₦airaland Forum

Welcome, Guest: RegisterLoginWith GoogleTrendingRecentNew

Stats: 3,331,319 members, 8,449,735 topics. Date: Wednesday, 22 July 2026 at 09:37 AM

Toggle theme

Saydfact's Posts

Nairaland ForumSaydfact's ProfileSaydfact's Posts

1 2 3 4 5 6 7 8 ... 23 24 25 26 27 28 29 30 31 (of 114 pages)

PropertiesRe: General Topic Thread-To Discuss Anything And Everything in Building Construction by saydfact(m): 3:21pm On Jun 26, 2020
rotecch77:
Don’t worry your self my brother, he is parading outside here as contractor and he wanted to learn instead of him to asked how it’s been done.
He is talking rubbish .

It’s not in my idea to talk this way but he trigger my anger.
i swear grin grin grin grin
but we go dey explain still
PropertiesRe: General Topic Thread-To Discuss Anything And Everything in Building Construction by saydfact(m): 1:42pm On Jun 26, 2020
tonididdy:
Jesu see client cement for ground...




You workmen... Don't be angry oh, but can you spend this much materials on your own project?

I know it's good to do a job correctly oh just asking.
lol...

Boss, thats not cement ooo - it is a mixture of cement and sand and the thickness depends on the level of the doors and the german floor levels...

cc: rotecch77
PropertiesRe: General Topic Thread-To Discuss Anything And Everything in Building Construction by saydfact(m): 1:39pm On Jun 26, 2020
megacontrol:
Words of wisdom ... #DontLeaveMe
grin grin grin grin grin grin grin grin grin grin grin grin grin grin grin grin grin grin grin dont leave me too ooooohh
PropertiesRe: General Topic Thread-To Discuss Anything And Everything in Building Construction by saydfact(m): 7:38am On Jun 26, 2020
Chekitaut:
11 still counting... you must be receiving 10tons as filling no doubt.
What people should understand about estimation is:

when an estimator says you need 40 tonnes of XYZ, the fact you paid a supplier to supply that and you end up using '60 tonnes' doesn't make the estimate wrong..

The fact is except you have a weighbridge or a GOD fearing person, you'll be supplied 10 tonnes as 20 tonnes...

I ONCE WENT TO THE QUARRY MYSELF (in 2007) to buy granite, I followed the tipper all the way to the site and delivered it to a site I was project manager on; MY CEO came to site and asked how many tonnes it was, I told him 30T.. He's a Q.S with years of experience - he said; NO! its impossible who supplied it, I said One supplier like that.

I didn't tell him it was me, cos that wasn't part of my job description...

cc: Enyinne
I'm not saying your supplier is doing that pls, I'm just explaining the challenges we estimators face.

ALL THIS ADD UNNECESSARILY TO BUILDING COST.

Morning All'
WE ARE CHAMPIONS OF ENGLAND, CHAMPIONS OF EUROPE AND CHAMPIONS OF THE WORLD. #LFC
EducationRe: What Course Can Someone With This WAEC Result Study? by saydfact(m): 10:58am On Jun 25, 2020
Renerd:
What can I study with this result.(pics attached below).

Actually, while in school I know what I was doing, I did take those subject for the purpose of studying medicine, because I love it so I purposely drop anything relating to engineering.

But after my secondary education, I had no opportunity to further my education ( being an orphan), therefore I took to hustling, and after some year, I'm now preparing to further my education. But I discovered that i cannot continue with medicine, due to the nature of my work, I won't be opportune to combine the stress of my job with the demands of studying medicine, so I am thinking of diverting.

But the problem involved is that, my result is only good for medicine, and can't be use for engineering, considering jamb requirements, therefore educationalist in the house, what course do you suggest I go for, with this result apart from medicine. (picture attached below)

Fynestboi, richiez, pls help include in featured post
consider SOCIAL SCIENCES since you're talking about engineering.
i.e Architecture, QS, Estate Management, Town Planning

you shoyld have stated your current job for better advice as it is advisable to remain in your experienced field.

Goodluck
PropertiesRe: General Topic Thread-To Discuss Anything And Everything in Building Construction by saydfact(m): 6:20am On Jun 25, 2020
decatalyst:
Good evening.

Sorry, I need someone that can assist with Architectural drawing of a 3bed in IBADAN It is important the person is in IBADAN because I would like the person to see the existing structure (window level) first.

Please quote or send me a PM. Thanks
Morning Sir.
Thanks for the offer, very well appreciated.

I won't be available in Ibadan, sorry about that.

Goodluck.
PropertiesRe: General Topic Thread-To Discuss Anything And Everything in Building Construction by saydfact(m): 6:18am On Jun 25, 2020
raymondFirstborn:
Parameters

-Young man, Labour would always cost more on a water logged land compared to dryland.

-Apart from the ground beam, you forgot to add calculation for the raft itself.
The ground beam sits on a raft.

-Apart from filling of land , what of filling of the foundation? Hardcore?

Filling of land (600mm(thick).lets say 500sqm
500 x 0.6m= 300cum x 1600 = 480,000kg/30,000
= 16trips.
16 x N60,000 = 960,000 + cost of payloader& operator N300k(Max of today's work)= N1.26m total


-Cost of labour for filling the foundation with sharp sand..
-Cost of compaction.

-What percentage did you set aside for preliminary works on the foundation?
(site storage
, borehole,
omonile,
security .etc)

-Labour would cost you more than 120k for steel works..

-Finally, there's more to building estimate, than just multiplying quantities against unit price.
Experienced builders and engineers can attest to this.

-Experience has thought me that on water logged land projects where there was no soil test done , no structural drawings. You should always Budget more for the unforseen, because so many issues would arise that has to be dealt with.
That's why I always add a percentage for contingency to all my estimates.
I called you Sir.
You called me young man..

Case closed... Levels ain't same.
PropertiesRe: General Topic Thread-To Discuss Anything And Everything in Building Construction by saydfact(m): 7:16pm On Jun 24, 2020
raymondFirstborn:
N3.5m won't finish that foundation.
What parameters did you use.

5bedroom duplex On a Waterlogged land .?

Filling of the land let's say 500sqm . With the use of a payloader and compactor.would cost at least 1m.

Filling of the foundation too@1200mm high.-11 trips of 30tonnes sharp sand.

BUDGET should be N5 - 6m.
Sir,
Rather than strike out my opinion (next time) share yours and let the OP decide which to take.

1. Building Length approx 20m, width approx 10m = volume of floor = 30m3 @ 40k / m3 = 1.2m (labour and material inclusive, rebar measured separately.

2. Approx length of ground beam = 100m, height 1.2m and thickness = 0.225mm = 27m3 = 1.08m (ditto)

3. Approx tonnage of rebar = 3.5T @ 200k = 700k + labour @ 25k per tonne = 90k = TOTAL 790K

4. Carpenter labour = 120k approx

5. lets allow 150 planks of 1by12 and a few 2x2 = 240k

ADD ALL = N3,430,000:00K

I also added that allow 1m for filling

TOTAL = 4.4Million

whatever his miscellaneous is wasn't my concern....

NOW, I'LL ASK YOU THE SAME QUESTION YOU ASKED ME:

What parameters did you use. TO GET 6M...

CC: mssiah:

i-say-d-fact
(OP only gets more accurate result if he shares his Structural drawings for height of ground beam and Rebars used)
PropertiesRe: General Topic Thread-To Discuss Anything And Everything in Building Construction by saydfact(m): 3:22pm On Jun 24, 2020
mssiah:
Is this better
Hi....
this is a ROUGH ESTIMATE using approximate values and a ground beam height of 1200mm (MINUS COMPULSORY FILLING to the footing in and out)

3.5 MILLION (send pics of the site, tag me) note: filling could be a added million.

Goodluck;

(i-say-d-fact)
PropertiesRe: General Topic Thread-To Discuss Anything And Everything in Building Construction by saydfact(m): 2:53pm On Jun 23, 2020
Looking forward to Page 1438...


Thanks to all peace makers; for we shall make heaven. grin
PropertiesRe: General Topic Thread-To Discuss Anything And Everything in Building Construction by saydfact(m): 8:01am On Jun 23, 2020
smallsmall:
Good evening professionals,

Please how many bags of cement would be needed for plastering of a room measuring 4x3.5m?

How much do bricklayer charge for workmanship for plastering?

How do bricklayer charge for flooring of a building?

Thanks in advance





What is going on here?

2-3bags? - Dennis3D
8Bags? - Sadyfact

Sadyfact, are you sure of that figure? (Four Walls of the Room.)
There is a reason a put the MIX RATIO used....
You dont expect sm1 mixing 1:8 (which is also allowed) to get same result....

ditto: sm1 mixing 1:2:4 concrete and the person using 1:3:6 OR 1:4:8 cant get same results.....

Goodluck
PropertiesRe: General Topic Thread-To Discuss Anything And Everything in Building Construction by saydfact(m): 9:00am On Jun 22, 2020
HealthCas:
Good evening professionals,

Please how many bags of cement would be needed for plastering of a room measuring 4x3.5m?

How much do bricklayer charge for workmanship for plastering?

How do bricklayer charge for flooring of a building?

Thanks in advance
8 bags (1:4 mix used)
PropertiesRe: General Topic Thread-To Discuss Anything And Everything in Building Construction by saydfact(m): 9:58am On Jun 19, 2020
gbadexy:
. Both are on WhatsApp
Thanks
PropertiesRe: General Topic Thread-To Discuss Anything And Everything in Building Construction by saydfact(m): 8:59am On Jun 19, 2020
Morning @Gbadexy

Pls I need your Whatsapp nos - thanks

Just for a chat thou
PropertiesRe: What Is Happening To My Decking? by saydfact(m): 8:01am On Jun 19, 2020
tonididdy:
Oh no of cos am not angry.
I came here for responses and I don't mind in what manner it will come.
About the structure, it's about 14sqm and consumed exactly 14bags of cement... I can't remember the ratio exactly but it was a...


1: 3: 3 or 1: 3: 4 or 1: 2: 3 ( I remember I got the ratio on here on NL, accompanied with some good engineering sites)

The wall plastering may have being of poor quality but the under decking plastering was a ratio of 1 bag to 6 or 5 buckets.

Also untop the decking before the water tanks were placed is partially tiled.

Do you think we were still highly economical?
even the most quality decking wld experience same under same condition..

1, get the tanks off it
2. get good water-proofing on
3. the decking wasn't designed (definitely) to carry such heavy dead load

Goodluck
PropertiesRe: General Topic Thread-To Discuss Anything And Everything in Building Construction by saydfact(m): 7:48am On Jun 19, 2020
jamepatrick:
I would like to start building my house next month but the problem is the weather as we all know it's raining season. The builder advised me to go ahead with the project irrespective of the weather that he's got it covered.

Do you guys think this is really possible I mean building a house(From foundation level) during this raining season? It rains almost every day in my area. Won't the cement wash out or lead to a poor foundation?

Please advise as I'm not too sure here if the guy is just looking to get paid.
Where is your area?
PropertiesRe: General Topic Thread-To Discuss Anything And Everything in Building Construction by saydfact(m): 4:16pm On Jun 18, 2020
JustCryptos:
Good day gurus in the house. Please can I get an estimate on how much will be needed to fence a half plot of land measuring 30*89 feet and an access way measuring 10*80 feet. I intend doing just 2-3 coaches above the ground.

Thanks.
https://www.nairaland.com/5818635/estimating-cost-fencing-6-plots
PropertiesRe: General Topic Thread-To Discuss Anything And Everything in Building Construction by saydfact(m): 6:02am On Jun 11, 2020
Adequate459:
Please be reminded
Shd be between 200k to 210k or 220k.

Im not too sure..
PropertiesRe: General Topic Thread-To Discuss Anything And Everything in Building Construction by saydfact(m): 8:27am On Jun 08, 2020
One4me:
We have discussed this issue before.
The fact that a Professional body issued a price guideline, does not mean that is what Customers will pay or you should charge a Customer.
It is like when the Pepper Grinder Association just wakeup one day and raise dthe price of grinding Pepper to #100, no matter how small it is.
Smart Pepper grinders recognise that if you charge too much as your association suggested, you wont get customers and you will still have to pay Association fees but the smart ones will look at your Pepper and say, 'Okay, it is small, l will take #50 for this' and before youknow it, theyhave made a lot of money while the ones still insisting on Association price, are still yawning and waiting for their first customer.

I had a similar issue with my Welder.
He said their 'Association has said anytime they go to weld anything in a Customers compound, they must charge a minimum of #5,000, no matter how small it is. Because he has been working with me for awhile, he came to do the work (just to use fire cut a Padlock that we misplaced the key. One other welder who overheard our discussion when l said l will only pay #2,000, went to report him and their Chairman came to carry his Welding Machine, just infornt of my house, as the guy was about to leave.
Well, l ensured the Chariman and his assistant got locked up and chargedfor stealing. Apart from bailing themselves, they also paid for the fiancial loss' suffered by the Welder. Now that is an extreme case, l just dont like their overbearing attitude and l was determined to remind them that joining a Union is voluntary, by law. They have left him alone since them.
Unionism should not be solely to extort the Client, all fees should be reasonable.

There are Surveyors who are smart and will do a Plot for less than #400K, l know a few and it is genuine (that is the bargaining excuse they greedy ones use, they scare the customer that if it is cheaper than what their Union prescribed, it wont be registered at Alausa! Bullsheeet). I have used them twice in the last two years.
The person requiring a Surveyor can send me a PM and l will give him numbers of Smart Surveyors who will do it for #300K/Plot.
If you ask these #400K Surveyors why it is #400K, their best defense is That is what the Institute Prescribed or that is the standard fee!
Who says it is the Standard fee and what right do they have, to impose such exhorbitant price on Clients?
Morning, how're you doing?

SurveyorGeo went as far as sharing the scale of fees..

Pls, in everything we should be fair to ourselves.

1. The surveyor's counsel is perhaps the only professional body in the the environment industry that's United and has a uniform fee anywhere in Nigeria.

2. EXCEPT THE SURVEYOR IS CHEATING, Eg back dating or producing fake documents he cannot charge less than the minimum fees shown on the scale of fees BECAUSE that's the amount he's paying to the government.

3. I'll advice you and Godisgreatest1 look at the complete scale of fees not just the screen shoot he sent, a location in Lagos could be 300k and another 400k, we have locations in Ogun at 120k and another at 300k etc.

You could easily think your surveyor would do it for 300k (an amount less than what he's required to pay to government) - How's he doing that?

SurveyorGeo was right in every word he put up there.

Lastly, at the end of the scale of fees, it then went on to define how much in range a surveyor shd be paid at different levels.... As low as 9k in some cases.

Goodluck
PropertiesRe: How To Build Your Comfortable House Earning Little (detailed) Pt 2 by saydfact(op): 8:05am On Jun 08, 2020
emy9ja:
Hello broda

Your thread is really educative and enlightening. Do keep it up for us.

Pls I want to know if there are reliable people doing terrazo floors in Edo State particularly Etsako region. If you have any pls share and the cost implications for a four bedroom apartment.

Thanks a bunch bro
Thanks boss for the good words.

Unfortunately, I do not have any contact on terrazzo... More so in Edo.

Thanks
PropertiesRe: Estimating Cost Of Fencing 6 Plots Of Land - A Nairalander's Question by saydfact(op): 8:00am On Jun 08, 2020
Madisonsqua:
Just an update to this thread and a big thank you to @saydfact for the wonderful estimation

So from your estimate, I realized it will cost around #3M - 3.5M for the 10 courses.... then I decided to kickstart it with #1M and see how far they will go with that as I'm not in the country at the moment....

So the job has been done and they were able to deliver 4 courses...this include #70k for digging and a few other settlements here and there....totalling around #50k....I believe another #1M will deliver 5 if not 6 courses as foundation wont be involved anymore.

Its single gated.....wider than a regular one,as we want to keep enough entrance for trucks when construction begins

Take note the person in charge is using direct labour and cutting the cost as he's experienced in this field.

@Saydfact, Do u think he had delivered enough with the first #1M? Because our estimation was 3k blocks but not sure if this is upto that.


Thanks for your time brother

Cheers
Congrats for progress.. This is 1m well spent... Now to the next level.

Goodluck
PropertiesRe: General Topic Thread-To Discuss Anything And Everything in Building Construction by saydfact(m): 9:17am On Jun 06, 2020
topsy23:
Also, i thank God for another successful 365days in my life

I wish myself happy birthday
congrats and Happy BornDay.
PropertiesRe: How To Build Your Comfortable House Earning Little (detailed) Pt 2 by saydfact(op): 9:12am On Jun 06, 2020
Olodapsing:
Can I compromise with the German floor thickness?
Maybe to like 75mm
The land is really a good land, we got something like the attached while digging the foundation
if I say yes, dem go query me for here oooohhhhh
lol

Fund and Quality na words and opposite - in the worst case (fund), do it.

grin grin grin grin grin grin grin
PropertiesRe: How To Build Your Comfortable House Earning Little (detailed) Pt 2 by saydfact(op): 4:41pm On Jun 05, 2020
Olodapsing:
Thanks for the swift response Sir.

German floor area = 160m²

Total Wall for plastering = 170m

So I need estimations for German floor (using 100mm thick concrete) = 70 bags of cement, 15 tonnes sand, 28 tonnes granite
Plastering materials - 30 bags, about 10 tonnes of plaster sand
Labour cost = German flr about 70k and plastering/dressing about 100 -150k

Thanks again
Share the quote you got with me, it also helps me review or modify my methodologies.

Goodluck
PropertiesRe: General Topic Thread-To Discuss Anything And Everything in Building Construction by saydfact(m): 2:12pm On Jun 05, 2020
Matracy:
Please I’m at the process of roofing and connecting my house with electrical and plumbing system. I will like someone to explain to me how water gets to the top flats in this building as I can’t see any tank towers or overhead tank.
Also what does a reverse osmosis for water treatment mean?

Thank you my NL family
Its possible with the use of booster pumps and standby electricity.. very common in High Class residence
PropertiesRe: How To Build Your Comfortable House Earning Little (detailed) Pt 2 by saydfact(op): 10:13am On Jun 05, 2020
Olodapsing:
Boss saydfact
I have been following this for sometimes now and it has really helped me a lot as I use to know the quantities of materials needed before getting quotation and it's mostly withing my calculations.

Now I got a quote that I feel it's outrageous so I need to confirm if I'm making mistakes.

Below is the drawing I'm able to get for the dimensions.

I need quote for flooring and plastering minus the wall and room marked out

Please I will really appreciate if you can help out.
Thanks
thanks for the good words and for following, can you pls help get the AREA OF FLOOR (to be tiled) and AREA OF WALL (to be plastered; in and out)

Thanks.....
PropertiesRe: How To Build Your Comfortable House Earning Little (detailed) Pt 2 by saydfact(op): 10:55am On Jun 01, 2020
YOMITEWIN:
Thanks for the prompt response, how much would it cost to roof it. It's a 2 bedroom apartment each room has toilet and a kitchen with inner balcony and corridor outside and would like to know which one is more preferable zinc,aluminium or abestos
Aluminium OR Asbestors (Zinc is not an option)

On cost - A lot more information is needed to know how much it wld cost; but budget about 800k for the job...

Goodluck
PropertiesRe: How To Build Your Comfortable House Earning Little (detailed) Pt 2 by saydfact(op): 9:07am On Jun 01, 2020
YOMITEWIN:
Thanks for your immense contribution, I'm fone with the lintel, really need to know is it compulsory I laid 3 couch on the lintel, because I want to fix POP for the ceiling instead of abestos
its better if you can or at least do 2 courses BUT the head room wld be low...

Goodluck
PropertiesRe: General Topic Thread-To Discuss Anything And Everything in Building Construction by saydfact(m): 11:20am On May 29, 2020
Muyi002:
May God Bless all the good good professionals on this thread who has provided information for free to novice and the experienced.

You guys are amazing. Continue the good job and I pray God will bless you plentifully. Ameen
Thanks Boss.... Amen
PropertiesRe: General Topic Thread-To Discuss Anything And Everything in Building Construction by saydfact(m): 8:37pm On May 28, 2020
Donoppy:
Hello everyone , I am embarking on a project which is a stormy building, a 2unit of 2 bedroom flat up and 2unit of 2 bedroom flat down
And below is the picture of the quotation I got from the builder for just labour charges to the German floor level.
Please I need your advice on how I can negotiate this.
NO1. 10k - 15k because its just blinding and shd be done in hours (does not include Iron bender work)
NO2. OK
NO3, 25K
NO4. We're talking of about 2500 blocks (l believe less) here if the design is massive; so 150k - 200k
NO5. 20k
NO6. 50K
NO7. FREE - shd be part of NO6 or done as goodwill, well 10k (2 days work)
NO8. LOL grin grin grin grin grin grin grin
NO9. If what you're using is mesh wire - 5k is OK, but if you're using 8mm rods then 15K
NO10. I don't even know how to price this, cos 150k should do the job.... (minus amount used to rent machine paid seperately)

This prices are generated using 2 bedroom flats x 2 -

TOTAL is about 550k
PropertiesRe: General Topic Thread-To Discuss Anything And Everything in Building Construction by saydfact(m): 7:28pm On May 28, 2020
Donoppy:
Hello everyone , I am embarking on a project which is a stormy building, a 2unit of 2 bedroom flat up and 2unit of 2 bedroom flat down
And below is the picture of the quotation I got from the builder for just labour charges to the German floor level.
Please I need your advice on how I can negotiate this.
Hi.. If I advice you would you listen?

1. The 1st 3 items are one, I love how he splitted it to gain more cash.

2. He's charging you to lay nylon on the floor lol.. Who does that

3. The charges are even out of this world...

NOW MY ADVICE.
Don't negotiate with him, tell him you don't need his service.

Offcourse that's my opinion, you don't have to take it BUT save this post.

Goodluck
PropertiesRe: General Topic Thread-To Discuss Anything And Everything in Building Construction by saydfact(m): 7:20pm On May 28, 2020
Jeff68:
@ Saydfact, wow! your site is very educational!!! thanks shocked can I ask, how much do you think I should pay somebody to do this work?
Thanks boss.. I appreciate..

To also encourage contractors (I'm one on other days too) -I prefer you share their quotations here OR in private and I'll advice.

Sometimes the cheaper labour isn't always the cheapest.. Thanks.

1 2 3 4 5 6 7 8 ... 23 24 25 26 27 28 29 30 31 (of 114 pages)