Milestone 2 Nearing Completion | Browne Mews by NextHome Cost till date - N8.2m (Fence, Main Building Foundation and Walls, and All Blocks required for this project.)
|
Browne Mews | Walls Up 3rd Milestone coming up shortly
|
EgunMogaji:Patiently waiting. |
I need GoPro Hero4. @EgunMogaji |
Another milestone nearing completion | Browne Mews |
EgunMogaji:Oga eghosajohnny, It's not my style to give advice on other peoples thread without taking permission from the OP. Sorry I had to do this for the diety! If the backfill was properly compacted and perimeter kept at a constant moisture and there's no leakage in the plumbing line, there wouldn't be any cause for alarm. That explains the reason why many agreed it's not necessary. What I said earlier is that it would have been better if there's reinforcement? Even with the reinforcement, hardcore and compaction - sand will still settle. |
The effect? Not catastrophic ![]() - Shrinkage/Settlement Crack - Misaligned Doors - Hollow sound in some area that settles faster due to poor compaction. The fix is to drill a hole and fill the void area. Also ensure that you keep your perimeter wall free from water. |
mrpally:No, the house is strong! But it would have been better if there's reinforcement (no matter how little) even if it is layers of hardcore prior to the slab. Here's a picture of a foundation after 10 months. What held the concrete in place is the reinforcement beneath the slab. Sand will definitely settle whether you're building a bungalow or storey buildings. Whether you use laterite or sharp sand to fill. Well done! https://www.youtube.com/watch?v=bDbVlYm6VOI |
None of the above. For £4m |
More pics from column and lintel concrete pour.
|
Villa Rosa | Roofing Milestone Achieved. Don't mind the picture quality.
|
Browne Mews by NextHome | Lintel and Columns Poured
|
Clean up
|
We're done | Time to clean up
|
Atlantic View by NextHome | Updates 2 Septic tanks poured. Roof Slabwork at 85%. Another milestone delivered. |
K-024 by NextHome | Another Milestone delivered. God has given me victory! |
K-024 | Updates In a structured environment like ours, everything requires documentation. The work we're doing now may spill over to the wee hours of the day and it's against the rules and regulations of the estate. So I'm meeting the estate manager for "Extended Work Hour Permit" in case we will ever need it. |
@smiley001, My stonedust at Browne Mews tomorrow pls! |
Atlantic View | Pre- Plastering Works Ongoing - Final fix electrical pipe work ongoing - Installation of scaffolds - Final fix mechanical works - Fabrication of window subframes started - Gate House | Maintenance room construction now ongoing. Picture updates coming soon. |
Chateau De Brabus | Our flagship project
|
Deliveries as at when needed | NextHome Dump Truck
|
K-024 | 40% Done
|
Updates | Atlantic View
|
NextHome Dump Truck | Always on time.
|
The best contemporary build of the year 2015! Seascape Villa | Atlantic View | K-024
|
Upcoming Update | Seascape Villa by NextHome |
Atlantic View | A perfect view of the ocean from the rooftop Update picture
|
K-024 by NextHome | What we are up against Almost 600sqm of floor space
|
NextHome Site Support Services | The things you don't have to pay for when you build with us. Each site has dedicated generator, hose, pumping and vibrator machine provided free of charge by NextHome. We provide them and fuel it at no cost to our clients
|
Yesterday, I had to reschedule K-024 and Atlantic View Concrete Pour for personal reason. Today, we are live! K-024 and Atlantic View is now been poured. Live updates from the two sites as we move. Over 120 workers are currently working at the 2 sites. 3 mixers and all site support equipment are in full use today. The biggest and the highest pour of the year happening now. |
Chateau De Brabus | The Entryway
|