Properties › Re: The Making Of The "Captivating" 5 Bedrooms Duplex In Enugu by spyder880(op): 8:26am On Mar 20, 2023 |
More blocks are being laid with some good speed ............
|
Properties › Re: The Making Of The "Captivating" 5 Bedrooms Duplex In Enugu by spyder880(op): 8:22am On Mar 20, 2023 |
We have started raising the block walls of this building...........
|
Properties › Re: The Making Of The "Captivating" 5 Bedrooms Duplex In Enugu by spyder880(op): 8:17am On Mar 20, 2023 |
michlins: what I think he is saying is this. Someone might be discouraged from starting a project because of the projected cost Thank you, how your side my man? |
Properties › Re: The Making Of The "Captivating" 5 Bedrooms Duplex In Enugu by spyder880(op): 5:31pm On Mar 17, 2023 |
From another side of the building..............
|
Properties › Re: The Making Of The "Captivating" 5 Bedrooms Duplex In Enugu by spyder880(op): 5:28pm On Mar 17, 2023 |
We have completed the concrete cast of the DPC for this house.............
|
Properties › Re: Estimates For Construction Of A 3 Bedroom Contemporary Bungalow In Rural Enugu by spyder880(op): 5:19pm On Mar 17, 2023 |
As seen from the top............
|
Properties › Re: Estimates For Construction Of A 3 Bedroom Contemporary Bungalow In Rural Enugu by spyder880(op): 5:17pm On Mar 17, 2023 |
More ............
|
Properties › Re: Estimates For Construction Of A 3 Bedroom Contemporary Bungalow In Rural Enugu by spyder880(op): 5:15pm On Mar 17, 2023 |
Pictures from our work at this site today............
|
Properties › Re: The Making Of The Asaba "Stepped" Block Of 6 Flats Of 2 Bedrooms by spyder880(op): 2:01pm On Mar 17, 2023 |
More works to be done here today as we plan to conclude the first stage, and move to the second stage within this weekend.
More updates later. |
Properties › Re: The Making Of The "Captivating" 5 Bedrooms Duplex In Enugu by spyder880(op): 7:59am On Mar 17, 2023 |
dominic17: Please how much has this project cost to get to this stage? My brother, let's not discuss budgets in the open like this, it may discourage a lot of people who wants to build in other places. Costs in a location may be very different from costs in another location. Thanks. |
Properties › Re: The Making Of The Asaba "Stepped" Block Of 6 Flats Of 2 Bedrooms by spyder880(op): 9:54pm On Mar 16, 2023 |
Concrete cast if the DPC starts..........
|
Properties › Re: The Making Of The Asaba "Stepped" Block Of 6 Flats Of 2 Bedrooms by spyder880(op): 9:53pm On Mar 16, 2023 |
Pictures from our works at this site, sand filling and wetting the foundation completed, we just completed the manual compaction to harden the soil in order to receive concrete..........
|
Properties › Re: The Making Of The "Captivating" 5 Bedrooms Duplex In Enugu by spyder880(op): 9:41pm On Mar 16, 2023 |
Some of the completed sections of the DPC............
|
Properties › Re: The Making Of The "Captivating" 5 Bedrooms Duplex In Enugu by spyder880(op): 9:22pm On Mar 16, 2023 |
Chidimercy: Please why do you have to spread the nylon doing the DPC, I was thinking the nylons on decking was to avoid wastage? Thanks for this question, the primary reason for spreading nylon sheets on top of a foundation is for damp prevention after the house is built, especially in a waterlogged area. But this site is not in a wet zone, not to talk of being waterlogged, but we had to do this to be on the safe side in case of future developments. |
Properties › Re: The Making Of The "Captivating" 5 Bedrooms Duplex In Enugu by spyder880(op): 4:37pm On Mar 16, 2023 |
Let's start the concrete cast of the DPC..............
|
Properties › Re: The Making Of The "Captivating" 5 Bedrooms Duplex In Enugu by spyder880(op): 4:34pm On Mar 16, 2023 |
Buying and spreading nylon sheets on this foundation course...........
|
Properties › Re: The Making Of The "Captivating" 5 Bedrooms Duplex In Enugu by spyder880(op): 7:58pm On Mar 15, 2023 |
The foundation as seen from a side of the building
|
Properties › Re: The Making Of The "Captivating" 5 Bedrooms Duplex In Enugu by spyder880(op): 7:43pm On Mar 15, 2023 |
The floor as at this evening..........
|
Properties › Re: The Making Of The "Captivating" 5 Bedrooms Duplex In Enugu by spyder880(op): 7:41pm On Mar 15, 2023 |
ValOkoye: Keep winning chief...I am in Enugu and I love what you are doing...I wish I can meet you. I am impressed in your work ethics. Thank you bro, you're welcome. |
Properties › Re: The Making Of The "Captivating" 5 Bedrooms Duplex In Enugu by spyder880(op): 7:32pm On Mar 15, 2023 |
Using a vibrating compactor machine to walk over this foundation, sinking in the top soil and firming it up for the DPC.
|
Properties › Re: The Making Of The "Captivating" 5 Bedrooms Duplex In Enugu by spyder880(op): 7:31pm On Mar 15, 2023 |
hypernikao: Top of the day to you chief, I am currently in the process of building a 3-bedroom bungalow and would like to know if it is important for me cast the DPC. The land is perfect and not water-logged, and I am getting different opinions, I would like to confirm from a professional.
Thanks you! The DPC is a building code requirement and is always included in building plans drawn by professionals, so, yes I recommend it, except where money is an issue and the land is firm and dry. I have seen people who didn't do a DPC and still lived in their houses without issues later on. |
Properties › Re: The Making Of The "Captivating" 5 Bedrooms Duplex In Enugu by spyder880(op): 4:16pm On Mar 15, 2023 |
Still offloading alot of materials for this DPC cast today, water, sand, stone, cement, etc.
|
Properties › Re: The Making Of The "Captivating" 5 Bedrooms Duplex In Enugu by spyder880(op): 3:36pm On Mar 14, 2023 |
Sinking the soul slowly..........
|
Properties › Re: The Making Of The "Captivating" 5 Bedrooms Duplex In Enugu by spyder880(op): 3:30pm On Mar 14, 2023 |
Watering the foundation today..........
|
Properties › Re: The Making Of The "Captivating" 5 Bedrooms Duplex In Enugu by spyder880(op): 12:11am On Mar 14, 2023 |
More pictures as we prepare to water this foundation before compaction.............
|
Properties › Re: The Making Of The "Captivating" 5 Bedrooms Duplex In Enugu by spyder880(op): 12:08am On Mar 14, 2023 |
Pictures from this foundation works today............
|
Properties › Re: The Posh 6 Flats Of 3 Bedrooms Block Of Flats In Enugu, The Construction Process by spyder880(op): 12:00am On Mar 14, 2023 |
Using an electric drill to get some speed on the well excavation..............
|
Properties › Re: The Making Of The "Emene Enugu Block Of 6 Flats Of 2 Bedrooms" by spyder880(op): 11:57pm On Mar 13, 2023 |
We are currently doing a parapet on these shops.........
|
Properties › Re: The Posh 6 Flats Of 3 Bedrooms Block Of Flats In Enugu, The Construction Process by spyder880(op): 8:23pm On Mar 13, 2023 |
Chidimercy: Please regarding this well, is there any Technology to know the waterline? Where one could easily get water? Yes, we did a Geophysical survey of the land to ascertain the level of water, and the most likely place in the compound 2here we can get good water. |
Properties › Re: The Posh 6 Flats Of 3 Bedrooms Block Of Flats In Enugu, The Construction Process by spyder880(op): 7:55am On Mar 13, 2023 |
Chidimercy: Please what's the size of this tank and what is the cost of each one? 500 gallons, GP brands costs N90,000 each, apart from the accessories. |
Properties › Re: The Posh 6 Flats Of 3 Bedrooms Block Of Flats In Enugu, The Construction Process by spyder880(op): 7:52am On Mar 13, 2023 |
We have hoisted all the tanks up on the tank stand.
We are still working on the manual borehole.
|
Properties › Re: The Posh 6 Flats Of 3 Bedrooms Block Of Flats In Enugu, The Construction Process by spyder880(op): 11:27pm On Mar 12, 2023*. Modified: 7:50am On Mar 13, 2023 |
kopell: Oga sypder well-done ooo. I kwon understand this 7 months thing in a year, what happens to the remaining months of the year? does this mean the well dry up for those months redgem: Meaning you pay 200k for water every 7 months...like they pump into a well for you? Or how is it done? Nooooo  I paid 70k to dig a well since 2016, bought submersible pump with 45k, paid well diggers for plastering, bought cement, sand and well cover, paid for pipes and plumbing, altogether, about N200,000. Then I haven't spent any other money on the maintenance of the well since 2016 that I moved into the house. Since then I haven't spent a dime on the well, but I get steady water supply pumped up my overhead tank for 7 months out of 12 months in a year. I only buy water from January till March each year when the well dried up. Enugu water is not costly. |