₦airaland Forum

Welcome, Guest: RegisterLoginWith GoogleTrendingRecentNew

Stats: 3,331,279 members, 8,449,554 topics. Date: Wednesday, 22 July 2026 at 12:39 AM

Toggle theme

Aventures's Posts

Nairaland ForumAventures's ProfileAventures's Posts

1 2 3 4 5 6 7 8 ... 21 22 23 24 25 26 27 28 29 (of 60 pages)

PropertiesRe: Construction Tread On 6 Units Of 2 B/rm Flat At Ikorodu: Reloaded by Aventures(op): 9:45pm On Jul 11, 2014
more pics on ground breaking

PropertiesRe: Construction Tread On 6 Units Of 2 B/rm Flat At Ikorodu: Reloaded by Aventures(op): 9:34pm On Jul 11, 2014
To ease the stress of how to get water and to ensure adequate supply of water, we sank a borehole. There after we cleared the site, set out the structure according to the drawings and there after we broke the ground.

PropertiesRe: Construction Tread On 6 Units Of 2 B/rm Flat At Ikorodu: Reloaded by Aventures(op): 9:29pm On Jul 11, 2014
Just a quick flash back;
Find below some of the architectural drawings of the project

PropertiesRe: Construction Tread On 6 Units Of 2 B/rm Flat At Ikorodu: Reloaded by Aventures(op): 8:53pm On Jul 11, 2014
Project Brief:

Project description : Construction of 6 unit of 2 bedroom flats (a storey building)

Location: Ikorodu, Lagos.

Client : Nairalander in Diaspora.

Project Phase 1: Completion of the Carcass.

Budget. : =N= 11, 147, 500. 00K

Contractor : Aventures (08023142108)
PropertiesConstruction Tread On 6 Units Of 2 B/rm Flat At Ikorodu: Reloaded by Aventures(op): 8:44pm On Jul 11, 2014
Dear all,

Due to the loss of data on NL as a result of the attack. We wish to reload the tread. Kindly follow us as we do most of updating with more of pics.
PropertiesRe: Cost Of Decking A Storey Building 2 Flats 3 Bedroom by Aventures(m): 5:24pm On Jul 04, 2014
wonders shall never end!!!1.5 mill initial qoute, then your rough estimate break down was 2 M. From the break down it was evident that Segcy14 try to squeezed the bill to 1.5m and it was practically impossible. mean while the break down is not realistic. I wish the OP can give segcy 14 this job and then we use his project for practical purpose. I am saying authoritatively, in this our present economy any structure decking proposed by the OP is done with even 2 million then the occupants should never sleep with their 2 eyes closed because they are only living inside a time bomb.
Moreover, the painful aspect of this kind of qoute is that the client will have a wrong budget and midway to the project he ll now be running up and down to make up for the short fall it is not professional.
PropertiesRe: Construction Of 2 Storey Building At Osapa-lekki Ajah. by Aventures(op): 7:57pm On Jan 10, 2014
pics

PropertiesRe: Construction Of 2 Storey Building At Osapa-lekki Ajah. by Aventures(op): 7:48pm On Jan 10, 2014
More pics on iron work
PropertiesRe: Construction Of 2 Storey Building At Osapa-lekki Ajah. by Aventures(op): 9:14am On Jan 10, 2014
good am every one back to work. more details later in the day
PropertiesRe: Construction Of 2 Storey Building At Osapa-lekki Ajah. by Aventures(op): 10:32pm On Jan 09, 2014
Chekitaut: I am honored working with you, thank you sir, i accept with you 101%, now i guess everyone will accept with zero tolerance for salty sand, SAVE your HOME...Casting formula Granite+Stone dust+Cement+water all in lime-stone family. Setting of block use sand.
Sand from ogun state is equally very good but not economical when you are taking it as far as place like lekki but stone dust become cheaper. You gave us a quality and good qty of stone dust for 100k per 30 ton and to our amazement we used 2 loads for almost 65 cubic meter of concrete while we were planning to use 2 .5 loads based on our calculation from what we ve been receiving from order supplier. Now if you considered the cost of full 20 tons of ogun sand to lekki and compare with the cost of 30 tons of dust then u ll understand better.

PropertiesRe: Construction Of 2 Storey Building At Osapa-lekki Ajah. by Aventures(op): 9:53pm On Jan 09, 2014
Thanks too chekitaut for your support and service on this project. I have mention earlier on that as part of our zero tolerance for salty sand we opted for stone dust as our fine aggregate.

@Merrigold thanks for your visit to the site, i appreciate.

Now back to class. More formwork pics and reinforcement work.
PropertiesRe: Construction Of 2 Storey Building At Osapa-lekki Ajah. by Aventures(op): 11:22am On Jan 09, 2014
Meritgoal: I will be their today.
i am at the site right now conducting final check on our preparation for ground floor slab casting.
PropertiesRe: Construction Of 2 Storey Building At Osapa-lekki Ajah. by Aventures(op): 7:08am On Jan 09, 2014
Good day every one!

PropertiesRe: Construction Of 2 Storey Building At Osapa-lekki Ajah. by Aventures(op): 10:17pm On Jan 08, 2014
Meritgoal: I just notice from the picture that your site is very close to some six buildings site i roofed two months ago. I also bided for the building beside your site.
you may be right there are lot of construction site around here.
PropertiesRe: Buildng A Block Of 4 Flat As A Framed Structure. Pix, cost and challenges. by Aventures(op): 8:48pm On Jan 08, 2014
Hajj you are welcome.
PropertiesRe: Construction Of 2 Storey Building At Osapa-lekki Ajah. by Aventures(op): 8:46pm On Jan 08, 2014
The work commenced as usual with blinding along the ground beam line. In this case there was no excavation apart from trimming and dressing of the grd beam line to keep it averagely levelled.

Also while that was ongoing we received the starting material such as woods and reinforcement.

PropertiesRe: Construction Of 2 Storey Building At Osapa-lekki Ajah. by Aventures(op): 8:29pm On Jan 08, 2014
The site plan below will answer some of the question here.
mufutau55: Do you really mean 9.107m? That is only about 28 feet. Please enlighten. Thanks.
Hajji Mufutau
yes the breadth is 9.107m on ground floor, on the upper floor we have cantilever and the breadth is 11.107m.
sdacosta79: Good day Sir,
Please what is the projected construction time for this project?
Seyi
Well, like i said earlier this project has been in progress but time has not permitted me to open a tread for it, meanwhile we will be rounding up the foundation by monday. We have spent close to 2 months on the foundation. After completion of this fdn we ll have a break of 1 month before proceeding to superstructure works.

PropertiesRe: Buildng A Block Of 4 Flat As A Framed Structure. Pix, cost and challenges. by Aventures(op): 10:31pm On Jan 07, 2014
mufutau55: That's a very interesting project.. I concluded that some part for the Oga/Owner and others for rental.. So sweet and nice.
Hajji Mufutau
Yes o as the rent for 3 bedroom flat in this axis is about 1.5m, the owner is going to use the duplex and still be raking in about 6M annualy. and the site plan is such that there is no interference between the tenants and the house owner, that is the advantage of the corner piece. i will upload the site plan later
PropertiesRe: Construction Of 2 Storey Building At Osapa-lekki Ajah. by Aventures(op): 10:26pm On Jan 07, 2014
Basically the first stage of this work is foundation. The site has been sand filled for a long time adequate enough for consolidation. The foundation construction we are working on is raft with spread. The basic principle of raft design is Pressure=Force/Area. The pressure is the soil bearing pressure capacity of the soil, force is the total weight of the structure and the area is the length x breadth of the building. Now raft foundation is considered when F/A is less than the Pressure, but if F/A is greater than the pressure then you can apply what we called spread to increase the area and then still make the raft applicable (though there are some limit to this application if the spread will not work, then other foundation type is considered.)
So in this case we have a raft foundation with spread, with a high construction specification.

Some of our precautions are:
Damproof protection. DPM on the blinding before the ground beam and on the earth filling before blinding that will receive slab reinforcement.

Salt protection: We apply a zero tolerance for salt by using a stone dust as our fine aggregate (sand), we ensure that the reinforcement are relatively new and not rusty .

Reinforcement strength: Pulkit reinforcement was predominantly used (an iron rod produced in Nigeria with strenght higher than some foreign products). Reinforcement arrangement to standard curtailment to BS standard.

Concrete strength: We ensure a thorough ratio mix of 1:2:4 and also the vibration was thorough giving us an average of 5.5 bags of cement per cubic meter.

Pls pardon me for all this my grammar, i was just doing this to allow some students in tertiary institution who follow our tread to learn before we go into pictures
PropertiesRe: Construction Diary Of A Semi Detached Bungalow At Ikorodu by Aventures(op): 9:56pm On Jan 07, 2014
PropertiesRe: Buildng A Block Of 4 Flat As A Framed Structure. Pix, cost and challenges. by Aventures(op): 9:55pm On Jan 07, 2014
PropertiesRe: Construction Of 2 Storey Building At Osapa-lekki Ajah. by Aventures(op): 9:53pm On Jan 07, 2014
More details about the structure:

This building is sitting on a corner piece plot and the total dimension is 26.971m x 9.107m

The structure is a semidetached building, on ground floor we have the ground floor of 4 bedrm duplex in front and attached to it at the back is 3-bedroom flat, on the first floor we have first floor of the duplex and the second 3-bedroom flat. On the second floor we have the 3rd 3 bedroom flat on top of the duplex and behind it is the fourth 3 bedroom flat.

see the attached below.

PropertiesConstruction Of 2 Storey Building At Osapa-lekki Ajah. by Aventures(op): 9:23pm On Jan 07, 2014
You are welcome to this tread. May I use this opportunity to say thank you a million times to all our friend and tread followers, despite of our shortcomings in blogging most of our work consistently you are still there for us. Thanks so much and welcome into a wonderful new Year. I pray for you all every of your dream project shall come to reality this year in Jesus Name. Amen.

Project Description : A single 2 storey structure containing 4 units of 3 bedroom flats and 1 unit of 4 bedroom duplex with maids quarters.

Land size: A full plot of land on a corner piece.

Location: Osapa London, Lekki Ajah
PropertiesRe: Buildng A Block Of 4 Flat As A Framed Structure. Pix, cost and challenges. by Aventures(op): 12:18pm On Jan 07, 2014
esoorita: Happy new year to you Aventures, we are eagerly looking forward to your updates on your on-going project.
thanks so much the tread will come up today by God's Grace.
PropertiesRe: Buildng A Block Of 4 Flat As A Framed Structure. Pix, cost and challenges. by Aventures(op): 7:39am On Jan 02, 2014
Happy new year to all our keen follower of our tread, We wish you an uncommon favour and bountiful harvest in 2014. Thanks for all your support, advises, encouragement and love you have shown to us in previous years. With God and you we can do better in 2014 and years ahead. Have a splendid and wonderful 2014. Amen.
PropertiesRe: Construction Diary Of A Semi Detached Bungalow At Ikorodu by Aventures(op): 7:36am On Jan 02, 2014
Happy new year to all our keen follower of our tread, We wish you an uncommon favour and bountiful harvest in 2014. Thanks for all your support, advises, encouragement and love you have shown to us in previous years. With God and you we can do better in 2014 and years ahead. Have a splendid and wonderful 2014. Amen.

Meanwhile, we work all thru the festive period in other to meet the target set for us by our client. Plastering work is almost done at this site. I will get the details and pictures across later.
PropertiesRe: Construction Diary Of A Semi Detached Bungalow At Ikorodu by Aventures(op): 7:59pm On Dec 17, 2013
Junapril: My oga,
Pls permit me to do this: https://www.nairaland.com/1558301/first-nairaland-inspired-real-estate
i have actually read this on first page before seeing the link here. A wonderful idea. May The Good GOD see you through. In case you need my assistance in anyway i ll be there by God's Grace.
PropertiesRe: Buildng A Block Of 4 Flat As A Framed Structure. Pix, cost and challenges. by Aventures(op): 8:49am On Dec 13, 2013
Watch out for our new tread on a project that has kept us on our toe for a while. To avoid keeping our tread follower in suspense i deliberately decided to finish a mile stone, gather all pics and cost update before opening the tread. The project is located at Lekki, a block of 3 floor containing 4 nrs of 3-bedroom flat and 1 nr of 4 bedroom duplex with maids quarters, all in a single block on 1 plot corner piece of land.

The link will be posted here soon.
PropertiesRe: Construction Diary Of A Semi Detached Bungalow At Ikorodu by Aventures(op): 8:46am On Dec 13, 2013
Watch out for our new tread on a project that has kept us on our toe for a while. To avoid keeping our tread follower in suspense i deliberately decided to finish a mile stone, gather all pics and cost update before opening the tread. The project is located at Lekki, a block of 3 floor containing 4 nrs of 3-bedroom flat and 1 nr of 4 bedroom duplex with maids quarters, all in a single block on 1 plot corner piece of land.

The link will be posted here soon.
PropertiesRe: Construction Diary Of A Semi Detached Bungalow At Ikorodu by Aventures(op): 8:37am On Dec 13, 2013
Sorry for keeping you all on hold in respect to the expenditure so far on this project, we have been busy on other project elsewhere. Kindly find below the cost per mile stone. In case anyone is interested in having a spread sheet breakdown per milestone pls send your request to this special emai add: request.aventures@gmail.com
Pls note that this expenditure can only provide a guide other project of this magnitude may vary in cost depending on location and management and standard of work required

Milestone 1: Clearing and setting out, borehole, omo onile settlement, foundation work up to concrete capping level =N= 1,195,500

Milestone 2: Superstructure block setting to lintel level, soak away ad septic tank, laterite filling =N= 1,685,500

Milestone 3: Lintel work, 3 courses of block to roof level & partition wall up thru d roof, roof carcass and Noggins, Aluminium Covering, omo onile roof money =N=2,825,550

Milestone 4: AC conduits, internal and external plumbing work, electrical conduit, security gadget conduits, window fabrications, Burglary fabrications, internal leveling & compaction and floor concreting =N= 2,277,060
PropertiesRe: Construction Diary Of A Semi Detached Bungalow At Ikorodu by Aventures(op): 6:54am On Dec 10, 2013
Missktinz: Sent you an email from ceekaybee01@yahoo.com. Kindly respond, thanks
i have responded
PropertiesRe: The Chateau In Ile-oluji: Our Construction Journal by Aventures(m): 5:15pm On Dec 09, 2013
helpee: good step but you need to make this a general rule. Let all builders on nairaland submit their certificates for verification by moderators before seeking for job as a professional. Not just brabus but all of them...spyder, muyesky, segcy etc.
Good one! but is it possible for the moderator to also confirm the authenticity of the CV's that people will send?

1 2 3 4 5 6 7 8 ... 21 22 23 24 25 26 27 28 29 (of 60 pages)