mufutau55:welcome sir |
setting out procedures 1. establishement of the building line 2. the other corners of the building is set at right angle to the building line using builder's square to get the correct andgle and a meter rule to measure the horizontal distance. allowance is made to allow for sagging of the meter rule. 4. the four cotners of the building is set and pegged. 5. A nail is placed ontop of the four pegs and each ate connected to form a perfect rectangle or square as the case may be. 6. from these four corners, an ofset of 1.2m or 1.5m ( to allow for digging and carting away of excavated material) is allowed from these four corners pegs. 7. The four offsets pegs are nailed an line connected to them to form another perfect rectangle and square as the case may be. 8. across the new line pegs are spaced at 2m c/c fo form a continuous chain of peg to wish profile boards are nailed to form a profile. 9 The structural building plans is transferred carefully to the profile. 10. at each grid line on the drawing a corresponding 5 nails are placed on the profile as follows. the center nail represent the grid, the next two nail represent the width of block while the last two nail represent the width of the foundation |
more
|
more pics
|
setting out picture
|
setting out: material includes the following 1. pegs : 7 boundle @ N1000 = N7, 000 2. profile board = 120 2" x 2" @ N250 = N30, 000 3. line, builder's square, claw hammer, heavy hammer, meter rule = N20, 000 4. miscellaneous = N10, 000 total = N67, 000 |
more picture
|
emmadejust:na only be say I still dey fear ebola |
more pics
|
pics
|
site clearance equipment = bulldozer duration of work = 2 days cost of clearance = 200k |
the construction of 14 block ube primary school at emuhoa community rviers state. project duration = 3 months starting date = 1st march 2015 |
lamido os just confused and desperate to be in good term with thief jeg. There is no such thing as muslim north and christiqn south. jonqthqn is from swampy bayelsa and doesn't represent all the good people of so called southern Nigeria state. There is no such thing as Christian south and muslim north. yorubas are muslim as well as Christmas, yorubas don't vote based on religious sentiment. Buharis is the people's choice |
Mushood:ok I will check |
Icon4s:people over spend alot by not planning properly while building a house. The following information can help low cost house builders 1.Do your architectural design focusing more on functionality than aesthetic. e.g don't proposed unnecessary curve, too many corners, very high roof etc. 2. Try do a 3 D . the 3 D allows for modifications and changes to be made b4 actual construction. 3. Try to do the setting out to make sure thee house is straight ( since itt cost little in the longg round) 4. supervise the construction together with a professional if you have the time or give a professional to supervised the job 5. Always procure materials yourself and don't be a victim of those so called building suppliers ( you can go with your site supervisor). 6. Get a good brick layers/mason for your job. give the block work out on a contract like N50/block, plastering out for N1200/partions. build q simple roof type and give the job to a good carpentern |
[quote author=drkay post=31207632][/quote]congratulations sir, it is really valuable here to hear from house owners. people always make that mistake of having a close friends suplying materials. The truth is suppliers are bad for the business they definitely inflate your price to make extra gain. you could have spend less if you had access to these information earlier. I like the part " trust your employee till you catched them red handed" |
Dieumerci:it is a template for the calculation of materials required in the production of concrete using mix ratio of 1:2:4. you can always use it for other operation like column, beam, slab etc by changing parameters like the length, width and thickness |
mufutau55:thank you sir |
more
|
some pics
|
emmadejust:bro...were you at the site. I left the site around 2:45 |
felifeli:It has been received sir...I will send a detailed provisional estimate tonight. thank you sir |
felifeli:phone no : 08169492682 email : jwastecx@gmail.com how many bedrooms are we talking about? |
description of setting out Date : 01-03-2015 materials: two bundle of peg ( 24/bundle) @ N1000/peg = N2000 profile board ( 2x2" : 20 @ N250/nr = N5000line and other miscellaneous = N3000 labour = N 2000 workmanship = N 10, 000 Total = N22, 000 |
Mushood:I always convert from mm to m when I want to do any calculation remember 1m = 1000mm |
1 2 3 4 5 6 7 8 ... 84 85 86 87 88 89 90 91 92 (of 127 pages)
: 20 @ N250/nr = N5000