PropertiesRe: DIY: Construction Of 3 Units Of 4-bedrooms Terraces [Surulere-I] by BITSWORKS(op): 6:50am On Jan 07, 2016
Work still ongoing on the interlocking stones, the ground has been compacted and polythene has been laid on it, and after that sharp sand will be laid on the polythene.

PropertiesRe: DIY: Construction Of 4 Units Of 2-bedrooms Terraces [Ikorodu-I] by BITSWORKS(op):
Perimeter wall is also ongoing, we will be taking it up to 12 coaches. We are using 6inches block and will be using the block to brace the wall at 3m intervals to act as columns. This is a cost saving measure once the soil is good.

PropertiesRe: DIY: Construction Of 3 Units Of 4-bedrooms Terraces [Surulere-I] by BITSWORKS(op): 3:54pm On Jan 04, 2016
We are currently testing the eletrical wiring and fittings (switches, sockets, light fittings) to ensure all lights fittings and switches are in sync an ensuring there's no bridging on wires.

The change-over switches have been fixed and the electrical armoured cable has been buried and connected to the PHCN pole.

PropertiesRe: DIY: Construction Of 3 Units Of 4-bedrooms Terraces [Surulere-I] by BITSWORKS(op): 2:24pm On Jan 04, 2016
lafolabi:
Well done brother, please how much is interlock Tiles per square meter in surulere area. Thanks.
The one we are using was moulded on request and its N1300/sq.m and I believe that's the prevailing price, but moulding it on request guarantees the quality and strength.
PropertiesRe: DIY: Construction Of 4 Units Of 2-bedrooms Terraces [Ikorodu-I] by BITSWORKS(op): 2:17pm On Jan 04, 2016
The size of the septic tank is 11ft x 11ft x 11ft while the soak-away is 5ft x 5ft x 6ft. We used 6inches block for the soak-away and will be using 9inches block for the septic tank.

The cost incurred as listed below

1. Digging - N40,000
2. Blockwork, flooring, plastering, reinforced slab cover, columns - N80,000
PropertiesRe: DIY: Construction Of 4 Units Of 2-bedrooms Terraces [Ikorodu-I] by BITSWORKS(op): 2:08pm On Jan 04, 2016
Septic tank and soak-away work currently ongoing. Running this works simultaneously will help reduce total project timline.

PropertiesRe: DIY: Construction Of 4 Units Of 2-bedrooms Terraces [Ikorodu-I] by BITSWORKS(op):
Septic tank and soak-away digging and blockwork is also ongoing.

PropertiesRe: DIY: Construction Of 4 Units Of 2-bedrooms Terraces [Ikorodu-I] by BITSWORKS(op): 1:40pm On Jan 04, 2016
First floor block work has started in earnest and we will be casting the columns and lintels this week.

PropertiesRe: DIY: Construction Of 4 Units Of 2-bedrooms Terraces [Ikorodu-I] by BITSWORKS(op): 1:28pm On Jan 04, 2016
sako28:
Please include material details for the decking.

Thank you
For the first floor suspended floor casting, these are the materials we used

1. 1nos trip of 20tons 3/4 down granite
2. 3nos trip of 10tons sharp sand
3. 80 bags of cement

The casting was done by a team of 16 people and they started at 9:30am and finished by 4:00pm.
PropertiesRe: Land On The Mainland (young Mum) by BITSWORKS: 4:48pm On Jan 03, 2016
Ikorodu is a good choice if you are ready for the long ride to-and-fro the mainland or you are an entrepreneur. You can get land in Ikorodu between N2million to N10million in good locations that are not too far from the major roads (you can get cheaper in some locations too but they might not be your choice).

I know some locations I can ask you to check out which are quite reasonable and have good access roads. Yes, am a architect/builder but am more of an entrepreneur.
PropertiesRe: Land On The Mainland (young Mum) by BITSWORKS: 4:03pm On Jan 03, 2016
Hello, you can get a plot of land in Surulere with an existing property that you can demolish and build on. Budget between N15million to N25million based on accessibility if Surulere is your thing. Getting a plot of land in an estate on the mainland will not come cheap. If you have another location in mind, let me know.
PropertiesRe: DIY: Construction Of 3 Units Of 4-bedrooms Terraces [Surulere-I] by BITSWORKS(op): 5:17pm On Dec 30, 2015
Interlocking stone work in progress, they are taking levels and compacting the ground for the sharp sand and dpm. The ground has already been treated with anti-fungi.

PropertiesRe: DIY: Project Management/Supervision Of Commercial Development [ogbomosho] by BITSWORKS(op): 6:59pm On Dec 22, 2015
Baseplate foundation footing for the marquee is also in progress, the consultant contracted for the marquee is a brilliant guy and took his time in making sure all the baseplates align properly before we did the casting.

PropertiesRe: DIY: Project Management/Supervision Of Commercial Development [ogbomosho] by BITSWORKS(op): 6:29pm On Dec 22, 2015
Site visit to Ogbomosho on the 9th - 12th of December. Windows have been fabricated in Lagos and transported down to Ogbomosho. Installation of both casement and sliding windows in progress.

PropertiesRe: DIY: Construction Of 4 Units Of 2-bedrooms Terraces [Ikorodu-I] by BITSWORKS(op): 8:58am On Dec 22, 2015
First floor suspended slab has been casted and blockwork will be starting soon. Pictures will be uploaded ASAP.
PropertiesRe: DIY: Construction Of 3 Units Of 4-bedrooms Terraces [Surulere-I] by BITSWORKS(op): 8:55am On Dec 22, 2015
lafolabi:
Nice kitchen cabinets.
Thanks for the compliment sir.
PropertiesRe: DIY: Construction Of 3 Units Of 4-bedrooms Terraces [Surulere-I] by BITSWORKS(op): 8:48am On Dec 22, 2015
External painting of the building has been done, but just one coat for now to give us a feel of what we want. Once all other external works are done, we will apply the finishing coats. The walls were screeded before painting though.

Internal painting is ongoing.

PropertiesRe: DIY: Construction Of 3 Units Of 4-bedrooms Terraces [Surulere-I] by BITSWORKS(op): 8:24am On Dec 22, 2015
@HajjM, my oga you did not even ask about your humble servant.

Finishing the project has been top priority and we thank God we are about to wrap it up for the year. Much has been achieved and I will update them seperately now.
AutosRe: 1999 Nissan Pathfinder @ 1.05m: Best Deal sold sold sold by BITSWORKS: 7:57am On Nov 25, 2015
Where can this vehicle be inspected, am offering N1million.
PropertiesRe: DIY: Construction Of 4 Units Of 2-bedrooms Terraces [Ikorodu-I] by BITSWORKS(op):
More reinforcement work pictures

PropertiesRe: DIY: Construction Of 4 Units Of 2-bedrooms Terraces [Ikorodu-I] by BITSWORKS(op): 7:39am On Nov 14, 2015
Iron reinforcement work ongoing.

PropertiesRe: DIY: Construction Of 3 Units Of 4-bedrooms Terraces [Surulere-I] by BITSWORKS(op): 8:08pm On Nov 12, 2015
Marble counter-top with sink on cabinets.

PropertiesRe: DIY: Construction Of 3 Units Of 4-bedrooms Terraces [Surulere-I] by BITSWORKS(op): 10:18am On Nov 12, 2015
More pictures of the kitchen cabinet.

PropertiesRe: DIY: Construction Of 3 Units Of 4-bedrooms Terraces [Surulere-I] by BITSWORKS(op): 7:26pm On Nov 11, 2015
Kitchen cabinet workin progress.

PropertiesRe: DIY: Construction Of 3 Units Of 4-bedrooms Terraces [Surulere-I] by BITSWORKS(op): 4:43pm On Nov 11, 2015
Staircase and terrace stainless steel balustrade in progress.

PropertiesRe: DIY: Construction Of 3 Units Of 4-bedrooms Terraces [Surulere-I] by BITSWORKS(op): 6:46am On Nov 07, 2015
The main entrance gate has been delivered and its being fixed.

PropertiesRe: DIY: Construction Of 3 Units Of 4-bedrooms Terraces [Surulere-I] by BITSWORKS(op): 6:41am On Nov 07, 2015
@drdreluv I will need to see a floor plan atleast, to be able to give you an estimate. Without a floor plan, am either over-quoting for you or under-quoting and that's risky in this construction business.
PropertiesRe: DIY: Construction Of 4 Units Of 2-bedrooms Terraces [Ikorodu-I] by BITSWORKS(op): 6:29am On Nov 07, 2015
More pictures, the staircase formwork in progress.

PropertiesRe: DIY: Construction Of 4 Units Of 2-bedrooms Terraces [Ikorodu-I] by BITSWORKS(op): 6:09am On Nov 07, 2015
Progress made so far on the first floor suspended slab in the pictures below. We are done with the platform which is ready for the reinforced iron work and the carpenter is on the staircase formwork.

PropertiesRe: DIY: Construction Of 4 Units Of 2-bedrooms Terraces [Ikorodu-I] by BITSWORKS(op): 5:58am On Nov 07, 2015
Carpentary formwork for the first floor suspended slab in progress.

PropertiesRe: DIY: Project Management/Supervision Of Commercial Development [ogbomosho] by BITSWORKS(op): 4:18pm On Oct 31, 2015
I was in Ogbomosho on the 28th of October to check the progress of work and below are the pictures, roofing of all the building has been concluded.

PropertiesRe: DIY: Construction Of 4 Units Of 2-bedrooms Terraces [Ikorodu-I] by BITSWORKS(op): 10:02am On Oct 31, 2015
Columns and lintels have been casted, getting set for the casting of the 1st floor suspended slab.