Re: Construction Process Of A Wing Duplex+flat At Ajah by segcymoor(m): 4:20pm On Apr 22, 2012 |
and finally concrete work.....with this process, ur foundation is 99.5% safe
|
Re: Construction Process Of A Wing Duplex+flat At Ajah by blacklion(m): 7:50pm On Apr 22, 2012 |
segcy.moor: Segcy, This surface treatment is done before the German floor? |
Re: Construction Process Of A Wing Duplex+flat At Ajah by aglomar: 9:06am On Apr 23, 2012 |
GIVE THIS BUILDING AN INTERNATIONAL QUALITY FINISHING We represent Aglomar SL, Monaco, Spain, makers of a unique range of water tight finishing products that have been used all around the world. Our products include the dual-purpose plaster paint, Brazilian stone, Sile stone, marble & tiles etc. The dual purpose plaster paint is essentially pigmented cement that simultaneously plasters and paints any surface, with the paint being durable for 12 years. These products are resistant to tropical weather and will meet your buildings' need for intl quality, durability, safety and protection. They are water-tight and come in all imaginable colours. Contact us today for a news[color=#006600][/color]letter (or e-mail), our catalog, VCD or a sample. T: 0813 2232 989, 0818 8360 168 W: www.ugo-rosis..com 1 Like |
Re: Construction Process Of A Wing Duplex+flat At Ajah by segcymoor(m): 5:09pm On Apr 25, 2012 |
blacklion. yes it done prior to german floor |
Re: Construction Process Of A Wing Duplex+flat At Ajah by segcymoor(m): 6:46pm On Apr 26, 2012 |
DAY 25-27 WE CONTINUE WTH FRAME STRUCTURE
|
Re: Construction Process Of A Wing Duplex+flat At Ajah by segcymoor(m): 6:49pm On Apr 26, 2012 |
those were d imported iron to carry d decking
|
Re: Construction Process Of A Wing Duplex+flat At Ajah by tolu10: 12:01pm On Apr 27, 2012 |
@segcy.moor,Keep up the good work and thanks for sharing! |
Re: Construction Process Of A Wing Duplex+flat At Ajah by segcymoor(m): 8:06pm On Apr 27, 2012 |
DAY 27; Reinforcement has been placed but before we place wood form work. We create Kicker
|
Re: Construction Process Of A Wing Duplex+flat At Ajah by segcymoor(m): 8:08pm On Apr 27, 2012 |
kicker
|
Re: Construction Process Of A Wing Duplex+flat At Ajah by segcymoor(m): 6:46pm On Apr 28, 2012 |
DAY 28;We established the Column |
Re: Construction Process Of A Wing Duplex+flat At Ajah by segcymoor(m): 6:49pm On Apr 28, 2012 |
FORM WORK
|
Re: Construction Process Of A Wing Duplex+flat At Ajah by segcymoor(m): 6:52pm On Apr 28, 2012 |
men at work
|
Re: Construction Process Of A Wing Duplex+flat At Ajah by segcymoor(m): 7:02pm On Apr 28, 2012 |
form work
|
Re: Construction Process Of A Wing Duplex+flat At Ajah by segcymoor(m): 5:06pm On Apr 30, 2012 |
Columns estabished
|
Re: Construction Process Of A Wing Duplex+flat At Ajah by segcymoor(m): 5:07pm On Apr 30, 2012 |
men work at work
|
Re: Construction Process Of A Wing Duplex+flat At Ajah by segcymoor(m): 6:29pm On May 03, 2012 |
DAY 30-We continue wth d formwork for beam
|
Re: Construction Process Of A Wing Duplex+flat At Ajah by segcymoor(m): 6:33pm On May 03, 2012 |
Call us on 07042144750, 08023807960 or--mooredesignbuild@gmail.com for enquiry on this project
|
Re: Construction Process Of A Wing Duplex+flat At Ajah by segcymoor(m): 8:26pm On May 04, 2012 |
DAY 31
|
Re: Construction Process Of A Wing Duplex+flat At Ajah by segcymoor(m): 8:29pm On May 04, 2012 |
formwk 1 Share
|
Re: Construction Process Of A Wing Duplex+flat At Ajah by segcymoor(m): 6:33pm On May 05, 2012 |
DAY 32,Slab formwk
|
Re: Construction Process Of A Wing Duplex+flat At Ajah by segcymoor(m): 6:35pm On May 05, 2012 |
men at work..
|
Re: Construction Process Of A Wing Duplex+flat At Ajah by segcymoor(m): 6:39pm On May 05, 2012 |
work..
|
Re: Construction Process Of A Wing Duplex+flat At Ajah by segcymoor(m): 5:05pm On May 06, 2012 |
work free day |
Re: Construction Process Of A Wing Duplex+flat At Ajah by ahf(m): 8:49pm On May 06, 2012 |
After casting german-floor,which is better to do next? Cast columns and deck or do blockwork first? What are positives and negatives? |
Re: Construction Process Of A Wing Duplex+flat At Ajah by segcymoor(m): 7:36pm On May 08, 2012 |
DAY33-34
|
Re: Construction Process Of A Wing Duplex+flat At Ajah by segcymoor(m): 7:41pm On May 08, 2012 |
proffessionals putting head together wth workers
|
Re: Construction Process Of A Wing Duplex+flat At Ajah by segcymoor(m): 7:42pm On May 08, 2012 |
work in progress
|
Re: Construction Process Of A Wing Duplex+flat At Ajah by segcymoor(m): 8:02pm On May 09, 2012 |
DAY 35-Reinforcemt work
|
Re: Construction Process Of A Wing Duplex+flat At Ajah by segcymoor(m): 8:16pm On May 10, 2012 |
DAY36
|
Re: Construction Process Of A Wing Duplex+flat At Ajah by segcymoor(m): 8:24pm On May 10, 2012 |
Project Engr examine d reinfocemt wk
|
Re: Construction Process Of A Wing Duplex+flat At Ajah by omanzo02: 5:54pm On May 11, 2012 |
Nice job dude |
Re: Construction Process Of A Wing Duplex+flat At Ajah by segcymoor(m): 8:13pm On May 11, 2012 |
DAY 37--working toward decking
|
(1) (2) (3) (4) (5) (6) (7) (8) (9) (10) ... (40) (Reply)
WATCH THIS SPACE (Electrical Showcase & Review) / Man Builds House With 14,800 Plastic Bottles In Kaduna (pics) / Latest New Year Promo Prices For High Quality Imported Doors.
(Go Up)
Sections: politics (1) business autos (1) jobs (1) career education (1) romance computers phones travel sports fashion health religion celebs tv-movies music-radio literature webmasters programming techmarket Links: (1) (2) (3) (4) (5) (6) (7) (8) (9) (10) Nairaland - Copyright © 2005 - 2024 Oluwaseun Osewa. All rights reserved. See How To Advertise. 18 |