Properties › Re: DIY: Construction Of 4 Units Of 2-bedrooms Terraces [Ikorodu-I] by BITSWORKS(op): 7:36pm On Feb 18, 2016 |
firstonajobi: How much was the cables used for the wiring of this project? The total wiring cost for the 2 units is N300,000 inclusive of distribution boards, coleman wire(1.5mm, 2.5mm and 16mm), change over and others. |
Properties › Scaffolds For Rent/lease : Galvanized Steel Pipes Scaffold For Building Works by BITSWORKS(op): 7:07am On Feb 07, 2016*. Modified: 4:18pm On Oct 11, 2019 |
We have scaffolds for rent/lease to construction companies, builders, contractors and artisans. Kindly contact BITSWORKS via the following channels to book your lease. We offer competitive rates and excellent customer service.
Telephone - 08022228584 Whatsapp - 08188569130
Email - seyisodiya@gmail.com
|
Properties › Re: Own A MultipurposeMega Event Management Center Or Banquet Hall Within One Week by BITSWORKS: 2:44am On Feb 05, 2016 |
Kindly send pricing details to my email, seyisodiya@gmail.com. Thanks |
Properties › Re: DIY: Construction Of 3 Units Of 4-bedrooms Terraces [Surulere-I] by BITSWORKS(op): 2:27am On Feb 05, 2016 |
Project nearing completion and handing over. Interlocking stone concluded and we are putting the final touches to the painting and other remedial works.
Client requested we add an additional 3 coaches to the rear perimeter wall. Tiling of the external water taps.
|
Properties › Re: DIY: Construction Of 4 Units Of 2-bedrooms Terraces [Ikorodu-I] by BITSWORKS(op): 2:27am On Feb 05, 2016 |
Floor and wall tiling ongoing. Also, the electrical wiring is in progress too.
|
Properties › Re: DIY: Construction Of 4 Units Of 2-bedrooms Terraces [Ikorodu-I] by BITSWORKS(op): 3:34pm On Feb 03, 2016 |
Internal and external plastering work currently in progress.
|
Properties › Re: DIY: Construction Of 4 Units Of 2-bedrooms Terraces [Ikorodu-I] by BITSWORKS(op): 11:06am On Jan 31, 2016 |
Roof cladding with aluminium longspan in progress. The roof is splitted into two by a parapet wall and the other half will be roofed next week.
|
Properties › Re: DIY: Construction Of 4 Units Of 2-bedrooms Terraces [Ikorodu-I] by BITSWORKS(op): 9:27pm On Jan 25, 2016 |
Casting of the suspended slab over the septic tank and soak-away.
|
Properties › Re: DIY: Construction Of 3 Units Of 4-bedrooms Terraces [Surulere-I] by BITSWORKS(op): 11:36pm On Jan 23, 2016 |
adewaleID: @BITWORKS I am a fan. How can we hook up?. we can do great things together. I am open to new opportunities, you can reach me via 1. email - seyisodiya@gmail.com 2. whatsapp, BBM or telephone (to be provided via mail) I will be looking forward to hearing from you. BR |
Properties › Re: DIY: Construction Of 4 Units Of 2-bedrooms Terraces [Ikorodu-I] by BITSWORKS(op): 8:16pm On Jan 23, 2016 |
Piping works for the toilets and kitchen in progress.
|
Properties › Re: DIY: Construction Of 4 Units Of 2-bedrooms Terraces [Ikorodu-I] by BITSWORKS(op): 7:58pm On Jan 23, 2016 |
PVC casement windows fixed in place for plastering work commencing next week.
|
Properties › Re: DIY: Construction Of 4 Units Of 2-bedrooms Terraces [Ikorodu-I] by BITSWORKS(op): 6:53am On Jan 23, 2016 |
EgunMogaji: I'm indebted to you. Again.
Thank you Sir.
One question, could I engineer a sloping high ceiling? Yes you can, the number of blockwork coaches you will build will determine that. For you to achieve a high sloping ceiling, you might need at the minimum 4-6 coaches. Also the roof carcass under will have to slope like the upper one so you will need a very experienced carpenter for that. |
Properties › Re: DIY: Construction Of 4 Units Of 2-bedrooms Terraces [Ikorodu-I] by BITSWORKS(op): 8:11pm On Jan 22, 2016 |
The internal roof carcass pictures as requested, showing the blockwork.
|
Properties › Re: DIY: Construction Of 4 Units Of 2-bedrooms Terraces [Ikorodu-I] by BITSWORKS(op): 6:16am On Jan 22, 2016 |
More roof carcass work pictures.
|
Properties › Re: DIY: Construction Of 4 Units Of 2-bedrooms Terraces [Ikorodu-I] by BITSWORKS(op): 5:58am On Jan 22, 2016 |
The roof carcass work is already in progress and they will use two days to construct the roof members and 2 days to construct the noggins and 1 more day to check and tidyup.
|
Properties › Re: DIY: Construction Of 4 Units Of 2-bedrooms Terraces [Ikorodu-I] by BITSWORKS(op): 5:51am On Jan 22, 2016 |
EgunMogaji: Thanks for sharing this.
Please share a total cost to do this including labor and all materials.
Thanks.
PS: and this one group will suffice for 4 units? I have already listed the labour cost earlier and will just include the material cost/quantity. I had a lot of leftovers from casting the decking so I didn't make new purchases. 1. Granite - leftover from casting the decking but you won't need more than 10tons to cast both - N65k 2. Iron reinforcement - leftover from decking casting but you won't use more than half ton of both 16mm and 12mm (N50k budget) 3. Sharp sand - 1 trip on 10ton - N25k |
Properties › Re: DIY: Construction Of 4 Units Of 2-bedrooms Terraces [Ikorodu-I] by BITSWORKS(op): 5:36am On Jan 22, 2016*. Modified: 10:32pm On Jan 22, 2016 |
donbuchi1: Please I will be happy if my concern can be addressed...
I have a building coming up gradually, it has been decked ( suspended slab). I have about 32 pillars from foundation to decking level. And about 20 are on the perimeter of the building. While 12 make up the inside.
Question: Please do I need to continue with all 32 pillars as I go to second floor or just 20 on the perimeter. I have 2 units of 2 bedrooms down and going 4 bedroom up. The configurations obviously would change up. So pls do I still need all 32? I will advise you follow your structural drawing detailing to the letter. Construction is not a guess work profession and that is why there are specific professionals for all aspect of the stages of construction. The one you just mentioned is the most crucial one that will determine the life expectancy of that building (structural stability and load bearing capacity I mean). Except your building does not have a structural drawing and that in itself is taking too much risk with your money or your clients money. A physical inspection or structural drawing will give me a better informed view, which I can use to advise you. |
Properties › Re: DIY: Construction Of 3 Units Of 4-bedrooms Terraces [Surulere-I] by BITSWORKS(op): 9:57pm On Jan 18, 2016 |
Saintee2009: @BITSWORKS I've been a silent reader ever since i discovered your threads. its very rare to see someone this magnanimous cos am sure it isn't a child's play keeping people updated on this thread after a very long tiring day on site. I must say you've motivated and encouraged a young civil engineer like me. I would love to be a part of your team if given the opportunity. Thanks and God bless you abundantly!
PS; Did i mention i read your threads simultaneously when am chanced? I've learnt one or two things. God Bless you once again. Thank you for the good words, its great to know we are touching lives as we go along lifes journey. I got your mail and will respond to you ASAP. |
Properties › Re: DIY: Construction Of 4 Units Of 2-bedrooms Terraces [Ikorodu-I] by BITSWORKS(op): 1:27pm On Jan 18, 2016 |
EgunMogaji: I would like to see pictures of the interior of this roof if possible.
My current build is slated to use two of this and I am trying to visualize the block work on the interior.
Thanks. Okay sir, will update you once I take the pictures. |
Properties › Re: DIY: Construction Of 4 Units Of 2-bedrooms Terraces [Ikorodu-I] by BITSWORKS(op): 1:25pm On Jan 18, 2016 |
More roof blockwork pictures.
|
Properties › Re: DIY: Construction Of 4 Units Of 2-bedrooms Terraces [Ikorodu-I] by BITSWORKS(op): 5:08am On Jan 18, 2016 |
Reinforced iron work done on the septic tank and soakaway, we will be casting soon.
Wood for the roof carcass work has been delivered also.
|
Properties › Re: DIY: Construction Of 4 Units Of 2-bedrooms Terraces [Ikorodu-I] by BITSWORKS(op): 4:56am On Jan 18, 2016 |
Blockwork for the roof slope in progress. The roofing style is a single slope roof that will have roof gutters at the rear. This is a cost saving roof style for people who are on a tight budget and it can still be appealing depending on the finishing.
|
Properties › Re: DIY: Construction Of 3 Units Of 4-bedrooms Terraces [Surulere-I] by BITSWORKS(op): 8:58pm On Jan 11, 2016 |
Parking space interlocking stone concluded today with parking for 3 cars clearly marked out.
|
Properties › Re: DIY: Construction Of 4 Units Of 2-bedrooms Terraces [Ikorodu-I] by BITSWORKS(op): 3:54pm On Jan 11, 2016 |
msogunro: What is the total costof the perimeter fence? Materials and labour.
Thank you Total cost 6inches block - 1500nos blocks @ N195,000 Cement - 40 bags of cement @ N58,000 Sharp sand - 1 trip of 10tons @ N24,000 Labour - works inclusive of digging, blinding and blockwork @ N50,000 |
Properties › Re: DIY: Construction Of 3 Units Of 4-bedrooms Terraces [Surulere-I] by BITSWORKS(op): 3:12pm On Jan 11, 2016 |
Work still ongoing on the interlocking stone, we are now working on the parking space in front.
|
Properties › Re: DIY: Construction Of 4 Units Of 2-bedrooms Terraces [Ikorodu-I] by BITSWORKS(op): 2:03pm On Jan 11, 2016 |
EgunMogaji: I feel complete now that I see that the poster child's of property section used 6 inchers for fence also like me. Lol, thanks for the good words sir. On a low budget and with a good soil to support it, 6inches blocks are perfect for perimeter walls. |
Properties › Re: DIY: Construction Of 4 Units Of 2-bedrooms Terraces [Ikorodu-I] by BITSWORKS(op): 2:20pm On Jan 10, 2016 |
Usman4: Good job! If you don't mind, what's the total tons of iron reinforcement used for the first floor suspended work? In all, we bought 5 tons and here is the breakdown 1. 16mm - 1.5 ton 2. 12mm - 2.5 ton 3. 10mm - 1.0 ton We still had like 0.5 ton left of a mix of 10mm and 12mm. |
Properties › Re: DIY: Construction Of 3 Units Of 4-bedrooms Terraces [Surulere-I] by BITSWORKS(op): 7:45pm On Jan 09, 2016 |
Progress of work today on the interlocking stones.
|
Properties › Re: DIY: Construction Of 3 Units Of 4-bedrooms Terraces [Surulere-I] by BITSWORKS(op): 8:57am On Jan 09, 2016 |
Laying of the interlocking stones has started and its being design to drain water off the compound.
|
Properties › Re: DIY: Construction Of 4 Units Of 2-bedrooms Terraces [Ikorodu-I] by BITSWORKS(op): 7:35am On Jan 07, 2016 |
Lintel and column formwork in progress, we will be casting tomorrow.
|
Properties › Re: DIY: Construction Of 4 Units Of 2-bedrooms Terraces [Ikorodu-I] by BITSWORKS(op): 7:15am On Jan 07, 2016 |
Ongoing block work on the first floor, we are almost at lintel level and the formwork for the lintels/columns will start soon.
|
Properties › Re: DIY: Construction Of 3 Units Of 4-bedrooms Terraces [Surulere-I] by BITSWORKS(op): 7:04am On Jan 07, 2016 |
Sharp sand being spread on the polythene and after that it will be sprayed with water and rammed with the compacting machine.
|