Properties › Re: Ikorodu Half Plot - 4 Bedroom Executive Duplex Active Construction by Dennis3D(op): 12:32pm On Oct 29, 2021 |
Hatesin: Well explained. Thanks for your time and good luck in your endeavors. Urw sir. Thank you for your time here |
Properties › Re: Ikorodu Half Plot - 4 Bedroom Executive Duplex Active Construction by Dennis3D(op): 11:14am On Oct 29, 2021 |
Hatesin: Wow! 5 courses only and am seeing 2 blocks outside. Does it mean that 4 courses will still be considered ok? 4 coarses is not entirely bad depending on your natural road level. The road here is not tarred or worked upon yet. So I took into consideration future road development on this particular project. Though that costed us additional 2 Trips of filling sand from the estimated 6 Trips. We now did 8 trips of 20 Tons filling sand. So check your road level before concluding yours. Thanks |
Properties › Re: Ikorodu Half Plot - 4 Bedroom Executive Duplex Active Construction by Dennis3D(op): 9:54am On Oct 29, 2021 |
It's now time for us to apply our membrane. It will equally be blinded today.
|
Properties › Re: Ikorodu Half Plot - 4 Bedroom Executive Duplex Active Construction by Dennis3D(op): 9:53am On Oct 29, 2021 |
Hatesin: Nice one there. How many courses is the foundation? We did 5 for this foundation. Foundation height from natural ground is about 900mm. When we do German floor (site concrete slab) - It will be 1050mm above the ground. |
Properties › Re: Ikorodu Half Plot - 4 Bedroom Executive Duplex Active Construction by Dennis3D(op): 9:26pm On Oct 28, 2021 |
Stay tuned still. Updates coming tomorrow |
Properties › Re: Ikorodu Half Plot - 4 Bedroom Executive Duplex Active Construction by Dennis3D(op): 6:44am On Oct 28, 2021 |
Good morning Viewers |
Properties › Re: 5 Bedroom Mansion (Duplex) Aba - Abia State Project by Dennis3D(op): 6:42am On Oct 28, 2021 |
Good morning... |
Properties › Re: 4 Bedroom Duplex Construction: Live Photos - Less than half plot - Agege Lagos by Dennis3D(op): 6:42am On Oct 28, 2021 |
Good morning |
Properties › Re: Semi Detached - 6 Bedroom Duplex with Pent House Construction - Osapa London by Dennis3D(op): 8:49pm On Oct 27, 2021 |
We are starting pent house next week So stay tuned here... |
Properties › Re: New 4 Flats Construction -Ile Ife Osun State by Dennis3D(op): 8:48pm On Oct 27, 2021 |
We are coming back here soon |
Properties › Re: Ikorodu Half Plot - 4 Bedroom Executive Duplex Active Construction by Dennis3D(op): 8:44pm On Oct 27, 2021 |
Plumbing work Details. Ground Floor and upper floor piping all started from here (Foundation Stage). Filling of the foundation ongoing simultaneously
|
Properties › Re: Ikorodu Half Plot - 4 Bedroom Executive Duplex Active Construction by Dennis3D(op): 4:58am On Oct 26, 2021 |
Good morning Viewers |
Properties › Re: Ikorodu Half Plot - 4 Bedroom Executive Duplex Active Construction by Dennis3D(op): 12:20pm On Oct 25, 2021 |
We are now back filling
|
Properties › Re: New 4 Flats Construction -Ile Ife Osun State by Dennis3D(op): 8:43pm On Oct 24, 2021 |
FYI
|
Properties › Re: Semi Detached - 6 Bedroom Duplex with Pent House Construction - Osapa London by Dennis3D(op): 8:43pm On Oct 24, 2021 |
FYI
|
Properties › Re: Ikorodu Half Plot - 4 Bedroom Executive Duplex Active Construction by Dennis3D(op): 8:42pm On Oct 24, 2021 |
Take a look at the site plan of this project below. As well as other views of the plan on 2D
|
Properties › Re: Oke Aro Ogun State Project - A 4 Bedroom Duplex With Saloon by Dennis3D(op): 7:34am On Oct 24, 2021 |
Good morning |
Properties › Re: New 4 Flats Construction -Ile Ife Osun State by Dennis3D(op): 7:34am On Oct 24, 2021 |
Good morning |
Properties › Re: 10 Rest Room School Reconstruction Project - Sponsored by Rotary Club of Ojodu by Dennis3D(op): 7:34am On Oct 24, 2021 |
Good morning |
Properties › Re: Ikorodu Half Plot - 4 Bedroom Executive Duplex Active Construction by Dennis3D(op): 7:30am On Oct 24, 2021 |
We would be casting the short pillars asap... Planks and Nails are here for that purpose already.
|
Properties › Re: Semi Detached - 6 Bedroom Duplex with Pent House Construction - Osapa London by Dennis3D(op): 7:29am On Oct 24, 2021 |
Good morning Electrical Piping ongoing on the internal walls.
|
Properties › Re: Semi Detached - 6 Bedroom Duplex with Pent House Construction - Osapa London by Dennis3D(op): 5:07am On Oct 24, 2021 |
See how the second decking now looks like just 2 days after pouring the concrete
|
Properties › Re: Ikorodu Half Plot - 4 Bedroom Executive Duplex Active Construction by Dennis3D(op): 5:03am On Oct 24, 2021 |
Block works have commenced here. We are targeting to use 900 Blocks on this foundation already.
|
Properties › Re: 10 Rest Room School Reconstruction Project - Sponsored by Rotary Club of Ojodu by Dennis3D(op): 10:48pm On Oct 22, 2021 |
..... |
Properties › Re: Semi Detached - 6 Bedroom Duplex with Pent House Construction - Osapa London by Dennis3D(op): 10:47pm On Oct 22, 2021 |
Picture updates to come here tomorrow. Stay tuned to see how it all came out. |
Properties › Re: Ikorodu Half Plot - 4 Bedroom Executive Duplex Active Construction by Dennis3D(op): 10:47pm On Oct 22, 2021 |
We faced so much rain today, however. We weren't deterred from doing the much we had to do today. Tomorrow is another day and we will definitely do our best. |
Properties › Re: Ikorodu Half Plot - 4 Bedroom Executive Duplex Active Construction by Dennis3D(op): 4:36pm On Oct 22, 2021 |
Just as promised. Here is what we are doing here today. Completing the colum layouts and grids.
|
Properties › Re: Semi Detached - 6 Bedroom Duplex with Pent House Construction - Osapa London by Dennis3D(op): 8:09am On Oct 22, 2021 |
Good morning all This is how we worked yesterday.
|
Properties › Re: Ikorodu Half Plot - 4 Bedroom Executive Duplex Active Construction by Dennis3D(op): 8:04am On Oct 22, 2021 |
Good morning Followwers. We would begin block setting and colum alignment this morning |
Properties › Re: Ikorodu Half Plot - 4 Bedroom Executive Duplex Active Construction by Dennis3D(op): 3:16pm On Oct 21, 2021 |
Blinding works going on here today too.
|
Properties › Re: Semi Detached - 6 Bedroom Duplex with Pent House Construction - Osapa London by Dennis3D(op): 3:13pm On Oct 21, 2021 |
Second Decking concrete work day Our routine is Beams and Staircase First. Our vibrator machine is equally and routinely at work with us.
|
Properties › Re: Semi Detached - 6 Bedroom Duplex with Pent House Construction - Osapa London by Dennis3D(op): 7:35am On Oct 21, 2021 |
The D Day
|