The concluded pix to roof level of the project
|
More
|
Good day all
|
Good day all
|
It will work it's just a little time of thinking,you will get it. I'm trying to get a sketch out now for 2flats you can call me or email on the following contacts below. 07014709098,07031886484 Mail:johnontop14@yahoo.com |
Pix
|
More pics
|
More pics on the project as we have already completed the project
|
PeoplesArmy:People like you never grow you hear something you didn't see you are following me about like an environmental demon shame on you go and find something reasonable to do with your life and time jobless man. If you are reasonable enough you will that it's always good to allow someone handling something for you to do what is right and not insisting. |
Hello all and how are you all doing,weve done so many things on site in the days past and we have completed the second building to roof which has led us to a break and will resume very soon. Pix below shows all we have done
|
More pix
|
Picx of the second building as we just concluded the the iron work and a pedestrian linking the 2building together
|
Picx of the completion of. This building
|
Happy Sunday all, below is the continuation of the progress of work ongoing
|
Block work to lintels
|
I've being busy that's why I've not being able to share with you all this update even when that issue was on I was working here all the same respect to you sir cos you really deserve to be respected. More pix on the block work
|
Sir I'm always loyal to you from the way you approach issue on this thread infact you are a great man and I will always respect you always hope all is well with you sir and your work too. We are always at your service and our contact still remain; Mail:johnontop14@yahoo.com Phone:07031886484,07014709098, Whatsapp:same number above
|
Block work progress
|
More
|
More
|
Pix
|
More pix
|
More Pix on the decking
|
Hello Fellows and welwishers in this forum join me as I share with you the updates in the construction of the above titled project. The ground floor was done before my arrival and I started from the decking of the first building which is raised to roof level and the second building decking is ongoing. I want everyone in the house to comment as we are all learning and I intend to show that I'm willing to take correction on any area that needs correction. PROJECT TYPE:40 ROOMS HOTEL CLIENT:NAIRALANDER CONTRACTOR:J O I CONSTRUCTION Pix below will show all we've done so far
|
enoqueen:Enoqueen pls mind the way you interfer in peoples business as you weren't there to confirm all the stories wrote that you read and I still say it that I owe nobody and if you have an email I can forward all the payment made and the mail acknowledgement so pls don't bring another tread to this cos what I endured there you won't take a quater,I give quote cos I know it is what will do the job not becos I need the job its every clients decision to invite who he intends to use and as I speak I'm handling a better project just being a little busy to open the tread which I will before the week runs below is the pic the same client saw this oyewoles tread I know what he said so pls don't judge who you don't know if you want to know me invite me with close watch unknown to me there you can call me what ever. The quote for a twin 2bedroom with everything mentioned will take 6.3m Below is the pics of my ongoing 40 rooms hotel project I'm sure you know what will be involved and till now no penny is taken pls back off
|
I am a builder and will appreciate any client who will give me the chance to work for him or her. Here are my contact 07031886484, Whatsapp 07014709098 BBM 27afc1c0 Johnontop14@yahoo.com Kindly contact me |
I am a builder and will appreciate any client who will give me the chance to work for him or her. Here are my contact 07031886484, Whatsapp 07014709098 BBM 27afc1c0 Johnontop14@yahoo.com Kindly contact me |
I am a builder and will appreciate any client who will give me the chance to work for him or her. Here are my contact 07031886484, Whatsapp 07014709098 BBM 27afc1c0 Johnontop14@yahoo.com Kindly contact me[/quote] |
HsLBroker:I never said anything to you,and its shame you are putting your accident on me when you know how drunk look the first day I entered this jeep of yours,I had to pray that we get to your hotel on time and when you said you should drop me remember I insisted that I will rather take an okada and also even this you are saying I had the accident first the second day after the plastering was given to you and took me 3days at home and the leg still disturbed me for some time I didn't say it was or did you had a hand in it cos that's the only reason that will make you think I caused your accident after accusing me that I swore for you which never happened,you didn't checking your drunk attitude and driving,mine was behind cos I don't get drunk and drive the same time, you really have to stop that and not pointing fingers on someone else. All the same hope you weren't that hurt cos I will never think eveil of anybody cos of money I will die on day and leave,speedy recovery
|
And another thing I did not give cheap quote to get the job I only gave what I felt would take the project and it didn't fail the only extra request I made was 300 blocks as a result of excessive breakages so if you are saying the cheapest isn't the best well know the area you are putting cos no engineer or builder will intensionally do something that he knows will affect him sometime one just don't get lucky like when you said follow the architech if I had done that it would have been another war when the second staircase was not included and I saw it and told dr and he told the arc to put if I had went on I know the storey woulDd have being worse or is that one too a lie. |
HsLBroker:Were you called for plastering job or roofing job and after that you went to tell doc that I was using blocks not strong for the only building he handed to me directly and told him you will take the plastering when doc has mobilised me and before he brought the money i have fixed the whole frame and paid for the labour and cement and before I new it the job was taken and the fence work we discussed again was taken before I new what was going and this were the reason I just got fedup of the whole thing and left cos I can't be on site where we discussed a supervision based on the ground that I will handle the plastering jobs and if I can get someone for other jobs that he will give me the job if the price is good but later said I shouldn't bother and I relaxed. The true thing here is because my case is up here that's why its alarming every body is a saint if he's not proven dr has being threatening about coming to nl and always telling me to leave his site I will just try and calm him down because I want see the work to completion personally and ii was already working on the parapet too. He is claiming I made away with his money and like I said the front fence that is remaining hanging of gate my balance 49,000 is with him the parapet I have 28,000 with him,the money I spent in hanging the frames 18,000 my supervision fee I assume 20-30k with him cos its only remaining tiles hanging of pop and plumbing,electrical fittings before painting all this put together can do the parapet cast the gate and even pay the electrician cos I know I owe the man and no one else. One last and true thing is for builders and engineers no one is above this mistakes but because you aren't brought out u want to kill the one that's out,someone here worked for the same dr and plumbing issue is still on in the building or the project in ogombo on a thread DESMOND flats you know what you did there all this was quiet cos the client didnt want to talk. DR I'm not owing you and you know that I'm just fed up with the way you started doing thing with me and if not for the parapet issue I would have left too since u decided to give the job we agreed on to a fello who claimed to be a nl like me and he's here barking that his plastering work is delayed. I made an error that's true but it doesn't make me a slave that I don't have my decisions and as I'm talking now I'm on a better project where the client respent his builder and believes his word and will be sharing it soon. DR you only came with the intension to spoil me but you are not GOD and with this thread this particular I've being lifted so you see GOD is not man |
I have done the pillar and beam and has cast the pillars before I left I just need to cast the beam the run the parapet that's all not that I just left it undone at all. Sir segcy you might be right on the pix about the beam I just don't know but the spaces between yours and this might be different in the lenght I'm just saying and for the casting or the building in general the cement is strong that I know. Sir adventure the article you wrote has nothing to do with what happened in anyway,a full building is standing and we are just saying things as if the building entirely is down,well it has happen and I really accept my fault but don't make things look like I've killed someone,I know better eng than people here have made mistakes too so pls let's be straight,that's the pix of what I've done so far and to crown it all I'm not a scam or a fraud if someone doesn't work for someone again though not like this does not make that person a fraud the job I did in ebonyi the lowest I'm paid there is 3m and I use it for there work the preson I owe is electrician and I stiill have balance with doctor I don't take clients money GOD forbid I just don't like the way things are going that's why I left thast all.I will talk to my carpenter tomorrow on how he will come board the parapet and when you say desperation on getting a job all that is wrong,I came to the forum new and didn't know how to go about it that was when I was on peoples thread and after I new I stoped even before I got the first job I stopped all that.
|
Na wa o....people never learn.