| Re: Construction Process Of A Wing Duplex+flat At Ajah by segcy.moor(m): 8:17pm On May 11, 2012 |
Beam |
| Re: Construction Process Of A Wing Duplex+flat At Ajah by segcy.moor(m): 7:54pm On May 12, 2012 |
DAY 38 |
| Re: Construction Process Of A Wing Duplex+flat At Ajah by segcy.moor(m): 7:59pm On May 12, 2012 |
men at work |
| Re: Construction Process Of A Wing Duplex+flat At Ajah by Oluwa4Sure: 10:05pm On May 12, 2012 |
Mr. Segcy.moor, Can you please tell me the purpose of 'kickers' you mentioned earlier Secondly, I noticed your Columns you used a 4" by 6" square rod(the name escaped my head) But i thought the 6" by 5" or even 8" by 8" would have being better. So if i may ask, is the 4" by 6" better than the later? |
| Re: Construction Process Of A Wing Duplex+flat At Ajah by segcy.moor(m): 2:37pm On May 13, 2012 |
pls i dont understand what u mean by 4 or 6. I used imported ukraine of 16mm and 18mm for column |
| This post has been hidden |
| Re: Construction Process Of A Wing Duplex+flat At Ajah by Akdams(m): 1:48am On May 14, 2012 |
Landscaping work, flowers and car ports Contact us Dapo 08120160199 Email : akdam_multiwealth@yahoo.com |
| Re: Construction Process Of A Wing Duplex+flat At Ajah by segcy.moor(m): 8:03pm On May 14, 2012 |
DAY 39--Working on slab reinfocement |
| Re: Construction Process Of A Wing Duplex+flat At Ajah by segcy.moor(m): 8:06pm On May 14, 2012 |
men at work |
| Re: Construction Process Of A Wing Duplex+flat At Ajah by segcy.moor(m): 8:48pm On May 15, 2012 |
DAY 40--REINFORCEMENT |
| Re: Construction Process Of A Wing Duplex+flat At Ajah by segcy.moor(m): 8:51pm On May 15, 2012 |
TECHNICAL WORK |
| Re: Construction Process Of A Wing Duplex+flat At Ajah by segcy.moor(m): 8:54pm On May 15, 2012 |
men at work... |
| Re: Construction Process Of A Wing Duplex+flat At Ajah by segcy.moor(m): 7:54pm On May 16, 2012 |
DAY 41 |
| Re: Construction Process Of A Wing Duplex+flat At Ajah by segcy.moor(m): 7:52pm On May 17, 2012 |
DAY 42 |
| Re: Construction Process Of A Wing Duplex+flat At Ajah by segcy.moor(m): 7:57pm On May 17, 2012 |
men at work |
| Re: Construction Process Of A Wing Duplex+flat At Ajah by segcy.moor(m): 9:52pm On May 20, 2012 |
DAY 43-45 |
| Re: Construction Process Of A Wing Duplex+flat At Ajah by segcy.moor(m): 10:13pm On May 20, 2012 |
casting |
| Re: Construction Process Of A Wing Duplex+flat At Ajah by segcy.moor(m): 7:02pm On May 21, 2012 |
I met this project Client on NL and he reside in UK. We are able to manage his fund well |
| Re: Construction Process Of A Wing Duplex+flat At Ajah by segcy.moor(m): 7:09pm On May 23, 2012 |
DAY 46---Having wait for 4 days for decking to dry. we intend to continue block work |
| Re: Construction Process Of A Wing Duplex+flat At Ajah by ahf(m): 6:33am On May 24, 2012 |
Please is there any standard (or industry) criteria for period to wait after decking before commencing upper blockwork? How does the 28days for concrete to cure factor in ? |
| Re: Construction Process Of A Wing Duplex+flat At Ajah by segcy.moor(m): 10:55am On May 25, 2012 |
DAY 47-Blockwork |
| Re: Construction Process Of A Wing Duplex+flat At Ajah by segcy.moor(m): 11:04am On May 25, 2012 |
Having cast d decking. we need to do what we call after treatment(the decking will be througly wet with water early monring before d sun rise and in the evening consecutive for atleast 4 day of casting) this is to ensure the decking absorbe water and this make it more stronger. Meawhile, one can proceed to set block after 4 day but to remove the plank after 28 days of casting |
| Re: Construction Process Of A Wing Duplex+flat At Ajah by segcy.moor(m): 8:04pm On May 26, 2012 |
DAY 48 |
| Re: Construction Process Of A Wing Duplex+flat At Ajah by segcy.moor(m): 4:50pm On May 29, 2012 |
DAY 49-50 |
| Re: Construction Process Of A Wing Duplex+flat At Ajah by segcy.moor(m): 4:52pm On May 29, 2012 |
Meanwhile, that was part our step. The theory behind this step is Aeroplane with wing. The wing of the step stand without anything hold it......it's purely structural work. By the time one put mable on this step. Forget it! |
| Re: Construction Process Of A Wing Duplex+flat At Ajah by segcy.moor(m): 6:44pm On May 31, 2012 |
DAY 51-53 |
| Re: Construction Process Of A Wing Duplex+flat At Ajah by segcy.moor(m): 6:35pm On Jun 02, 2012 |
DAY 54 |
| Re: Construction Process Of A Wing Duplex+flat At Ajah by segcy.moor(m): 8:32pm On Jun 05, 2012 |
DAY 55-56 |
| Re: Construction Process Of A Wing Duplex+flat At Ajah by segcy.moor(m): 7:36pm On Jun 08, 2012 |
DAY 57-59 |
| Re: Construction Process Of A Wing Duplex+flat At Ajah by segcy.moor(m): 7:54pm On Jun 11, 2012 |
DAY 60-61 |
| Re: Construction Process Of A Wing Duplex+flat At Ajah by segcy.moor(m): 8:01pm On Jun 13, 2012 |
DAY 62-63 |
| Re: Construction Process Of A Wing Duplex+flat At Ajah by Taliban: 3:07pm On Jun 14, 2012 |
Great job. |
(0) (1) (2) (3) (4) (5) (6) (7) (8) (9) ... (18) (Reply)
Land Fraudsters Tricks I Learnt In 2010 And Tips On How To Avoid Them This 2011 / POP & PVC CEILINGS, SCREEDING AND PAINTING. (PICTURES) / Will These Home Designs Sell In Nigeria, And Where?
(Go Up)
Sections: politics (1) business autos (1) jobs (1) career education (1) romance computers phones travel sports fashion health Links: (0) (1) (2) (3) (4) (5) (6) (7) (8) (9) Nairaland - Copyright © 2005 - 2013 Oluwaseun Osewa. All rights reserved. See Privacy Policy & Nairalist. 23.20.196.179 |