PropertiesRe: General Topic Thread-To Discuss Anything And Everything in Building Construction by Thenext: 9:09pm On Oct 30, 2020
Just to give my feedback on the granite I bought from Chekitaut, I can confirm to the house that he made the delivery of the granite on time as promised and the quantity of the granite is confirmed by my Engr. compared to the one we bought before. Keep it up bro and warm up for granite supply for the decking. Attached is the picture of the 30 tons he supplied for me.

PropertiesRe: General Topic Thread-To Discuss Anything And Everything in Building Construction by Thenext: 6:25pm On Oct 27, 2020
Thanks for your contribution. The project will run between 12-15 months due to funds.

n3xt:
- 7.5 - 8% of the total contract sum should be fine regardless of his expertise and the complexity of the project.

- Make installmental payments based on milestones achieved.

- Retain 20% holdback for 30 days after
completion of work.

______

The build can’t be more than a duplex. N4m supervision fee for a duplex ain’t too bad.

The project can be completed within 90 days at average of 40k per day shocked
PropertiesRe: General Topic Thread-To Discuss Anything And Everything in Building Construction by Thenext: 12:14pm On Oct 27, 2020
My Engr. said the least he can collect from me is 10%. He is highly experienced and very good in the field, he built my home country house for me around 2016 and the building is fantastic. In short he is very good and has many projects(private and government) he is handling currently.

micgray100:
As a registered Engineer, we use total sum and source of project to determine Engineer's cost..

Total Sum of project Less than 50million and Private owned, can be percentaged at 2.5%


Total Sum of project Less than 50million and govt own /big multinational company, can be percentaged at 5%


Total Sum of project more than 50million and Private owned, can be percentaged at 5%


Total Sum of project more than 50million and govt own/ private big multinational company owned, can be percentaged at 7.5%..


lastly.. kobokobo stages supervision... 1 to 2%
PropertiesRe: General Topic Thread-To Discuss Anything And Everything in Building Construction by Thenext: 12:10pm On Oct 27, 2020
I need one firstly because I belief they are knowledgeable/experienced in the field and would be able to deliver a standard project. I don’t want to build a house and be seing cracks etc due to some errors which would have been captured by the Engr. during construction.
Secondly my work won’t permit me to be around all the time to monitor the mason(Baba Lati in your case �).

EgunMogaji2:
I’ve never required the service of one because I serve as my own General Contractor.

Why do you need one? Or at least on a full time basis.
PropertiesRe: General Topic Thread-To Discuss Anything And Everything in Building Construction by Thenext: 12:05pm On Oct 27, 2020
Please the stage you are talking about, are you referring to some like to DPC level, lintel level, decking level etc

raymondFirstborn:
Ok you can agree on a flat rate. Between 150 - 400k for each stage.
PropertiesRe: General Topic Thread-To Discuss Anything And Everything in Building Construction by Thenext: 7:09am On Oct 27, 2020
Thanks for your response. It’s a project of 45m according to the BOQ prepared for me by quantity surveyor.

raymondFirstborn:
Depends on the size of the project & engineers experience.
5% - 8% of the project cost.
Or the client and engineer can agree on a flat rate.
PropertiesRe: General Topic Thread-To Discuss Anything And Everything in Building Construction by Thenext: 5:30am On Oct 27, 2020
Please what’s the standard/normal pay for Engr. supervising a site. Note: it’s a kobokobo project oooo
CC:
Nx3t
Egunmogaji
Raymondfirstborn
QSfemi
Hajj M
PropertiesRe: General Topic Thread-To Discuss Anything And Everything in Building Construction by Thenext: 7:37pm On Oct 14, 2020
Thanks baba, I appreciate.

n3xt:
shocked Baba spend this thing na!

You can get 10KVA Japanese Engine for 850k (Soundproof)

‭You can reach Ikenna for that on 0706 210 3238‬
PropertiesRe: General Topic Thread-To Discuss Anything And Everything in Building Construction by Thenext: 5:08pm On Oct 14, 2020
Thanks for your response, but this ones are for big boys ooo not kobokobo like us.

n3xt:
I always patronize JMG Generators (FG Wilson Perkins UK Brands).
Not sure they have 7.5 - 10KVA but sure of 12.5KVA. That’s around #3.2m

www.jmglimited.com
Technology MarketRe: Professor On Any Type Of Generator. by Thenext: 3:49pm On Oct 14, 2020
Please I want to buy brand new Diesel engine generator within the range of 7.5-10kva, please which brand can I go for and the likely price that I can get it.
PropertiesRe: General Topic Thread-To Discuss Anything And Everything in Building Construction by Thenext: 3:32pm On Oct 14, 2020
My good people here, please I need Diesel engine generator in the range of 7.5-10kva. Please who can recommend a good brand for me with price as well.
CC
Egunmogaji
Nx3t
Kiekie
Etc
PropertiesRe: General Topic Thread-To Discuss Anything And Everything in Building Construction by Thenext: 6:03pm On Oct 07, 2020
Just exactly what someone told me. You are a blessing to this forum.

n3xt:
I hope this helps.

Pros and Cons of 0.5hp and 1hp Submersible Pump

1. Power Requirement: 0.5hp submersible pump will work even in situation where there’s low voltage. 1hp requires full current.
You can also power 0.5hp pump with a medium size generators. If you try using same generator for 1hp pump, it might burn the pump.

2. Borehole Depth: 1hp submersible pump is an overkill where the borehole depth is not more than 20m. 0.5hp will work fine in most Lagos sites. But if your depth is over 50m or even more, you’ll require a bigger pump.

3. Usage



#personalopinion #notabibeli
PropertiesRe: General Topic Thread-To Discuss Anything And Everything in Building Construction by Thenext: 11:56am On Oct 07, 2020
Thank you sir, I appreciate.

n3xt:
Best? I can’t really tell but I use Interdab submersible pump and it’s kinda reliable. Just ensure it is Copper type.

You can get between 0.5hp and 1.5hp but I think you should be fine with 0.5hp.

InterDab Pump Price (as at the time I’m typing this reply)
0.5hp Copper Coil - #52,500
1hp Copper Coil - #63,000
PropertiesRe: General Topic Thread-To Discuss Anything And Everything in Building Construction by Thenext: 9:34am On Oct 07, 2020
Please who can recommend a good/best submersible pumping machine and price as well.

CC
Rotech77
n3xt
Egunmogaji
PropertiesRe: General Topic Thread-To Discuss Anything And Everything in Building Construction by Thenext: 6:24pm On Sep 26, 2020
These one are not for kobo kobo project ooo����

rotecch77:
Oh BABA agbalagba have spoken I will post some here sir.

For those that have plan to become King in there domain like my OGA EGUN these is for you.
PropertiesRe: General Topic Thread-To Discuss Anything And Everything in Building Construction by Thenext: 3:31pm On Sep 26, 2020
Very lovely.

rotecch77:
You will find so many lovely designs in rough iron
PropertiesRe: General Topic Thread-To Discuss Anything And Everything in Building Construction by Thenext: 7:45am On Sep 24, 2020
I don’t know why people keep complaining about the said roofing that it’s too tall. I am very sure if you see it life you will not only like it but envy it. My home country house(bungalow) that I built around 2015/2016 is taller than this and no one passes by without appreciating the roofing. Infact when I completed the house and moved in then, a lot of passerby people do branch my house to appreciate the house especially the roofing.

Godisgreatest1:
Wonderful! Oga the roof is taller than the building. The owner can just add stair case and live in the roof.
PropertiesRe: General Topic Thread-To Discuss Anything And Everything in Building Construction by Thenext: 8:41am On Sep 21, 2020
I just like this forum, one keep learning new things everyday. I appreciate you guys here-Brabus, rotech77, Egunmogaji, michlin etc

BrabusNG:
I did a project here and we were looking at spending about N15m in 2015 to import fortified glass only. We will fabricate the frames here.

I told the client “There’s no sense in this no matter how hard you try to convince me. We want to put a N20m window in a house where we used N150 naira block.”

That was the end of the story!
Jobs/VacanciesRe: OilandGasJobs Recruitment 2020 by Thenext: 8:31pm On Sep 19, 2020
NNPC accept ND or HND as technician or operator.

leks4sure:
Sir, I'm telling you their policy.

No top FG agencies including those under ministry of petroleum resources accept HND even if it's a distinction grade. You must have master's degree with the HND to get job there.

NCDMB and NNPC have the same requirement.

Let's stop deceiving ourselves. I'm only stating the fact.

For GT, if you've have second class lower or HND without a Master's degree, the chances are very very slim. It may sound brutal but I needed to clarify the policy.
Jobs/VacanciesRe: OilandGasJobs Recruitment 2020 by Thenext: 8:29pm On Sep 19, 2020
Those your friends must be working as a technician or operator but not as an Engr.

electof:
Your first paragraph is nothing but pure lies.

You saying it with this confidence.makes it more surprising.

I have friends every in the oil industry that got the job with HND only.

Let me list the oil companies for you...

Shell, Total, Schlumberger and many of them in NNPC.

This is a public forum... You should be mindful of rumors you are stating as facts.
PropertiesRe: General Topic Thread-To Discuss Anything And Everything in Building Construction by Thenext: 3:17pm On Sep 15, 2020
Thank you oga. For the omonile, I don’t think I may experience that as my land is inside Estate. I bought the land from a company selling the estate land.


n3xt:
Just like rotecch77 advised above, kindly set aside N5 - N5.5m for the project (foundation to first floor slab level)

God is your strength!

______
You also need to work with the locals (mouthed ones grin) to manage the mainland boys. Their own percentage is non-negotiable.

My eyes see a lot in Bariga and Akoka
PropertiesRe: General Topic Thread-To Discuss Anything And Everything in Building Construction by Thenext: 12:24pm On Sep 15, 2020
Thank you sir oga roteccch77.

rotecch77:
To get real fact figure building plan is necessary here.
But to safe time and since you only needs Likely cost here we go.

Things to consider
- Rapid increment in cost of materials presently
- your site location (mainland) a lot of street urchin (omo-aye) demanding payment from all angle.
-Size of the building.

Based on experience you can budget btw 3-3.5m for the foundation
Then budget 2-2.3m for the block work to the decking stage.
PropertiesRe: General Topic Thread-To Discuss Anything And Everything in Building Construction by Thenext: 12:23pm On Sep 15, 2020
My oga well appreciated. I am just trying to gather data before embarking on the journey so as to have a smooth ride.

n3xt:
Based on the attached, we used:


Foundation Work

60 tons of Granite (up to DPC level)
3 Sharp Sand (20 tons)
27 trips of filling sand
16 lengths of 16mm for the starter column
8 dozen of 7 by 7 ring (10mm)
15 lengths of 12mm for column base
1 ton of 10mm rod (DPC)
20kg DPM
1/2 bundle of binding wire
1850 blocks (due to the topography of the land)
110 bags of cement (all ground works incldg DPC)
30 pcs of 1 x 12 planks
First fix pipe work (mechanical)

Labour Rates (Foundation only)

Sandfilling 3,500 per trip
All ground works (Excavation, Blinding, Block Work, Iron Works, Formwork, Surface Treatment, DPC casting) - 440,000


Budget: N2.5m for the foundation work (minimum)



Ground Floor (to first floor slab level)

3700 blocks (Headroom is 3.5m in some room)
80 bags of cement
30 tons of sharp sand
15 tons of granite
40 lengths of 16mm rod (1 length divided to 3 pcs)
27 dozen of 7 x 7 ring (10mm) for lintels/columns
**Formwork was rented at this stage.
Rough-in pipe work (Mechanical)

Labour Rate (Ground Floor only)
All works (Block work, Carpentary, Iron Work, Casting) - 380,000
Formwork Rental - 150k

Budget: N1.8m for this stage of work (minimum)
_____
Note:

- Blocks were produced at this stage by NextHome onsite at N150 per block (using stonedust)

- Formwork rented was also used during the slabwork. Total amount spent on Formwork Rental (including slab and upper floor) on the project is 520k

- Due to the slope, the foundation depth is 1.6m deep in some area and 1m deep in others.

- Building size is less than 260sqm so I encourage you to keep some change in reserve.

Pic 1&2: Foundation Work
Pic 3&4: Formwork installation (before and after casting)
PropertiesRe: General Topic Thread-To Discuss Anything And Everything in Building Construction by Thenext: 10:01am On Sep 15, 2020
My oga, I have an upcoming project to be commenced soon and similar to the earlier posted, though mine is 4 bedroom duplex with 3 bedroom flat.

The total land measured 650sqm while the building area is 350sqm. Please like how much i should budget for this project from - Blinding, Foundation Wall, DPC, Ground Floor Blockwork to Columns/Lintels to make it ready for decking.

NOTE: Location is lagos(mainland) and the land is dry.

Thanks in advance.
CC
rotech77
Dennis 3D


n3xt:
oseiwe


kindly assist see if this looks OK, I want to give the go ahead. any modifications?

My response in Red. Pls this is just my unsolicited opinion on the quote. It’s not bible.

pic isn't attaching.

This estimation is for 2bedroom and 4bedroom duplex to decking level
Does this include the foundation cost or just the cost of work from foundation to lintel?
If I get you right, you’re building a 2 bedroom and a 4 bedroom duplex. Am I right?

If the answer is yes to the above, the estimate is too cheap to build anything worthy.


2500pcs of blocks (200 * 2500) = #500,000
2500 blocks can never finish 2 bedroom and a 4 bedroom duplex whether you’re building from DPC level or starting from the ground up. You’ll need more block. N200 per block is a good deal!

60bags of cement (2700 * 60) = #162,000
If these will be used to take care of the following:

- Blinding
- Foundation Wall
- DPC
- Ground Floor Blockwork
- Columns/Lintels

60 bags of cement won’t be enough even if you’re using just 2500 blocks.


15tonnes of granite = #85,000
This will work for column/lintels but not inclusive of foundation

20tonnes of sharp sand = #60,000
Maybe for ground floor blockwork and lintel. You can always check/compare prices with locals.

20tonnes of soft sand = #50,000
I don’t know about this one.

Half tonne of 12mm iron = #130,000
This is for what exactly.

If it’s Lintels/Column, it’s impossible! Beside, it’s recommended that you use a 16mm Rods for Column supporting a slab (decking)



Iron for decking
This is confusing though!

8pcs of 16mm iron (4,800 * cool = #38,400
The price is right. The quantity is impossible for whatever you’re planning.

I am stopping here until I get further clarification on exactly what you’re trying to achieve.


20lenghts of 10mm iron = #44,000

1 roll of binding wire = *#8,000*

Planks for pillar and linted*�
50pcs if planks (1400 * 50) = *#70,000*
1bag of nail = *#6,000*
Workmanship = *#350,000*
*******

For pegging
If pegging is involved, it means you’re doing foundation. Just forget about it sir! The total estimate won’t get you off ground in any part of the South West.

6pcs of somi planks (1400 * 6) = 8400*
Cutting of some planks (200 * 6) = *1200*
2 bundle of Peggy wood (2500 *2) = *#5000*
Nail = 3,000
*Total = #1,521,4000*
PropertiesRe: General Topic Thread-To Discuss Anything And Everything in Building Construction by Thenext: 7:50am On Sep 04, 2020
This forum is full of intelligent engrs., this your analysis/breakdown will surely help some of us here.

n3xt:
Estimate for 6cm 420sqm Double T Interlock

Materials for casting

No of Days: 14 Days

45 tons of stone dust
130 bags of cement (+ first layer/wastage)
50l of diesel + oil mixture @ 25,000
1 bag of pigment @ N50,000
1,000 Moulds (rentage) @ N5

Materials for laying

No of Days: 4 Days

50kg of casting leather (Nylon) @ N60,000
45 tons of stone dust
Compactor Rental (2 days) @ N15,000
5 bags of Cement @ N2600

Labour for casting, screeding & laying @ N600


Total = N1,100,000 (+/- N2600 per sqm)


*pricing varies based on location.
PropertiesRe: General Topic Thread-To Discuss Anything And Everything in Building Construction by Thenext: 8:55am On Aug 26, 2020
Thank you sir.

Dennis3D:
More like it... That range is realistic
PropertiesRe: General Topic Thread-To Discuss Anything And Everything in Building Construction by Thenext: 8:52am On Aug 26, 2020
Thank you sir.

rotecch77:
Budget 3.8-4.3m
PropertiesRe: General Topic Thread-To Discuss Anything And Everything in Building Construction by Thenext: 5:07pm On Aug 25, 2020
Good evening my Oga dem,

Please like how much one can budget for decking of 330sqm.

CC
n3xt
rotecch77
Dennis3D
Egunmogaji
PropertiesRe: General Topic Thread-To Discuss Anything And Everything in Building Construction by Thenext: 7:38am On Aug 09, 2020
Okay. But I can understand you, it will means I will pay for tax clearance at the same time I will still pay for building approval which is based on size, length etc of the building. Hope I am not getting you wrong

Oliran:
Yes, The checklist is a summary of all what is required to get your building plan approval.

The tax clearance is the last stage, approval comes out in less than two weeks after tax clearance.

That's why I asked if he was issued any letter.
Two letters will be issued to him, one stating the amount he is to pay for tax, they use the clause that the tax is not up to date thereby so so amount has been issued to him, this particular letter is from LIRS.

The second letter is from planning office, stating that without clearance from tax office (paying what was calculated from LIRS) he can't be granted the approval etc.
PropertiesRe: General Topic Thread-To Discuss Anything And Everything in Building Construction by Thenext: 7:32am On Aug 09, 2020
Thanks Oliran. Sure this really helped but sorry for my omission, the building is 4 bedroom duplex with two units of mini flats. I quite understand the stages now with your explanation below, but I guess the person that is handling it for me just wants me to get all required documents so that he can have a smooth application and approval.

But from your last sentence, it means I will need tax clearance which is what I am asking the way out since I don’t have one.

Thank you for your response so far.

Oliran:
I am sure the person ticked all what is required to get approval for you. However it is done in stages.
From your description I am guessing it's a bungalow, I'll list the stages below.

Stage 1:
Survey
Architectural drawings

The survey is charted to be sure your land is free of Government acquisition, your drawing is vetted and ensure comply with the required setback,airspaces etc.

Stage 2:
Someone from the district office will go for site visit to be sure of the size of land and confirm you've not started building if it is a proposed drawing.

Stage3:
Calculations are done using your architectural drawings to calculate assessment, the amount is depending on the size of the building (Length,Breadth and Height), the rate also depends on the location, Lekki fee is not same as Ikorodu fee. Each LGA is categorized into Low, Medium and High density.

Stage4:

After payment is done, the receipt for payment, deed of Assignment for the land, Affidavit with stamp duty and your passports with your drawings is used to open a file for you, a registration number will be issued.
The file is then forwarded to LIRS

Last Stage is the tax clearance stage.


I hope this helps. smiley