Re: The Making Of The Asaba "Stepped" Block Of 6 Flats Of 2 Bedrooms by spyder880(m): 8:16am On Mar 31, 2023 |
Lintels, columns in this building is getting our attention right now............
|
Re: The Making Of The Asaba "Stepped" Block Of 6 Flats Of 2 Bedrooms by spyder880(m): 8:19am On Mar 31, 2023 |
Getting ready for the decking, more pictures later today. |
Re: The Making Of The Asaba "Stepped" Block Of 6 Flats Of 2 Bedrooms by spyder880(m): 11:45am On Mar 31, 2023 |
More pictures from the lintels, column cast and levelling of blocks in readiness for the decking slab today...........
|
Re: The Making Of The Asaba "Stepped" Block Of 6 Flats Of 2 Bedrooms by spyder880(m): 12:04pm On Mar 31, 2023 |
Still offloading more blocks for levelling..............
|
Re: The Making Of The Asaba "Stepped" Block Of 6 Flats Of 2 Bedrooms by spyder880(m): 10:19pm On Apr 01, 2023 |
Bringing in more chippings..............
|
Re: The Making Of The Asaba "Stepped" Block Of 6 Flats Of 2 Bedrooms by spyder880(m): 10:23pm On Apr 01, 2023 |
Pictures from our works this week..........
|
Re: The Making Of The Asaba "Stepped" Block Of 6 Flats Of 2 Bedrooms by spyder880(m): 10:23pm On Apr 01, 2023 |
More pictures as we continue to cast the concrete beams and columns.............. 1 Like
|
Re: The Making Of The Asaba "Stepped" Block Of 6 Flats Of 2 Bedrooms by spyder880(m): 12:32pm On Apr 05, 2023 |
Still at this site, more updates later.........
|
Re: The Making Of The Asaba "Stepped" Block Of 6 Flats Of 2 Bedrooms by spyder880(m): 6:57am On Apr 06, 2023 |
Around this house as we conclude the ground floor walls...........
|
Re: The Making Of The Asaba "Stepped" Block Of 6 Flats Of 2 Bedrooms by spyder880(m): 7:07am On Apr 06, 2023 |
More pictures from around the ongoing building............
|
Re: The Making Of The Asaba "Stepped" Block Of 6 Flats Of 2 Bedrooms by spyder880(m): 7:09am On Apr 06, 2023 |
More........
|
Re: The Making Of The Asaba "Stepped" Block Of 6 Flats Of 2 Bedrooms by spyder880(m): 7:10am On Apr 06, 2023 |
More
|
Re: The Making Of The Asaba "Stepped" Block Of 6 Flats Of 2 Bedrooms by vastolord4(m): 8:35am On Apr 06, 2023 |
Omo the currency value is very bad.. wish I started mine 4 years back but the estimated value keeps getting high.. well, was advised to start first and won't even know when I complete it. Good work Mr spider 1 Like |
Re: The Making Of The Asaba "Stepped" Block Of 6 Flats Of 2 Bedrooms by spyder880(m): 9:57am On Apr 06, 2023 |
vastolord4: Welcome bro. 1 Like |
Re: The Making Of The Asaba "Stepped" Block Of 6 Flats Of 2 Bedrooms by spyder880(m): 8:07am On Apr 08, 2023 |
Awaiting the start of the decking works. |
Re: The Making Of The Asaba "Stepped" Block Of 6 Flats Of 2 Bedrooms by spyder880(m): 8:12am On Apr 14, 2023 |
We have started this decking slab works............
|
Re: The Making Of The Asaba "Stepped" Block Of 6 Flats Of 2 Bedrooms by spyder880(m): 8:14am On Apr 14, 2023 |
Some of the materials we bought for this works.........
|
Re: The Making Of The Asaba "Stepped" Block Of 6 Flats Of 2 Bedrooms by spyder880(m): 12:24am On Apr 19, 2023 |
Decking works continue after a brief stop due to community youths distributing the works............
|
Re: The Making Of The Asaba "Stepped" Block Of 6 Flats Of 2 Bedrooms by spyder880(m): 2:09pm On Apr 21, 2023 |
Progress report on the decking wooden platform..........
|
Re: The Making Of The Asaba "Stepped" Block Of 6 Flats Of 2 Bedrooms by dettolgel: 9:43pm On Apr 22, 2023 |
oga spyder I salute ooh. Biko we have a 80 X 60 plot of land in Abakpa, We are looking at building 6 blocks of flat; on the ground floor we will have on one side 2 bedroom flat and on the other side 3 bedroom flat. Then the first and second floor will be 3 bedroom flats. In total 5 units of 3 bedroom flats and 1 unit of 2 bedroom flat. Please based on your experience how much do you think we will require to build such a structure ? |
Re: The Making Of The Asaba "Stepped" Block Of 6 Flats Of 2 Bedrooms by spyder880(m): 10:23am On Apr 23, 2023 |
dettolgel: About N40m for the construction stages till roofing only. Materials prices are crazy in Asaba right now. Do you mean Asaba or Abakpa? |
Re: The Making Of The Asaba "Stepped" Block Of 6 Flats Of 2 Bedrooms by dettolgel: 1:45pm On Apr 23, 2023 |
spyder880: Thanks bros I meant Abakpa, I am switching letters again "Till roofing only" so no roofing ? Roofing, doors and window will set us back like how much ? 1 Like |
Re: The Making Of The Asaba "Stepped" Block Of 6 Flats Of 2 Bedrooms by spyder880(m): 3:00pm On Apr 23, 2023 |
dettolgel: Ok, I understand. In Abakpa, you can have the building done for N37.5m till roofing is completed. For a complete full finish with doors, windows, tiles, electrical fittings and painting all done, budget about N75m, no compound or fence works included. Just the main building. |
Re: The Making Of The Asaba "Stepped" Block Of 6 Flats Of 2 Bedrooms by spyder880(m): 10:04pm On Apr 26, 2023 |
We will start the iron reinforcement works for this decking by tomorrow, we aim to bring in our iron supplies by tomorrow morning............... More updates from this site tomorrow. |
Re: The Making Of The Asaba "Stepped" Block Of 6 Flats Of 2 Bedrooms by spyder880(m): 7:18pm On Apr 27, 2023 |
Pictures from our works at this site today...........
|
Re: The Making Of The Asaba "Stepped" Block Of 6 Flats Of 2 Bedrooms by spyder880(m): 7:21pm On Apr 27, 2023 |
Pictures from around the house today............
|
Re: The Making Of The Asaba "Stepped" Block Of 6 Flats Of 2 Bedrooms by spyder880(m): 7:24pm On Apr 27, 2023 |
Pictures from outside the site today............
|
Re: The Making Of The Asaba "Stepped" Block Of 6 Flats Of 2 Bedrooms by spyder880(m): 7:26pm On Apr 27, 2023 |
More from around the house............
|
Re: The Making Of The Asaba "Stepped" Block Of 6 Flats Of 2 Bedrooms by spyder880(m): 10:25pm On Apr 28, 2023 |
Buying iron reinforcement rods, and offloading then at the site..............
|
Re: The Making Of The Asaba "Stepped" Block Of 6 Flats Of 2 Bedrooms by spyder880(m): 10:30pm On Apr 28, 2023 |
Offloading the rods at site...... ...
|
Re: The Making Of The Asaba "Stepped" Block Of 6 Flats Of 2 Bedrooms by spyder880(m): 10:34pm On Apr 28, 2023 |
From the top...........
|
Re: The Making Of The Asaba "Stepped" Block Of 6 Flats Of 2 Bedrooms by spyder880(m): 10:36pm On Apr 28, 2023 |
More pictures from the top.............
|
(1) (2) (3) (4) (5) (6) (7) (8) (9) (10) ... (19) (Reply)
Lagos Vows To Enforce Monthly Rental Policy / *Updated*Properties In Ibadan To Let*With Pictures* / BEST QUALITY IMPORTED BULLETPROOF SECURITY DOORS AT REDUCED PRICES FOR HOMES
(Go Up)
Sections: politics (1) business autos (1) jobs (1) career education (1) romance computers phones travel sports fashion health religion celebs tv-movies music-radio literature webmasters programming techmarket Links: (1) (2) (3) (4) (5) (6) (7) (8) (9) (10) Nairaland - Copyright © 2005 - 2024 Oluwaseun Osewa. All rights reserved. See How To Advertise. 25 |