Process Of Terrace Building (5 Duplex) at Lekki by Sprumbaba: 8:48am On Sep 22, 2012 |
It is now six? |
| Re: Construction Process Of Terrace Building (5 Duplex) at Lekki by segcy.moor(m): 9:53pm On Sep 22, 2012 |
DAY 20 --Casting of 1st half |
| Re: Construction Process Of Terrace Building (5 Duplex) at Lekki by segcy.moor(m): 10:12pm On Sep 22, 2012 |
Conc. Romance-Machine |
| Re: Construction Process Of Terrace Building (5 Duplex) at Lekki by thirdeye(m): 12:03am On Sep 23, 2012 |
Not all toilets has window for ventillation for industrial/institutional buildings especially where source of electricity is constant you can have an extractor thats connect to main fan up of roof and also air supply direct to the toilet. |
| Re: Construction Process Of Terrace Building (5 Duplex) at Lekki by segcy.moor(m): 8:32pm On Sep 24, 2012 |
DAY 21 |
| Re: Construction Process Of Terrace Building (5 Duplex) at Lekki by segcy.moor(m): 6:06pm On Sep 25, 2012 |
DAY 22 |
| Re: Construction Process Of Terrace Building (5 Duplex) at Lekki by segcy.moor(m): 7:12am On Sep 26, 2012 |
How is ur night..... |
| Re: Construction Process Of Terrace Building (5 Duplex) at Lekki by segcy.moor(m): 8:21pm On Sep 26, 2012 |
DAY 23....2nd half Formwork |
| Re: Construction Process Of Terrace Building (5 Duplex) at Lekki by tlops(m): 9:12pm On Sep 26, 2012 |
In what ways does the govt supervise the construction of buildings, to make sure houses are properly built to standard. good spacing from neighbours, ventilation, green-zone, same type of building in an area etc. the building around are def obstructing yours... Good job though. |
| Re: Construction Process Of Terrace Building (5 Duplex) at Lekki by segcy.moor(m): 7:27am On Sep 27, 2012 |
Their is Town Planninig Authority that regulates the Building permit....they emphasise on what u mention |
| Re: Construction Process Of Terrace Building (5 Duplex) at Lekki by segcy.moor(m): 7:56pm On Sep 27, 2012 |
DAY 24...Formworks continues |
| Re: Construction Process Of Terrace Building (5 Duplex) at Lekki by Olarmituns(m): 1:29am On Sep 28, 2012 |
This is a Great job |
| Re: Construction Process Of Terrace Building (5 Duplex) at Lekki by segcy.moor(m): 8:44pm On Sep 28, 2012 |
DAY 25..Concluding d formwork, to cast tommorrow |
| Re: Construction Process Of Terrace Building (5 Duplex) at Lekki by segcy.moor(m): 7:38am On Sep 29, 2012 |
DAY 26..Casting on-going...pics later in d day |
| Re: Construction Process Of Terrace Building (5 Duplex) at Lekki by bigoba: 2:49pm On Sep 29, 2012 |
whats ur contact. can you provide breakdown of work you are doing. |
| Re: Construction Process Of Terrace Building (5 Duplex) at Lekki by segcy.moor(m): 9:43pm On Sep 29, 2012 |
DAY 27...Our Cooporate office:Suite A74, Ikota Shopping Complex, VGC, Lekki. Mobile;08023807960, 07042144750 So far we ve spent 10m to date. pls mail us at segetony@gmail.com for d breakdown. Thanks |
| Re: Construction Process Of Terrace Building (5 Duplex) at Lekki by segcy.moor(m): 9:51pm On Sep 29, 2012 |
Casting |
| Re: Construction Process Of Terrace Building (5 Duplex) at Lekki by segcy.moor(m): 12:13pm On Sep 30, 2012 |
....10m inclusive of filling(average of 100 tippers) with d surface treatment excluding DPC work(i.e Reinforcement and oversite conctrete) |
| Re: Construction Process Of Terrace Building (5 Duplex) at Lekki by segcy.moor(m): 8:25am On Oct 01, 2012 |
To my Fellow Proud Nigerian!..HAPPY INDEPENDENT! |
| Re: Construction Process Of Terrace Building (5 Duplex) at Lekki by segcy.moor(m): 9:17pm On Oct 01, 2012 |
Work free... |
| Re: Construction Process Of Terrace Building (5 Duplex) at Lekki by segcy.moor(m): 8:25pm On Oct 02, 2012 |
DAY 28...clearing d plank for filling work |
| Re: Construction Process Of Terrace Building (5 Duplex) at Lekki by segcy.moor(m): 8:09pm On Oct 03, 2012 |
DAY 29....This little thing we are doing is highly important. U will observe some iron normally expose after casting. d best thing to do is to plaster it as d salt water tend to rust d iron....we can then fill |
| Re: Construction Process Of Terrace Building (5 Duplex) at Lekki by segcy.moor(m): 7:37pm On Oct 04, 2012 |
DAY 30...Filling work on-going |
| Re: Construction Process Of Terrace Building (5 Duplex) at Lekki by tlops(m): 8:39pm On Oct 04, 2012 |
Hows work going on this site. |
| Re: Construction Process Of Terrace Building (5 Duplex) at Lekki by segcy.moor(m): 9:34pm On Oct 05, 2012 |
DAY 31...Filling work |
| Re: Construction Process Of Terrace Building (5 Duplex) at Lekki by segcy.moor(m): 8:05pm On Oct 06, 2012 |
DAY 32....Filling work in process |
(0) (1) (2) (3) (4) (5) (6) (7) (8) (9) ... (11) (Reply)
Who Can Supply Solar Energy In Nigeria!? / Lekki Conservation Centre, Lagos (pictures) / Cost Of Borehole Drilling In Lagos
(Go Up)
Sections: politics (1) business autos (1) jobs (1) career education (1) romance computers phones travel sports fashion health Links: (0) (1) (2) (3) (4) (5) (6) (7) (8) (9) Nairaland - Copyright © 2005 - 2013 Oluwaseun Osewa. All rights reserved. See Privacy Policy & Nairalist. 50.19.155.235 |