₦airaland Forum

Welcome, Guest: RegisterLoginWith GoogleTrendingRecentNew

Stats: 3,331,326 members, 8,449,783 topics. Date: Wednesday, 22 July 2026 at 10:45 AM

Toggle theme

FEGEITOK's Posts

Nairaland ForumFEGEITOK's ProfileFEGEITOK's Posts

1 2 3 4 5 6 7 8 ... 30 31 32 33 34 35 36 37 38 (of 68 pages)

PropertiesRe: The Posh 6 Flats Of 3 Bedrooms Block Of Flats In Enugu, The Construction Process by FEGEITOK: 8:50am On Oct 29, 2022
spyder880:
The only way I guarantee that my works pass integrity tests is to keep doing things the right way every time. Each building has a building plan and it should be studied and all the specifications followed. Building is a science, and there are processes to be followed to get things right.

I usually have very knowledgeable persons around each of my building sites at the critical stages of the construction, to avoid any oversize on my part. There are times we run into difficult plans, and new methods or new styles of construction, the best thing to do is to ensure that someone who is an expert with that type of work comes around to supervise that part of the project.

Forget governments building control task force or staff, they may never visit your site after you pay them, the onus then lies on you to use the best building methods and observe every good building process in making sure the building comes out perfect.

Every builder is only as good as their last job, so I will love to be remembered for a well built, beautiful house, that's the only way I can guarantee myself of more projects.

You can measure your builder by hiring another professional to appear on site at intervals to monitor the processes and report the results to you.
I watched a YouTube video; a guy was modifying the garage entrance by building a new concrete driveway and the local government sent someone to supervise the works down to the concrete mix.

So why won't we have buildings collapsing here?
PropertiesRe: General Topic Thread-To Discuss Anything And Everything in Building Construction by FEGEITOK: 8:36am On Oct 29, 2022
sethtsadopp:
??
Does he have a tile cutter machine?

the motorized one not the manual one?

That is if you are a person that is fastidious.

PropertiesRe: General Topic Thread-To Discuss Anything And Everything in Building Construction by FEGEITOK: 8:00pm On Oct 28, 2022
Successbay:
Yours is better sir..

I paid someone on this thread #820,000 to do a job based on previous work relationship and on trust...since August...

Till today he has not done 10% of the job, he is nowhere to be found and he keeps promising today, tomorrow etc.. Just cos I never knew his office..met him here on NL

You can try his number again to go check on him at the hospital if he picks..or try him with a different number..

All will be fine.
I bought several TVs valued at almost 3 million Naira from a Nigerian I never met. I was attracted by his pricing and his professionalism. I chatted with him, he sent me a professional invoice, I conducted OSINT investigations into his name, phone number, email addresses and company names (previous and current) and then went ahead and he delivered.

I hope you have not just his name and number but also the entity or entities that he uses to do business.

It will help you recover your funds when you finally decide to take action.

I am sorry for your disappointment with doing business with Nigerians online, but I can guarantee you there are several good eggs you can do business with online.

You might just need to do a little more vetting before committing funds.

Busy people just don't have the time to personally visit offices of everyone they intend to do business with.
PropertiesRe: General Topic Thread-To Discuss Anything And Everything in Building Construction by FEGEITOK: 2:04pm On Oct 23, 2022
I respectfully disagree with you, Ericko2K2 and Mavverick.

Regardless of situation (garages and generators), there should be a working smoke detector at the entrance of each sleeping area.

Carbon Monoxide sensors should be located at an approved diameter.

In my city it's the law, for a purpose, and I actually have a detached garage.

Combining both detectors to me is the benefit of technology, which I cuddle.

There's a reason why we have one of the shortest life expectancy in the world.

Oh I'm also adding a radon detector but that might just push you guys off the ledge so I'll STFU about that grin
Only 5 mentions of the gas radon on this forum.

Why is that?

The video below demonstrates how they do it in other climes.


https://www.youtube.com/watch?v=wc7JWNnQw5Q&ab_channel=360Construction

As I attempt to repair the source of the mold and mildew and damp, I have stripped the house to its foundation and now I am considering adding something like the above before doing the new german floor
PropertiesRe: General Topic Thread-To Discuss Anything And Everything in Building Construction by FEGEITOK: 10:10am On Oct 20, 2022
GloriousGbola:
i advise you buy as much as you can, because i dont think the new owners of shoprite plan on continuing with hardware supplies.
once the stock is gone, i think it will be gone forever
I'll clear the shelves then.

Thanks so much.
PropertiesRe: General Topic Thread-To Discuss Anything And Everything in Building Construction by FEGEITOK: 9:53am On Oct 20, 2022
FEGEITOK:
There is an update on the above.

If you want to prevent off-gassing, you need to use low VOC wood glue when doing woodwork.

Here is an article from an architectural website that goes into detail about the problem.

It is important for service providers to also play the role of trusted advisors, when they do this, telling the client the pros and cons of certain buying decisions, a bond of trust is formed that allows the client to have no objection to paying more for the service provider and trusted advisor roles.

But the client doesn't get this from the service provider and has to do the kind of work that I have done to guarantee health and safety, such a service provider becomes disposable/dispensable.

I hope this helps someone else commissioning woodwork in the office or the home.

Thank God for Shoprite, I am now using a low VOC wood glue known as Alcolin wood glue. I am saying thank God because our wood markets don't source for this type of glue, and the next best option would have been to import it from Amazon which would take time.

Once again this illustrates how important proper ventilation is for the home and the office.
Low VOC adhesive at Shoprite

Satellite TV TechnologyRe: Solar Energy, A Complement To FTA by FEGEITOK: 11:57pm On Oct 19, 2022
Sapiosexuality:
Guys, say I'm trying to do a 24hr solar source for about 600W or 1000w, would that be possible with a budget of 350k?

The total load is actually about 515 but I'm trying to raise it to 600 or 1000w (depending on cost). Is the budget enough for 600w and 24hr? If not, what can I can with that budget? Thanks.
Inverter and battery? Yes
Solar Panels, Charge Controller, inverter, batteries? Maybe, depending on the brand

But it has to be a DIY as there is little room for profit so heavy weight installers will look past this request
PropertiesRe: General Topic Thread-To Discuss Anything And Everything in Building Construction by FEGEITOK: 11:47pm On Oct 19, 2022
Nigerian Building Efficiency Code III

PropertiesRe: General Topic Thread-To Discuss Anything And Everything in Building Construction by FEGEITOK: 11:46pm On Oct 19, 2022
Nigerian Building Efficiency Code II

PropertiesRe: General Topic Thread-To Discuss Anything And Everything in Building Construction by FEGEITOK: 11:43pm On Oct 19, 2022
By the way I just ran a search and found zero reference to the Nigeria Building Energy Efficiency Code on this forum as a whole and the property subsection in particular

Satellite TV TechnologyRe: Solar Energy, A Complement To FTA by FEGEITOK: 8:57am On Oct 19, 2022
NiyiOmoIyunade:
So Morningstar had Modbus TCP support, embedded webserver, email and triggered alert functionality and so on bundled into their CCs at least 10 years ago.

It is just that their target market was more of industrial and engineering and dealing with the complexity needed to use those features was normal for those environments - the users had the required technical background and rigor to use the tools without trouble.

Victron appears better because they open sourced their own development and thereby made it easy for hard core technical people and normal users and DIYers to collaborate and leverage on each other's work.
In other words they were Industrial Control Systems (ICS) compliant way way back.

To be honest with you. I am beginning to realize that taking some time to understand the market before investing is paying off. I know the power of Modbus and this is capability is important to me.

The way it is going, I might end up not getting the Schneider.
Satellite TV TechnologyRe: Solar Energy, A Complement To FTA by FEGEITOK: 8:55am On Oct 19, 2022
olopan:
Good morning Guys, i will be hosting a Twitter space on saturday, it is basically a how to guide/education on what to expect, what frame of mind is needed before shelling out some cash to avoid mistakes of having an improperly designed solar system.

I hope to see some of us that may be chanced to grace the event and share their thoughts so that everybody pick a few newer ideas to take away.

I will be joined by Sintolord, trippledot and bigbrovar on the space.

Don't miss out! See you this weekend, Don't forget to set your reminder.

Link to Join Below

https://twitter.com/i/spaces/1dRJZMovewgGB
Thanks for this.
Satellite TV TechnologyRe: Solar Energy, A Complement To FTA by FEGEITOK: 8:55am On Oct 19, 2022
Still looking for the comparison with Victron

PropertiesRe: Is It A Bad Practice To Fill The Holes In Foundation Block-Works With Laterite? by FEGEITOK: 5:38am On Oct 18, 2022
bewildered:
Bad idea. Instead fill them up with stones or broken bricks.

Laterite could accommodate moisture and weaken the block in the long run.
PropertiesRe: Is It A Bad Practice To Fill The Holes In Foundation Block-Works With Laterite? by FEGEITOK: 5:37am On Oct 18, 2022
Charisdesigns:
It is a wrong practice

when it comes in contact with ground water through seepage it causes damp walls, hence growth of algae on your walls.


Because of it geological composition, it is prone to swell hence causes your wall to crack, which is a ripple effect of expansion within the block wall.

It also contains organic materials that deteriorate, which in turn causes shrinkage thus weakening the block walls, still resulting to crack walls


Recommendation, If you most fill your foundation hollow block, please do so with weak concrete.
PropertiesRe: Is It A Bad Practice To Fill The Holes In Foundation Block-Works With Laterite? by FEGEITOK: 5:35am On Oct 18, 2022
Nauttyprof:
No Sir, it is bad.

It will aid capillary rise in water or moisture and also weaken the block in the long run.

Mass concrete is preferable to fill the block holes in foundation.
PropertiesRe: Is It A Bad Practice To Fill The Holes In Foundation Block-Works With Laterite? by FEGEITOK: 5:32am On Oct 18, 2022
danduchi:
From a geologist point of view, laterite contains mineral like montmorillonite, illite or smectite.

Laterite with montmorillonite tends to swell when in contact with water or moisture and shrinks back when dry. So to avoid cracks on your buildings, do not fill in with laterite, rather use granite or broken blocks
PropertiesRe: Is It A Bad Practice To Fill The Holes In Foundation Block-Works With Laterite? by FEGEITOK: 5:32am On Oct 18, 2022
blaise26abj:
It is wrong .

Lean or weak concrete mixed with water seal additives should be used to fill instead of laterite.

This is recommended for areas with high tendency for capillary movement of water .


It is the reason lower parts of both internal and external walls have serious water damages and people tend to use tiles to cover up .
PropertiesRe: Is It A Bad Practice To Fill The Holes In Foundation Block-Works With Laterite? by FEGEITOK: 5:31am On Oct 18, 2022
lonesome501:
It's practically something everyone ((bricklayer or laborer)) does when filling the building foundation,,and the reason for that is because it's the cheapest way...

the best and costly way is to fill the blocks holes with concrete ((cement,sand, granite)),,so as to prevent the water that would be filling the blocks holes when rain falls from traveling down to damage the foundation blocks

,,JUST MY OWN OPINION
PropertiesRe: Is It A Bad Practice To Fill The Holes In Foundation Block-Works With Laterite? by FEGEITOK: 5:30am On Oct 18, 2022
HOLAROCKDAY:
The picture you attached didn't explained your question instead you are only showing us A pad footing foundation base with it starter bar.

The reason why hollow block are been fill is to prevent upright movement of water into our foundation "Capillary water" which reduced the strength of the foundation. In many cases, it caused dampness on the building wall.

Has you have said earlier if a chain beam can't be provided, the best to do is fill in the hollow block with weak concrete.

And it is always best you provide DPC with good Damp proof membrane on your foundation to avoid story that touch later in the future.

My own 2 Kobo
PropertiesRe: Is It A Bad Practice To Fill The Holes In Foundation Block-Works With Laterite? by FEGEITOK: 5:29am On Oct 18, 2022
ArchyDesmond:
...
There is a reason why the block is a hollow block.

Filling the block with laterite will always make your internal wall damp.....weaken ur foundation and eventually collapse the wall.


You can only fill with a solid concrete not laterite
PropertiesRe: Is It A Bad Practice To Fill The Holes In Foundation Block-Works With Laterite? by FEGEITOK: 5:29am On Oct 18, 2022
agent01:
It is wrong to fill foundation hollow blockwork with Laterite.

Lean mix concrete should be used because it adds to the structural strength of your foundation and also a measure to prevent horizontal dampness.

It will be a bad practice to use Laterite. It cannot replace the use of lean mix concrete to fill solid in hollow blockwork.
PropertiesRe: Is It A Bad Practice To Fill The Holes In Foundation Block-Works With Laterite? by FEGEITOK: 5:28am On Oct 18, 2022
enambobo:
The aim of grouting the block walls is to strengthen the foundation walls and offer better stability to the structure.

Hence preventing the percolation of water from the site area into the the foundation itself. Laterite offers negligible strength and zero restraints to the percolation of water. It is therefore not a suitable material for that purpose.

Also, using laterite increases the susceptibility to termite attack which in no distant time will affect the integrity of the structure. It is therefore best practice to use light concrete as a grouting material.
PropertiesRe: Is It A Bad Practice To Fill The Holes In Foundation Block-Works With Laterite? by FEGEITOK: 5:27am On Oct 18, 2022
Reference:
They should not be filled with anything. The reason why hollow blocks are sometimes used in foundations is to present a moisture barrier between the soil surrounding the building which can get very moist under rainfall and the materials used in filling to grade which should remain stable.

Laterite which is a derivative of clay compounds has distinctive properties of water affinity. It attracts and bonds to water easiily and thus will cause two undesirable effects.


First, it will increase in volume and place tensile stresses within hollow block structure degrading its lifespan.


Secondly, it will act as a capillary to transmit moisture into the foundation leading to the degredation of the fill material.


Where foundations have to be reinforced to provide retention concrete is the best material for that purpose however alternative waterproofing regimes should be provided to protect the fill.
PropertiesRe: Is It A Bad Practice To Fill The Holes In Foundation Block-Works With Laterite? by FEGEITOK: 5:26am On Oct 18, 2022
Aforxzy:
Laterite is a very fine soil material that contains alot of clay. It is not permeable and has very high water retaining capacity.

Most foundation with sancrete blocks are filled with lean concrete to make the foundation wall stronger, resist water seeping into the foundation and also counter the effect of the earth pressure on the wall.




Is there anything wrong in filling the holes of the foundation block-works with the laterite soil while the filling of the foundation was going on.??
..
In fact, what exactly is the main reason why the holes in the foundation block-works are being blocked-off during the filling of foundation with Laterite??
..
I really need to know the reason.
I need to learn this.
PropertiesRe: Is It A Bad Practice To Fill The Holes In Foundation Block-Works With Laterite? by FEGEITOK: 5:25am On Oct 18, 2022
highoctane:
What prevents you from using solid blocks, it depends on the type of building, for a building not more than 1 floor 9inchs solid blocks is appropriate, bungalows can accommodate 6inhs solid block


Your foundation concrete Insitu should be allowed 21 days to harden or cure before laying any blocks.

In water log area or any other earth situation, the 1st to 4th foundation block coaches will be laid flat, convince the owner why it necessary to do this instead of standing.

This will prevent cracking as the building took the full weight of the roof.

Most importantly the foundation concrete must be allowed to cure, cake or harden for 21 days or more during raining periods.

But you didn't state the kind of structure you erecting
PropertiesRe: Is It A Bad Practice To Fill The Holes In Foundation Block-Works With Laterite? by FEGEITOK: 5:24am On Oct 18, 2022
randomme:
The idea of filling block holes is to give the foundation stability, and reduce moisture in the block while water capillary is high.

However, this should only be done using weak concrete of ratio 1:4:8.

Using laterite to fill the hole is a bad practice because the laterite will cause your wall to damp and your finishing (plaster, painting, tiles) will start falling off within a short time.
PropertiesRe: Is It A Bad Practice To Fill The Holes In Foundation Block-Works With Laterite? by FEGEITOK: 5:23am On Oct 18, 2022
GodsOwn2004:
It is a very bad practice, the ideal thing to do is to fill the hollow blocks with lean concrete.

Foundations are critical element of any building structure.

Capillary action and algae growth, damping, etc poses negative impact on structural stability, serviceability, strength and aesthetics of a building structure.
PropertiesRe: Is It A Bad Practice To Fill The Holes In Foundation Block-Works With Laterite? by FEGEITOK: 5:22am On Oct 18, 2022
adanny01:
As a Civil Engr, there is one reason i have deduced for this norm in our building industry.

Structurally, its just to increase compressive strength of the foundation wall.

Usually, any building which has no columns transmits its entire load through the walls. It is also expected that the load increases from the top to the bottom of the wall. Therefore, the foundation walls bear the entire dead and live loads of the building's superstructure. Note that the foundation walls carries more load than the superstructure walls. Also, the foundation walls experience more deterioration due to dampness, wetting, drying and even chemical contents of the soil it is constantly in contact with.

In a bid to make the blocks of the foundation stronger, it is filled with lean concrete. Concrete is good in compression so by filling the block holes, the foundation walls will bear more load and the likely hood of failure is greatly reduced.

However, in practice, most builders don't actually fill the block holes as recommended. Some put broken blocks, boulders and like you said soil. These actions completely defeats the purpose of block hole filling. Putting laterite in block holes is worse than leaving it empty. Soil or laterite will encourage damping due to capillary action.

Block hole filling becomes very important in blockwork drainage where an access slab is placed for vehicle access. Sometimes you find these blockwork reinforced. Imagine the weight of a 30ton dumper truck over block work, if no concrete filling in the blocks, if the slab doesn't fail, the blocks under the slab will crush due to excessive compression.
PropertiesRe: Is It A Bad Practice To Fill The Holes In Foundation Block-Works With Laterite? by FEGEITOK: 4:46am On Oct 18, 2022
Nauttyprof:
There is a great wrong in this. You are[b] giving these block high moisture content as the block will now be faced with external moisture content from surrounding soil and internal capillary rise in moisture as a result of the laterite used in filling the blocks.[/b] This is a high risk for the block and its strength.
Block High moisture content from internal and external sources.

External: surrounding soil
Internal: Capillary rise in moisture content from laterite in the blocks

Wrong Building practices that lead to damp walls.
PropertiesRe: Is It A Bad Practice To Fill The Holes In Foundation Block-Works With Laterite? by FEGEITOK: 11:23pm On Oct 17, 2022
Slimszy read all of this thread
PropertiesRe: General Topic Thread-To Discuss Anything And Everything in Building Construction by FEGEITOK: 10:47pm On Oct 17, 2022
FEGEITOK:
The first time I fought damp walls, I took down the old plaster from the floor to the midway point between the floor and the ceiling in all the rooms of the house. Then personally supervised a cement mix in the following formula

1 part cement to 3 parts stone dust to 2 parts sharp sand and 1 part plaster sand.

Five years later there is no evidence that the house was not properly built, the paint no longer pealed, and anyone workman who has worked on that part of the house said, the plasterwork is like concrete.

I also added a water proofing powder whose name I cannot remember since it is more than 5 years ago.

By the way this was internal not external walls.

I must admit the walls were not smooth. But screeding or another layer of plaster with a different mix can easily resolve that. I later screeded it to make them smooth.
Slimszy

1 2 3 4 5 6 7 8 ... 30 31 32 33 34 35 36 37 38 (of 68 pages)